File #: 191657    Version:
Type: Resolution Status: Passed
File created: 2/11/2020 In control: COMMON COUNCIL
On agenda: Final action: 3/3/2020
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $911,000 for a total estimated cost of these projects being $10,696,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

191657

Version

SUBSTITUTE 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $911,000 for a total estimated cost of these projects being $10,696,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $911,000 with the total cost estimated to be $10,969,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

1st Aldermanic District

 

N. Sherman Blvd. (east side) - W. Fairmount Ave. to W. Villard Ave. (WT410210627) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $2,500; Nonassessable Water Fund Budget Line 6410 -- $22,500). The total estimated cost of this project including the requested amount is $340,000.  This project is anticipated to be completed during the 2021 construction season. 

 

W. Thurston Ave. - N. 36th St. to N. 40th St. (WT410210630) Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $2,500; Nonassessable Water Fund Budget Line 6410 -- $22,500).   The total estimated cost of this project including the requested amount is $335,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 35th St. - W. Silver Spring Dr. to W. Oriole Dr. (WT410210631) Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $3,000; Nonassessable Water Fund Budget Line 6410 -- $27,000).   The total estimated cost of this project including the requested amount is $425,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 36th St. - W. Silver Spring Dr. to W. Florist Ave. (WT410210632) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $4,000; Nonassessable Water Fund Budget Line 6410 -- $36,000). The total estimated cost of this project including the requested amount is $675,000.  This project is anticipated to be completed during the 2021 construction season.

 

1st and 4th Aldermanic District

 

N. 27th St.and W. Highland Blvd. Bioretention Maintenance Contract (SM499200001)  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $10,000).  The total estimated cost of this project including the requested amount is $59,000.  This project is anticipated to be completed during the 2020 construction season. 

 

 

2nd Aldermanic District

 

W. Hampton Ave. (Southside) - N. 71st St. to N. 74th St. (WT410210626) Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $2,500; Nonassessable Water Fund Budget Line 6410 -- $22,500).   The total estimated cost of this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2021 construction season. 

 

2nd and 5th Aldermanic Districts

 

W. Hampton Ave. (Southside) - N. 77th St. to N. 81st St. (WT410210625)  Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $2,500; Nonassessable Water Fund Budget Line 6410 -- $22,500).  The total estimated cost of this project including the requested amount is $375,000.  This project is anticipated to be completed during the 2021 construction season. 

 

2nd, 5th and 9th Aldermanic Districts

 

N. 91st St.and N. 92nd St. Bioretention Maintenance Contract (SM499200003)  (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $10,000).  The total estimated cost of this project including the requested amount is $33,000.  This project is anticipated to be completed during the 2020 construction season. 

 

3rd Aldermanic District

 

N. Dousman St. - E. Locust St. to 125’ north of E. Roadsmeet St. (WT410210624) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500).The total estimated cost of this project including the requested amount is $120,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. Fratney St. - E. Meinecke Ave. to E. Keefe Ave.  (SM495200022)  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project including the requested amount is $91,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. Gordon Pl. - E. Roadsmeet St. to 125’ north of E. Roadsmeet St. (WT410210623) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $1,500;Nonassessable Water Fund Budget Line 6410 -- $13,500).

The total estimated cost of this project including the requested amount is $35,000.  This project is anticipated to be completed during the 2021 construction season. 

 

E. Roadsmeet St. - N. Dousman St. to N. Gordon Pl. (WT410210622) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $80,000.  This project is anticipated to be completed during the 2021 construction season. 

 

4th Aldermanic District 

 

W. Kilbourn Ave. - N. 11th St. to N. 12th St.(WT410210621) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2021 construction season. 

 

W. Kilbourn Ave. - N. 25th St. to N. 27th St. (WT410210634) Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500).  The total estimated cost of this project including the requested amount is $190,000.  This project is anticipated to be completed during the 2021 construction season. 

 

W. Michigan St. - N. 31st St. to N. 35th St. (WT410210616) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $2,500; Nonassessable Water Fund Budget Line 6410 -- $22,500). The total estimated cost of this project including the requested amount is $340,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 26th St. - 50’ south of W. Kilbourn Ave. to W. State St.  (WT410210635) Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500).  The total estimated cost of this project including the requested amount is $140,000.  This project is anticipated to be completed during the 2021 construction season. 

 

5th Aldermanic District

 

W. Auer Ave. - N. 76th St. to N. 84th St. (WT410210609) Relaying water main

(Nonassessable Water Fund Budget Line 5010 -- $4,000; Nonassessable Water Fund Budget Line 6410 -- $36,000). The total estimated cost of this project including the requested amount is $675,000.  This project is anticipated to be completed during the 2021 construction season. 

 

W. Douglas Ave. - 360’ east of N. River Trail Dr. to 800’ east of N. River Trail Dr.

(SM495200011) Installing new storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project including the requested amount is $111,000.  This project is anticipated to be completed during the 2020 construction season. 

 

W. Grantosa Dr. - W. Hampton Ave. to W. Potomac Ave. (WT410210610) Relaying water main. (Nonassessable Water Fund Budget Line 5010 - $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $35,000.  This project is anticipated to be completed during the 2021 construction season. 

 

W. Hope Ave. - N. 78th St. to N. 81st St. (WT410210605) Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $18,000). The total estimated cost of this project including the requested amount is $250,000.  This project is anticipated to be completed during the 2021 construction season. 

 

W. Lynmar Tr. - W. Marion St. to N. 80th St. (WT410210601) Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2021 construction season. 

 

W. Potomac Ave. - W. Grantosa Dr. to N. 86th St. (WT410210611) Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500.  The total estimated cost of this project including the requested amount is $130,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 80th St. - W. Hope Ave. to W. Lynmar Tr. (WT410210602) Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $95,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 80th St. - W. Marion St. to W. Congress St. (WT410210600)  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $155,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 82nd St. - W. Burleigh St. to W. Auer Ave. (WT410210608) Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $160,000.  This project is anticipated to be completed during the 2021 construction season. 

 

6th Aldermanic District

 

N. Killian Pl. - E. Reservoir Ave. to E. Brown St. (WT410210619) Relaying water main

(Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $120,000.  This project is anticipated to be completed during the 2021 construction season. 

 

W. Randolph St. --  N. Vel R. Phillips Ave. to N. 5th St. (WT410210607) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $70,000.  This project is anticipated to be completed during the 2021 construction season. 

 

E. Reservoir Ave. - N. Hubbard St. to N. Buffum St. (WT410210618) Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2021 construction season.

 

N. Richards St. - E. Burleigh St. to E. Ring St. (WT410210628) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $18,000). The total estimated cost of this project including the requested amount is $255,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N.2nd St. - W. North Ave. to W. Center St. (SM499180117) (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $5,000).   The total estimated cost of this project including the requested amount is $195,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 5th St.--  N. Dr. Martin Luther King, Jr. Dr. to W. Keefe Ave. (WT410210606)  Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $18,000). The total estimated cost of this project including the requested amount is $250,000.  This project is anticipated to be completed during the 2021 construction season. 

 

7th Aldermanic District

 

W. Vienna Ave. - N. 37th St. to N. 41st St. (WT410210614) Relaying water main

(Nonassessable Water Fund Budget Line 5010 -- $2,500; Nonassessable Water Fund Budget Line 6410 -- $22,500).The total estimated cost of this project including the requested amount is $310,000.  This project is anticipated to be completed during the 2021 construction season. 

 

7th and 15th Aldermanic Districts

 

N. Sherman Blvd. Bioretention Maintenance Contract (SM499200002) (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $10,000)   The total estimated cost of this project including the requested amount is $49,000.  This project is anticipated to be completed during the 2020 construction season. 

 

8th Aldermanic District

 

W. Lapham Blvd. - N. 20th St. to N. 22nd St.(WT410210613) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $175,000.  This project is anticipated to be completed during the 2021 construction season. 

 

9th Aldermanic District

 

N. 46th St. - W. Woolworth Ave. to W. Mill Rd. (WT410210636) Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500).   The total estimated cost of this project including the requested amount is $65,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 51st St. - W. Mill Rd. to W. Green Tree Rd. (WT410210637) Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $4,000; (Nonassessable Water Fund Budget Line 6410 -- $36,000).   The total estimated cost of this project including the requested amount is $665,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 85th St. - W. Glenbrook Rd. to 120’ north of N. Joyce Ave. (WT410210633) Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500).  The total estimated cost of this project including the requested amount is $190,000.  This project is anticipated to be completed during the 2021 construction season. 

 

10th Aldermanic District

 

W. Adler St. - 60’ east of S. 59th to S. 62nd St. - (SM495200015) . Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project including the requested amount is $262,000.  This project is anticipated to be completed during the 2020 construction season. 

 

S. 64th St. - W. Main St. to W. Dickinson St. (SM495200016) Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project including the requested amount is $142,000.  This project is anticipated to be completed during the 2020 construction season. 

 

S. 67th St. - W. Dixon St. to 300’ south of W. Dixon St. (SM495200014) Relaying sanitary sewer.   (Nonassessable Sewer Maintenance Relay Fund -- $12,000

The total estimated cost of this project including the requested amount is $143,000.  This project is anticipated to be completed during the 2020 construction season. 

 

S. 68th St. - 330’ north of W. Main St. to W. Main St. (SM495200017)  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project including the requested amount is $87,000.  This project is anticipated to be completed during the 2020 construction season. 

 

S. 68th St. - W. Stevenson St. to 275’ north of W. Stevenson St. (SM495200018) Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 76th St. - 330’ south of W. Stevenson St. to W. Stevenson St. (SM495200019) Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project including the requested amount is $88,000.  This project is anticipated to be completed during the 2020 construction season. 

 

S. 80th St. - 290’ north of W. O’Connor St. to W. O’Connor St. (SM495200020) Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project including the requested amount is $84,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 80th St. - W. Fairview Ave. to W. Stevenson St. - (SM495200013)  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project including the requested amount is $83,000.  This project is anticipated to be completed during the 2020 construction season. 

 

13th Aldermanic District

 

W. Ohio Ave. - S. 23rd St. to S. 26th St. (WT410210629) Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $2,000; (Nonassessable Water Fund Budget Line 6410 -- $18,000).  The total estimated cost of this project including the requested amount is $245,000.  This project is anticipated to be completed during the 2021 construction season. 

 

14th Aldermanic District

 

S. Logan Ave. - E. Wilbur Ave. to E. Saveland Ave. (WT410210620) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $1,500; Nonassessable Water Fund Budget Line 6410 -- $13,500). The total estimated cost of this project including the requested amount is $170,000.  This project is anticipated to be completed during the 2021 construction season. 

 

15th Aldermanic District

 

W. Galena St. - N. 15th St. to N. 18th St. (WT410210615)  Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $18,000).The total estimated cost of this project including the requested amount is $265,000.  This project is anticipated to be completed during the 2021 construction season. 

 

W. North Ave. - N. 19th St. to N. 21st St. (SM495200021)  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project including the requested amount is $198,000.  This project is anticipated to be completed during the 2020 construction season. 

 

W. Walnut St./W. Lisbon Ave. - N. 24th St. to N. 27th St. (WT410210617) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $2,500; Nonassessable Water Fund Budget Line 6410 -- $22,500). The total estimated cost of this project including the requested amount is $340,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 17th St. - W. North Ave. to 33’ +/- north of W. North Ave.  (SM495200012) Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).   The total estimated cost of this project including the requested amount is $161,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 30th St. - W. Cherry St. to W. Walnut St. (WT410210612) Relaying water main and Lead Replacement of Service.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $18,000). The total estimated cost of this project including the requested amount is $250,000.  This project is anticipated to be completed during the 2021 construction season. 

 

City Wide

 

2020 Bioretention Maintenance Contract (SM499200004) (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $20,000).   The total estimated cost of this project including the requested amount is $295,000.  This project is anticipated to be completed during the 2020 construction season.

 

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/dl

Npr 8 Sub