powered help
header-left header-center header-right
File #: 091433    Version:
Type: Resolution Status: Passed
File created: 3/2/2010 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 3/24/2010
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,341,000 for a total estimated cost of these projects being $4,859,300.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Fiscal Note, 2. Cover Letter, 3. Hearing Notice List

Number

091433

Version

SUBSTITUTE 1

Reference

090762

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,341,000 for a total estimated cost of these projects being $4,859,300.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $3,341,000.  The total estimated cost of these projects is $4,859,300.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

3rd Aldermanic District

 

Riverside Backup Power Generation Project (WT450088100): (Nonassessable Water Fund Budget Line 6410 -- $200,000, Additional Funds).  The total estimated cost for this project including the requested amount is $1,562,300.  This project is anticipated to be completed during the 2010 construction season.

 

4th Aldermanic District

 

E. Buffalo St. - N. Water St. to N. Milwaukee St. (WT410081012) File Number 070266: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $29,000; Nonassessable Water Fund Budget Line 6410 -- $406,000).  The total estimated cost for this project including the requested amount is $450,000.  This project is anticipated to be completed during the 2010 construction season.

 

N. 25th St. - W. Wells St. to W. State St. (SM495090071) File Number 090762: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $195,000).  The total estimated cost for this project including the requested amount is $210,000.  This project is anticipated to be completed during the 2010 construction season.

 

6th and 15th Aldermanic Districts

 

N. 8th St. - W. Hadley St. to W. Burleigh St. (SM495080036) File Number 080237: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $465,000).  The total estimated cost for this project including the requested amount is $477,000.  This project is anticipated to be completed during the 2010 construction season.

 

8th Aldermanic District

 

W. Montana St. - S. 29th St. to S. 33rd St. (SM495090096) File Number 090909: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $345,000).  The total estimated cost for this project including the requested amount is $357,000.  This project is anticipated to be completed during the 2010 construction season.

 

S. 38th St. - W. Branting Ln. to W. Mitchell St. (SM495090077) File Number 090762: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $237,000).  The total estimated cost for this project including the requested amount is $249,000.  This project is anticipated to be completed during the 2010 construction season.

 

8th and 11th Aldermanic Districts

 

S. 43rd St. - W. Cleveland Ave. to W. Forest Home Ave. (SM495090068) File Number 090762: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $308,000).  The total estimated cost for this project including the requested amount is $323,000.  This project is anticipated to be completed during the 2010 construction season.

 

11th Aldermanic District

 

W. Ohio Ave. - S. 25th St. to s. 27th St. (SM495090094) File Number 090762: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $153,000).  The total estimated cost for this project including the requested amount is $165,000.  This project is anticipated to be completed during the 2010 construction season.

 

12th Aldermanic District

 

S. 15th St. - W. Mitchell St. to W. Forest Home Ave. (SM495080032) File Number 080237: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $109,000).  The total estimated cost for this project including the requested amount is $121,000.  This project is anticipated to be completed during the 2010 construction season.

 

13th Aldermanic District

 

S. 17th St. - W. Ohio Ave. to W. Crawford Ave. (SM495090059) File Number 090194: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $664,000).  The total estimated cost for this project including the requested amount is $679,000.  This project is anticipated to be completed during the 2010 construction season.

 

S. 18th St. - W. Oklahoma Ave. to W. Euclid Ave. (SM495090057) File Number 090762: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $128,000).  The total estimated cost for this project including the requested amount is $140,000.  This project is anticipated to be completed during the 2010 construction season.

 

14th Aldermanic District

 

W. Ohio Ave. - 165 feet m/l west of S. 6th St. to S. 6th St. (SM495090075) File Number 090762: Relay storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $34,000).  The total estimated cost for this project including the requested amount is $46,000.  This project is anticipated to be completed during the 2010 construction season.

 

S. 6th St. - W. Ohio Ave. to W. Euclid Ave. (SM495100008) File Number 090971: Storm sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $68,000).  The total estimated cost for this project including the requested amount is $80,000.  This project is anticipated to be completed during the 2010 construction season.

 

; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Nfr 9

03/04/10