File #: 041286    Version:
Type: Resolution Status: Passed
File created: 1/11/2005 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 2/1/2005
Effective date:    
Title: Substitute resolution authorizing and directing the City Comptroller to transfer funds, and create the appropriate accounts for the proposed railroad work as part of the reconstruction of North Teutonia Avenue between West Ruby Avenue and West Villard Avenue in the City of Milwaukee with 80% Federal and/or State Aid under the Surface Transportation Program. (Infrastructure Services Division)
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, RAILROADS, STREET IMPROVEMENTS
Attachments: 1. Cover Letter.pdf, 2. Fiscal Note.pdf
Number
041286
Version
SUBSTITUTE
Reference
Sponsor
THE CHAIR
Title
Substitute resolution authorizing and directing the City Comptroller to transfer funds, and create the appropriate accounts for the proposed railroad work as part of the reconstruction of  North Teutonia Avenue between West Ruby Avenue and West Villard Avenue in the City of Milwaukee with 80% Federal and/or State Aid under the Surface Transportation Program. (Infrastructure Services Division)
Analysis
This substitute resolution authorizes and directs the City Comptroller to transfer funds and create the necessary accounts for the railroad work as part of the reconstruction of  North Teutonia Avenue from West Ruby Avenue to West Villard Avenue.  The Project Agreement for the project was approved by Common Council Resolution File Number 020464 on July 16, 2002.  The total railroad work for this project is estimated at $280,000, of which the City's share is estimated to be $56,000.
Body
Whereas, Common Council Resolution File Number 020464, adopted July 16, 2002, authorized and directed the Commissioner of Public Works to execute a revised Project Agreement with the Wisconsin Department of Transportation (WISDOT) for the programming and reconstruction of  North Teutonia Avenue from West Ruby Avenue to West Villard Avenue; and
 
Whereas, The Commissioner of Public Works executed the Agreement and WISDOT subsequently authorized the railroad work; and
 
Whereas, WISDOT has informed us that Federal/State funding for this project is available for construction in 2005; and
 
Whereas, It is necessary to begin processing railroad issues on this project in order to meet the scheduled 2005 construction; and
 
Whereas, It is necessary to transfer funds and create the project accounts for the railroad work of the project; now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized and directed to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project/Grant Chartfield Values for Railroad Work (Sate Project I.D. 2080-04-50, 51, 52) (Expenditure) and transfer to any of these accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor's share and local share or $5,000, whichever is greater, as follows:
 
 
 
Infrastructure Services Division
 
Project I.D. 2080-04-50, 51, 52
City Share
Account No. ST320050000
Fund 0333
$56,000
 
Grantor's Share (Non-Reimbursable)
Account No. SP032050100
Fund 0306
$224,000
 
Estimated Total
$280,000
 
; and, be it
 
Further Resolved, That the City Engineer is hereby authorized and directed to approve and make periodic payments to the WISDOT upon receipt of invoices for the City's share of costs of the above project.
Requestor
Department of Public Works
Draftor
Infrastructure Services Division
LCG:AH:amh
January 13, 2005
SubRes N Teutonia Ave RR Project.doc