File #: 170779    Version:
Type: Resolution Status: Passed
File created: 9/6/2017 In control: COMMON COUNCIL
On agenda: Final action: 9/26/2017
Effective date:    
Title: Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,863,000 for a total estimated cost of these projects being $10,369,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
10/5/20171 MAYOR SIGNED   Action details Meeting details Not available
9/26/20171 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Video Video
9/13/20170 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Proposed Substitute B
Pass5:0 Action details Meeting details Video Video
9/13/20170 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - DPW
Pass5:0 Action details Meeting details Video Video
9/6/20170 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

170779

Version

Substitute 1

Reference

161154

Sponsor

THE CHAIR

Title

Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,863,000 for a total estimated cost of these projects being $10,369,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $4,863,000.  The total estimated cost of these projects is $10,369,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

1st Aldermanic District

 

Area bounded by W. Congress St. to W. Hope Ave. and N. 27th St. to the Soo Line Railroad #2 (SM495150027) File Number 161154:  Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $1,000,000, Additional Funds).  The total estimated cost for this project including the requested amount is $4,000,000.  This project is anticipated to be completed during the 2017 construction season.

 

5th Aldermanic District

 

West Good Hope Road Bioswales: W. Good Hope Rd. - N. 91st St. to N. 107th St. (SM499160109) File Number 151848:  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $5,000, Additional Funds).  The total estimated cost for this project including the requested amount is $300,000.  This project is anticipated to be completed during the 2018 construction season.

 

8th Aldermanic District

 

W. Pierce St. - S. 37th St. to S. 39th St. (SM495160091) File Number 161153:  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $128,000).  The total estimated cost for this project including the requested amount is $140,000.  This project is anticipated to be completed during the 2018 construction season.

 

9th Aldermanic District

 

West Good Hope Road Bioswales:  W. Good Hope Rd. - N. 43rd St. to N. 91st St. (SM499160122) File Number 161153:  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $15,000, Additional Funds).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2018 construction season.

 

11th Aldermanic District

 

W. Ohio Ave. - S. 35th St. to S. 39th St. (SM495160090) File Number 161153:

Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $296,000).  The total estimated cost for this project including the requested amount is $308,000.  This project is anticipated to be completed during the 2017 construction season.

 

S. 57th St. - 160 feet m/l north of W. Holt Ave. to Lyons Creek Outfall (SM495170018) File Number 161694:   Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $77,000).  The total estimated cost for this project including the requested amount is $89,000.  This project is anticipated to be completed during the 2018 construction season

 

12th Aldermanic District

 

S. Water St. - E. Washington St. to E. National Av. (ST211170195) File Number 161694:  Railroad track removal.  Replace pavement as necessary.  (Nonassessable Reconstruction Paving Fund -- $35,000, Additional Funds).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2017 construction season.

 

13th and 14th Aldermanic Districts

 

Area bounded by W. Oklahoma Ave. to E. Bottsford Ave. from S. 13th St. to S. Kansas Ave. (SM494160202) File Number 160589:   Sanitary sewer lining.  (Infiltration/Inflow Reduction Fund -- $2,690,000).  The total estimated cost for this project including the requested amount is $2,715,000.  This project is anticipated to be completed during the 2017 construction season.

 

14th Aldermanic District

 

S. Pennsylvania Ave. - E. Euclid Ave. to E. Fernwood Ave. (SM495160006) File Number 151288:  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $17,000).  The total estimated cost for this project including the requested amount is $27,000.  This project is anticipated to be completed during the 2017 construction season.

 

Various Aldermanic Districts

 

2017 High Impact paving projects ADA requirement work (ST216160110) File Number 161441:  Removing and replacing concrete curb and sidewalk ramps to meet ADA requirements, replace abutting pavement if necessary, sodding and grading.  (Nonassessable High Impact Streets -- $300,000, Additional Funds).  The total estimated cost for this project including the requested amount is $2,000,000.  This project is anticipated to be completed during the 2017 construction season.

 

2017 Speed hump projects (ST211170215): Engineering and signage installation for speed humps - Nonassessable Reconstruction Paving Fund --$100,000. This work is anticipated to be completed during the 2017 construction season.

 

2018 Speed hump projects (ST211180150): Engineering and signage installation for speed humps - Nonassessable Reconstruction Paving Fund -- $200,000. This work is anticipated to be completed during the 2018 construction season.

 

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Jean Ziller

Nfr 1

9/05/2017