Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $132,700 for a total estimated cost of $141,500.
Sponsors: THE CHAIR
Indexes: ALLEY IMPROVEMENTS, PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Letter for Rescheduled PW Meeting for 9-13-2011, 3. Official Notice Number 22

Number

110565

Version

SUBSTITUTE 1

Reference

101541

Sponsor

THE CHAIR

Title

Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $132,700 for a total estimated cost of $141,500.

Analysis

This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.  The City cost of these projects approved by this resolution is estimated to be $132,700.  The total estimated cost of these projects is $141,500.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

 

6th Aldermanic District

 

N. 22nd St. - W. Hopkins St. to W. Townsend St. (ST211110182):  Install traffic calming speed hump(s).  (Assessable Reconstruction Paving Fund -- $13,500; Nonassessable Reconstruction Paving Fund -- $3,000).  The total estimated cost for this project including the requested amount is $16,500.  This project is anticipated to be completed during the 2012 construction season.  This project will be funded with 2012 budgeted funds.

 

10th Aldermanic District

 

Alley between W. Auer Ave., W. Concordia Ave., N. 53rd St., and N. 54th St. (ST212110107) File Number 101541:  Concrete alley pavement reconstruction, replace some abutting sidewalk or driveway approach, and grading.  (Assessable Alley Paving Fund -- $41,200; Nonassessable Alley Paving Fund -- $75,000).  The total estimated cost for this project including the requested amount is $125,000.  This project is anticipated to be completed during the 2012 construction season.  This project will be funded with 2012 budgeted funds.

 

; and

 

Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and

 

Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works’ Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it

 

Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it

 

Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That projects: N. 22nd St. (ST211110182) and Alley W. Auer Ave. (ST212110507) will be billed after January 1, 2013, but not before 12 months after the project contract has been completed.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Afr 1

09/14/2011