Number
071585
Version
ORIGINAL
Reference
Sponsor
THE CHAIR
Title
Resolution authorizing the City Comptroller to transfer funds to various State and/or Federal Aid project sub-accounts for the estimated remaining Wisconsin Department of Transportation and City of Milwaukee preliminary engineering costs totaling $75,000.00, City share is $15,000.00 and the Grantor’s share is $60,000.00.
Analysis
This resolution authorizes the City Comptroller to transfer funds to the previously established sub-accounts for the remaining Wisconsin Department of Transportation and City of Milwaukee preliminary engineering costs in the amount of $75,000.00. The City Milwaukee’s share is $15,000.00 and the grantor share is $60,000.00, increasing the total costs to $3,215,000.00 with the City share of $643,000.00 and the grantor share of $2,572,000.00.
Body
Whereas, The Common Council has previously adopted resolutions authorizing the City Comptroller to transfer funds to various State and/or Federal Aid project sub-accounts for preliminary engineering; and
Whereas, Additional planning and review during the design stage have resulted in increased costs charged against the project; and
Whereas, Additional funds are, therefore, necessary for the estimated remaining Wisconsin Department of Transportation and City of Milwaukee preliminary engineering costs for the projects; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized and directed to transfer funds to the project grant chartfields as follows:
Project Grant Value
State I.D. 2667-03-00
BR32000601
Humboldt Avenue Bridge over North Commerce Street
City Share Non-Assessable Structure Fund
BR300080000
Fund 0303
$15,000.00
Grantor Reimbursable Structure Fund
SP032080100
Fund 0306
$60,000.00
Construction is scheduled for 2009
Previously authorized for bridge preliminary engineering: $140,000.00
Current estimated cost for bridge preliminary engineering: $215,000.00
Current estimated cost of total project including this resolution: $3,215,000.00
Original estimated cost of total project (Resolution #041495): $1,035,000.00
Summary of projects in this resolution:
City Share Non-Assessable Structure Fund (0303): $15,000.00
Grantor Reimbursable Structure Fund (0306): $60,000.00
Resolution total: $75,000.00
Requestor
Department of Public Works
Drafter
Infrastructure Services Division
CSL:lja
March 10, 2008