This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed. After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable. A resolution will be submitted after the Public Hearing authorizing construction.
BODY:
Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:
2nd Aldermanic District
Alley between W. Chambers St., W. Girard Ave., N. 64th St., N. 66th St. (ST212010141): Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $1,000)
3rd Aldermanic District
E. Belleview Pl. - N. Lake Dr. to N. Downer Ave. (ST211010145): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $1,000)
E. Kenwood Blvd. - 800 feet m/l east of N. Lake Dr. to 150 feet m/l east of N. Lake Dr. (ST211010146): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $1,000)
Alley between N. Jackson St., N. Jefferson St., E. Pleasant St., N. Water St. (Southerly 125 feet m/l) (ST212010140): Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $1,000)
5th Aldermanic District
N. 82nd St. - 125 feet m/l south of W. Center St. to W. Center St. (Sponsored by the City of Wauwatosa) (ST211000169): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $500)
Alley between W. Highwood Ave., W. Keefe Ave., N. 100th St., City Limits (Sponsored by the City of Wauwatosa) (ST212000157): Paving the alley with asphalt. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $500)
Alley between W. Highwood Ave., W. Nash St., N. 100th St., N. 101st St., City Limits (Sponsored by the City of Wauwatosa) (ST212000158): Paving the alley with asphalt. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $500)
Alley between W. Melvina St., W. Vienna Ave., N. 100th St., N. 101st St., City Limits (Sponsored by the City of Wauwatosa) (ST212000159): Paving the alley with asphalt. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $500)
Alley between W. Nash St., W. Vienna Ave., N. 100th St., N. 101st St., City Limits (Sponsored by the City of Wauwatosa) (ST212000160): Paving the alley with asphalt. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $500)
12th Aldermanic District
6th Street Viaduct over the Menomonee Valley (BR30180801/ST30180801): Structure replacement. (BR30180801 - Nonassessable State Aid Structure Fund -- $108,468, State/Federal Grantor Structure Fund -- $759,282; ST30180801 - Nonassessable State Aid Fund -- $13,406, State/Federal Grantor Paving Fund -- $94,344)
17th Aldermanic District
Alley between W. Garfield Ave., W. North Ave., N. Sherman Blvd., N. 42nd St. (Westerly North-South Leg) (ST212010139): Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $1,000)
;and, be it
Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it
Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it
Further, Resolved, That the City Comptroller is authorized and directed to transfer additional funds to the Sixth Street Viaduct non-assessable preliminary engineering subaccounts for additional preliminary engineering work relative to implementing the Design-Build process for the Viaduct replacement; and, be it
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.