powered help
header-left header-center header-right
File #: 220077    Version:
Type: Resolution Status: Passed
File created: 5/10/2022 In control: COMMON COUNCIL
On agenda: Final action: 6/1/2022
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,353,000 for a total estimated cost of these projects being $4,785,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number

220077

Version

Substitute 1

Reference

211199

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $4,353,000 for a total estimated cost of these projects being $4,785,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $4,353,000.  The total estimated cost of these projects is $4,785,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

6th Aldermanic District

 

N. 1st St. - 315’ South of W. Locust St. to W. Locust St. (SM495210103) File Number 211199: Combined sewer relay. (Nonassessable Sewer Maintenance Relay Fund -- $154,000).  The total estimated cost of this project including the requested amount is $166,000.  This project is anticipated to be completed during the 2022 construction season.

 

N. Achilles St. - E. Burleigh St. to E. Concordia Ave. (SM495210089) File Number 211199: Combined sewer relay. (Nonassessable Sewer Maintenance Relay Fund -- $545,000).  The total estimated cost of this project including the requested amount is $560,000.  This project is anticipated to be completed during the 2022 construction season.

 

E. Auer Ave. - N. Achilles St. to N. Bluhms Pl. (SM495210086) File Number 211199: Combined sewer relay. (Nonassessable Sewer Maintenance Relay Fund -- $79,000).  The total estimated cost of this project including the requested amount is $89,000.  This project is anticipated to be completed during the 2022 construction season.

 

E. Auer Ave. - N. Richards St. to N. Buffum St. (SM495210046) File Number 210701: Combined sewer relay. (Nonassessable Sewer Maintenance Relay Fund -- $95,000).  The total estimated cost of this project including the requested amount is $107,000.  This project is anticipated to be completed during the 2022 construction season.

 

N. Buffum St. - E. Auer Ave. to 325’ +/- North of E. Concordia Ave. (SM495210057) File Number 210856: Combined sewer relay. (Nonassessable Sewer Maintenance Relay Fund -- $226,000).  The total estimated cost of this project including the requested amount is $241,000.  This project is anticipated to be completed during the 2022 construction season.

 

N. Fratney St. - E. Vienna Ave. to E. Capitol Dr. (WT410220669) File Number 201552: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0. Nonassessable Water Fund Budget Line 6410 -- $365,000). The total estimated cost of this project including the requested amount is $385,000. This project is anticipated to be completed during the 2022 construction season.

 

W. Hadley St. - N. 5th St. to N. 6th St.  (SM495210098) File Number 211199: Combined sewer relay. (Nonassessable Sewer Maintenance Relay Fund -- $160,000).  The total estimated cost of this project including the requested amount is $172,000.  This project is anticipated to be completed during the 2022 construction season.

 

E./W. Ring St. - N. Achilles St. to N. 2nd St. (SM495220011) File Number 211600: Combined sewer relay. (Nonassessable Sewer Maintenance Relay Fund -- $171,000).  The total estimated cost of this project including the requested amount is $183,000.  This project is anticipated to be completed during the 2022 construction season.

 

10th Aldermanic District

 

W. Cherry St. - N. 47th St. to N. 48th St. (SM495210060) File Number 210701: Combined sewer relay. (Nonassessable Sewer Maintenance Relay Fund -- $109,000).  The total estimated cost of this project including the requested amount is $121,000.  This project is anticipated to be completed during the 2022 construction season.

 

11th Aldermanic District

 

S. 72nd St. - W. Bennett Ave. to W. Oklahoma Ave. (WT410220640) File Number 201552: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0. Nonassessable Water Fund Budget Line 6410 -- $100,000). The total estimated cost of this project including the requested amount is $115,000. This project is anticipated to be completed during the 2022 construction season.

 

S. 91st St. - 105’ North of W. Morgan Ave. to W. Morgan Ave. (WT410220686) File Number 201552: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0. Nonassessable Water Fund Budget Line 6410 -- $50,000). The total estimated cost of this project including the requested amount is $65,000. This project is anticipated to be completed during the 2022 construction season.

 

W. Holt Ave. - S. 84th St. to S. 88th St. (WT410220687) File Number 201552: Relaying water main and water main extension. (Nonassessable Water Fund Budget Line 5010 -- $0. Nonassessable Water Fund Budget Line 6410 -- $335,000). The total estimated cost of this project including the requested amount is $360,000. This project is anticipated to be completed during the 2022 construction season.

 

W. Oklahoma Ave. (Northside) - S. 70th St. (Extended) to S. 72nd St. (WT410220639) File Number 201552: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $180,000).  The total estimated cost of this project including the requested amount is $195,000.  This project is anticipated to be completed during the 2022 construction season.

 

15th Aldermanic District

 

N. 12th St. - W. Vliet St. to 215’ North of W. Cherry St. (WT410220664) File Number 201552: Relaying water main and lead replacement of service.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $230,000).  The total estimated cost of this project including the requested amount is $245,000.  This project is anticipated to be completed during the 2022 construction season.

 

N. 13th St. - W. Kneeland St. to W. Cherry St. (WT410220665) File Number 201552: Water main extension. (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $65,000).  The total estimated cost of this project including the requested amount is $80,000.  This project is anticipated to be completed during the 2022 construction season. 

 

W. Cherry St. - N. 12th St to N. 13th St. (WT410220663) File Number 201552: Relaying water main and lead replacement of service.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $100,000).  The total estimated cost of this project including the requested amount is $115,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Clarke St. - N. 37th St. to N. 38th St. (SM495210051) File Number 210701: Combined sewer relay. (Nonassessable Sewer Maintenance Relay Fund -- $49,000).  The total estimated cost of this project including the requested amount is $61,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Kneeland St. - N. 13th St to N. 14th St. (WT410220666) File Number 201552: Relaying water main and lead replacement of service.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $140,000).  The total estimated cost of this project including the requested amount is $155,000.  This project is anticipated to be completed during the 2022 construction season.

 

W. Walnut St. - N. 12th St. to N. 20th St. (WT410220001) File Number 201552: Hydrant alteration, relaying water main and lead replacement of service.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $1,050,000).  The total estimated cost of this project including the requested amount is $1,070,000.  This project is anticipated to be completed during the 2022 construction season.

 

City Wide

 

Water Repairs/Distribution Referred (WT410220840) File Number 211344: Water main repairs. (Nonassessable Water Fund Budget Line 5010 -- $0). (Nonassessable Water Fund Budget Line 6410 - Additional Funds $150,000). The total estimated cost for this project including the requested amount is $300,000. This project is anticipated to be completed during the 2022 construction season.

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Holly Rutenbeck/tw

Nfr 12 Sub