Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $959,000 for a total estimated cost of these projects being $2,449,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $959,000. The total estimated cost of these projects is $2,449,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
4th and 12th Aldermanic Districts
Sixth Street Viaduct Cable-Stayed Bridges (BR100120103) File Number 111690: Consultant design services for in-depth inspection of the cable stay bridges. (City Share Non-assessable Structure Fund -- $50,000, Additional Funds). The total estimated cost for this project including the requested amount is $300,000. This project is anticipated to be completed during the 2012 construction season.
5th and 10th Aldermanic Districts
W. Burleigh St. - W. Lisbon Ave. to West City Limits (ST211120178): Paving the roadway with asphalt. (Nonassessable Reconstruction Paving Fund -- $400,000). The total estimated cost for this project including the requested amount is $1,000,000. This project is anticipated to be completed during the 2012 construction season.
8th Aldermanic District
S. 35th St. - 400 feet m/l south of W. Greenfield Ave. to W. Greenfield Ave. (SM495120020) File Number 111474: Combined sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $42,000). The total estimated cost for this project including the requested amount is $52,000. This project is anticipated to be completed during the 2012 construction season.
13th Aldermanic District
W. Oklahoma Ave. - S. 26th St. to S. 27th St. (SM495120024) File Number 111474: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $150,000). The total estimated cost for this project including the requested amount is $165,000. This project is anticipated to be completed during the 2012 construction season.
S. 17th St. - W. Euclid Ave. to W. Oklahoma Ave. (SM495110058) File Number 111024: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $142,000). The total estimated cost for this project including the requested amount is $157,000. This project is anticipated to be completed during the 2012 construction season.
Various Aldermanic Districts
Asphalt resurfacing of various streets by contract (1) South (ST211120177) File Number 111025: (Nonassessable Reconstruction Paving Fund -- $175,000, Additional Funds). The total estimated cost for this project including the requested amount is $775,000. This project is anticipated to be completed during the 2012 construction season.
now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is directed to proceed with said work; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
MLD:dr
Nfr 14
07/24/2012