Number
170020
Version
Substitute 1
Reference
151521
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,103,500 for a total estimated cost of these projects being $6,791,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $4,103,500. The total estimated cost of these projects is $6,791,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
2nd Aldermanic District
N. 60thSt. - W. Glendale Ave. to W. Lincoln Creek Dr. (North) (WT410170621) File Number 151521: Relaying water main. (Nonassessable Water Fund Budget Line 6410 -- $80,000). The total estimated cost for this project including the requested amount is $95,000. This project is anticipated to be completed during the 2017 construction season.
N. 76th St. - 290 feet south of W. Grantosa Dr. to W. Medford Ave. (SM495150084) File Number 160413: Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $169,000, Additional Funds). The total estimated cost for this project including the requested amount is $194,000. This project was completed in 2016.
4th Aldermanic District
W. Michigan St. - N. 32nd St. to N. 33rd St. (ST214170105) File Number 170019: Install traffic calming speed hump(s). (Developer Paving Fund -- $5,000). The total estimated cost for this project including the requested amount is $7,000. This project is anticipated to be completed during the 2017 construction season.
W. Michigan St. at N. 34th St. (ST214170106) File Number 170019: Install traffic calming device - speed table crosswalk. (Developer Paving Fund -- $22,000). The total estimated cost for this project including the requested amount is $25,000. This project is anticipated to be completed during the 2017 construction season.
N. Van Buren St. - E. Michigan St. to E. Wisconsin Ave. (WT410160719) File Number 151288: Abandon water main. (Nonassessable Water Fund Budget Line 6410 -- $15,000). The total estimated cost for this project including the requested amount is $30,000. This project is anticipated to be completed during the 2017 construction season.
Sewer Manhole Reconstruction (SM495170031): (Nonassessable Sewer Maintenance Relay Fund -- $485,000). The total estimated cost for this project including the requested amount is $500,000. This project is anticipated to be completed during the 2017 construction season.
N. 23rd St. - W. Michigan St. to W. Wisconsin Ave. (SM495160043) File Number 151848: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $110,000). The total estimated cost for this project including the requested amount is $122,000. This project is anticipated to be completed during the 2017 construction season.
4th, 6th and 7th Aldermanic Districts
Various locations in System 3016 (Sewer Exam Contract) (SM495160069) File Number 161695: (Nonassessable Sewer Maintenance Relay Fund -- $75,000, Additional Funds). The total estimated cost for this project including the requested amount is $622,000. This project is anticipated to be completed during the 2017 construction season.
5th and 10th Aldermanic Districts
N. 60th St. - W. Vliet St. to W. Center St. and N. 100th St. - W. Keefe Ave. to W. Lisbon Ave. (Portions in the City of Wauwatosa) (ST214170104) File Number 170022: Removing and replacing concrete curb and sidewalk ramps to meet ADA requirements, replace abutting pavement if necessary, sodding and grading. (Developer Paving Fund -- $25,500). The total estimated cost for this project (City Wide) including the requested amount is $1,900,000. This project is anticipated to be completed during the 2017 construction season.
6th Aldermanic District
N. Holton St. - E. Concordia Ave. to E. Townsend St. (WT410170695) File Number 161440: Abandon water main. (Nonassessable Water Fund Budget Line 6410 -- $45,000). The total estimated cost for this project including the requested amount is $60,000. This project is anticipated to be completed during the 2017 construction season.
N. 2nd St. - W. Garfield Ave. to W. North Ave. (SM495160061) File Number 160412: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $146,000). The total estimated cost for this project including the requested amount is $158,000. This project is anticipated to be completed during the 2017 construction season.
7th Aldermanic District
N. 22nd St. - W. Locust St. to W. Chambers St. (SM495160084) File Number 160917: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $161,000). The total estimated cost for this project including the requested amount is $173,000. This project is anticipated to be completed during the 2017 construction season.
N. 27th St. - W. Auer Ave. to 100 feet north of W. Auer Ave. (SM495160085) File Number 160914: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $32,000). The total estimated cost for this project including the requested amount is $42,000. This project is anticipated to be completed during the 2017 construction season.
N. 27th St. - W. Burleigh St. to 300 feet north of W. Burleigh St. (SM495160086) File Number 160914: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $83,000). The total estimated cost for this project including the requested amount is $93,000. This project is anticipated to be completed during the 2017 construction season.
10th Aldermanic District
N. 60th St. - W. Wright St. to W. Center St. (SM495170010) File Number 161440: Relaying sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $294,000). The total estimated cost for this project including the requested amount is $306,000. This project is anticipated to be completed during the 2017 construction season.
11th Aldermanic Districts
W. Lincoln Ave. - Union Pacific Railroad R.O.W. to S. 61st St. (Sponsored by the City of West Allis) (ST216170101) File Number 161022: Asphalt pavement resurfacing, replace curb and gutter, sidewalk, and grading where necessary. (Nonassessable High Impact Streets -- $105,000). The total estimated cost for this project including the requested amount is $125,000. This project is anticipated to be completed during the 2017 construction season.
13th Aldermanic District
W. Henry Ave. - S. 23rd St. to S. 26th St. (SM495150044) File Number 150118: Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $66,000). The total estimated cost for this project including the requested amount is $78,000. This project is anticipated to be completed during the 2017 construction season.
15th Aldermanic District
W. Meinecke Ave. - N. 19th St. to N. 21st St. (SM495160004) File Number 151288: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $159,000). The total estimated cost for this project including the requested amount is $171,000. This project is anticipated to be completed during the 2017 construction season.
W. Wright St. - N. 20th St. to N. 22nd St. (SM495160005) File Number 151288: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $130,000). The total estimated cost for this project including the requested amount is $142,000. This project is anticipated to be completed during the 2017 construction season.
N. 9th St. - W. Center St. to W. Hadley St. (SM495160054) File Number 151848: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $213,000). The total estimated cost for this project including the requested amount is $225,000. This project is anticipated to be completed during the 2017 construction season.
N. 20th St. - W. Brown St. to 115 feet south of W. Garfield Ave. (SM495160074) File Number 160589: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $1,101,000). The total estimated cost for this project including the requested amount is $1,116,000. This project is anticipated to be completed during the 2017 construction season.
N. 21st St. - W. Wright St. to 250 feet north of W. Wright St. (SM495160014) File Number 151288: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $82,000). The total estimated cost for this project including the requested amount is $92,000. This project is anticipated to be completed during the 2017 construction season.
City Wide
Large diameter sewer cleaning and taping (SM495160036) File Number 151746: (Nonassessable Sewer Maintenance Relay Fund -- $500,000). The total estimated cost for this project including the requested amount is $515,000. This project is anticipated to be completed during the 2017 construction season.
now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
Mary Dziewiontkoski/Denise Reinholtz
Nfr 11
04/21/2017