Number
100217
Version
SUBSTITUTE 1
Reference
091343
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,017,000 for a total estimated cost of these projects being $22,297,956.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $3,017,000. The total estimated cost of these projects is $22,297,956.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
3rd and 6th Aldermanic Districts
E./W. Keefe Ave. - N. Humboldt Ave. to N. 7th St. (ST520042010) (2059-00-71)
For construction related cost. (City Share Non-Assessable Paving Fund -- $20,000)
Previously authorized for Engineering -- $115,000
Current estimated cost of the total project including this resolution -- $2,152,774.74
Original estimated cost of the total resolution (Resolution File No. 040400) -- $1,844,000
This project is anticipated to be completed during the 2010 construction season.
4th Aldermanic District
E. State St. - N. Edison St. to N. Prospect Ave. (ST30684010) (2204-01-70)
For construction related cost. (City Share Non-Assessable Paving Fund -- $20,000)
Previously authorized for engineering -- $268,050
Current estimated cost of the total project including this resolution -- $2,066,693.58
Original estimated cost of the total resolution (Resolution File No. 950972) -- $604,200
This project is anticipated to be completed during the 2010 construction season.
4th and 12th Aldermanic Districts
S. 2nd St. - W. National Ave. to W. St. Paul Ave. (ST520091310) (2245-02-70)
For construction related cost. (City Share Non-Assessable Paving Fund -- $20,000)
Previously authorized for engineering -- $30,000
Current estimated cost of the total project including this resolution -- $737,000
Original estimated cost of the total resolution (Resolution File No. 051254) -- $672,000
This project is anticipated to be completed during the 2010 construction season.
4th and 15th Aldermanic Districts
W. Cherry St. - N. 13th St. to N. 14th St. (SM495100042) File Number 091343: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $64,000). The total estimated cost for this project including the requested amount is $76,000. This project is anticipated to be completed during the 2010 construction season.
N. 14th St. - W. Cherry St. to W. Vliet St. (SM495100041) File Number 091343: Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $117,000). The total estimated cost for this project including the requested amount is $129,000. This project is anticipated to be completed during the 2010 construction season.
5th Aldermanic District
N. 90th St. - W. Center St. to 187 feet m/l north of W. Center St. (SM495100067) File Number 100013: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $44,000). The total estimated cost for this project including the requested amount is $56,000. This project is anticipated to be completed during the 2010 construction season.
N. 95th St. - W. Concordia Ave. to W. Auer Ave. (SM495100051) File Number 091432: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $54,000). The total estimated cost for this project including the requested amount is $66,000. This project is anticipated to be completed during the 2010 construction season.
6th Aldermanic District
W. North Ave. - N. Booth St. to N. Dr. Martin Luther King Jr. Dr. (ST520091410)
(2445-07-70)
For construction related cost. (City Share Non-Assessable Paving Fund -- $20,000)
Previously authorized for Engineering -- $30,000
Current estimated cost of the total project including this resolution -- $2,898,451.47
Original estimated cost of the total resolution (Resolution File No. 090970) -- $1,929,200
This project is anticipated to be completed during the 2010 construction season.
8th and 11th Aldermanic Districts
S. 43rd St. - W. Cleveland Ave. to W. Forest Home Ave. (SM495090068) File Number 091433: Relay sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $343,000, Additional Funds). The total estimated cost for this project including the requested amount is $666,000. This project is anticipated to be completed during the 2010 construction season.
10th Aldermanic District
W. Blue Mound Rd. - N. 79th St. to W. Glenview Ave. (SM495090070) File Number 090762: Sanitary relay and new sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $2,185,000). The total estimated cost for this project including the requested amount is $2,200,000. This project is anticipated to be completed during the 2012 construction season.
12th Aldermanic Districts
S. Cesar Chavez Dr. - W. Greenfield Ave. to W. Pierce St. (ST520090110)
(2615-00-72)
For construction related cost. (City Share Non-Assessable Paving Fund -- $20,000)
Previously authorized for Engineering -- $130,644
Current estimated cost of the total project including this resolution -- $1,326,883.67
Original estimated cost of the total resolution (Resolution File No. 090194) -- $1,250,000
This project is anticipated to be completed during the 2010 construction season.
S. 13th St. - W. Cleveland Ave. to W. Windlake Ave. (ST520091610) (2505-08-70)
For construction related cost. (City Share Non-Assessable Paving Fund -- $20,000)
Previously authorized for Engineering -- $30,000
Current estimated cost of the total project including this resolution -- $2,630,378.90
Original estimated cost of the total resolution (Resolution File No. 081512) -- $2,280,500
This project is anticipated to be completed during the 2010 construction season.
12th and 14th Aldermanic Districts
S. 1st St. - W. Lincoln Ave. to S. Kinnickinnic Ave. (ST520042210) (2219-00-70)
For construction related cost. (City Share Non-Assessable Paving Fund -- $20,000)
Previously authorized for Engineering -- $30,000
Current estimated cost of the total project including this resolution -- $2,086,726.05
Original estimated cost of the total resolution (Resolution File No. 040400) -- $1,562,000
This project is anticipated to be completed during the 2010 construction season.
13th Aldermanic District
Mitchell Interchange Local Review (ST320080201) (1030-20-00) File Numbers 071594 and 081391: Review costs associated with the reconstruction of the Mitchell Interchange (Grantor Reimbursable Paving Fund -- $50,000).
These funds are to be transferred to the review account (ST320080201)
Previously authorized for local review: $210,000
Current estimated cost of the total review project including this resolution: $250,000
Original estimated cost of the total project (File No. 071594): $100,000
This project is anticipated to be completed during the 2010 construction season.
14th Aldermanic District
S. 6th St. Bridge over the Kinnickinnic River (BR520100110) (2235-01-71)
For construction related cost. (City Share Non-Assessable Paving Fund -- $20,000)
Previously authorized for Engineering -- $1,917,138
Current estimated cost of the total project including this resolution -- $4,956,047
Original estimated cost of the total resolution (Resolution File No. 081489) -- $2,061,034
This project is anticipated to be completed during the 2010 construction season.
now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
MLD:dr
Nfr 14
06/18/10