powered help
header-left header-center header-right
File #: 061098    Version:
Type: Resolution Status: Passed
File created: 12/12/2006 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 1/17/2007
Effective date:    
Title: Substitute resolution authorizing the City Comptroller to transfer funds to provide enhancements to the existing Pavement Management Administration System with a total estimated cost of this project in 2007 being $80,000, the estimated cost of this project in 2006 was $80,000 for a total estimated cost of $160,000.
Sponsors: THE CHAIR
Indexes: CONSULTANTS, PUBLIC IMPROVEMENTS, STREET IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter.pdf, 2. Fiscal Note, 3. Cover Letter

Number

061098

Version

SUBSTITUTE 1

Sponsor

THE CHAIR

Title

Substitute resolution authorizing the City Comptroller to transfer funds to provide enhancements to the existing Pavement Management  Administration System with a total estimated cost of this project in 2007 being $80,000, the estimated cost of this project in 2006 was $80,000 for a total estimated cost of $160,000.

Analysis

This resolution directs the City Comptroller to transfer funds to undertake surface distress survey and roughness testing of pavements and retain additional consultant services to provide enhancements to the existing Pavement Management Administration System.  The City cost of the project approved by this resolution is estimated to be $80,000.  The total estimated cost of this project is $160,000, all City funds.

Body

Whereas, The Department of Public Works (DPW) previously implemented a Pavement Management Administration System to assist in preparing the roadway paving program; and

 

Whereas, The Common Council of the City of Milwaukee has previously adopted File Number 941631 on February, 1995, which authorized and directed the Commissioner of Public Works to engage a Consultant to assist the DPW in upgrading and expanding the existing Pavement Management Administration System; and

 

Whereas, The Common Council of the City of Milwaukee authorized the Commissioner of Public Works to enter into contract amendment number two, File Number 000478 on July 25, 2000; and

 

Whereas, The Common Council of the City of Milwaukee authorized the Commissioner of Public Works to enter into contract amendment number three, File Number 060155 on June 20, 2006; and

 

Whereas, The Pavement Management Administration System requires timely data for proper implementation and presently most of the data is outdated and not compatible with the new system; and

 

Whereas, Surface distress survey and roughness testing data is necessary to evaluate the current condition of the pavements and thus assure proper implementation of the Pavement Management Administration System; and

 

Whereas, The Consultant would undertake surface distress and roughness testing and provide enhancements to the Pavement Management Administration System software; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works is authorized to enter into contract amendment number four between the City of Milwaukee and Stantec Consulting Inc., and, be it

 

Further Resolved, That the City Engineer is authorized to expend funds necessary for the surface distress and roughness testing, additional services and enhancements to the existing Pavement Management System; and, be it

 

Further Resolved, That the City Comptroller is hereby authorized and directed to transfer $80,000 from the Major Street Improvement parent account 0333-ST320070000, to an expenditure account within the Capital Improvement Fund-Grant and Aid Projects; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer additional amounts as required for the work, but not to exceed a 10 percent in the amount as set aside above. 

 

City Share

Fund Number 0333

Project Grant Number ST320070000

$80,000

 

Previously authorized $80,000

 

Current estimate $160,000

 

Original estimate $160,000

 

This project is anticipated to be completed during the 2007 construction season.