Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
8th Aldermanic District
Alley between W. Becher St., W. Grant St., S. 31st St., and S. 32nd St. (ST212020102) File Number 941197: Concrete alley pavement reconstruction, replace some abutting sidewalk or driveway approach, and grading. (Assessable Alley Paving Fund -- $66,900; Nonassessable Alley Paving Fund -- $1,700)
Alley between W. Becher St., W. Rogers St., S. 33rd St., and S. 34th St. ST212010146) File Number 000312: Concrete alley pavement reconstruction, replace some abutting sidewalk or driveway approach, and grading. (Assessable Alley Paving Fund -- $67,300; Nonassessable Alley Paving Fund -- $3,500)
Alley between S. Layton Bl., W. National Ave., W. Pierce St., and S. 26th St. (ST21290145) File Number 872248: Concrete alley pavement reconstruction, replace some abutting sidewalk or driveway approach, and grading. (Assessable Alley Paving Fund -- $61,100; Nonassessable Alley Paving Fund -- $26,500)
;and
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works' Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it
Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
Further Resolved, That projects Alley W. Becher St. (ST212020102) and Alley W Becher St. (ST212010146) will be billed after January 1, 2004, and Alley S. Layton Bl. (ST21290145) will be billed after January 1, 2005, but not before 12 months after the project contract has been completed; and, be it
Further Resolved, That the following projects be deleted from the 2002 Paving Program.
8th Aldermanic District
S. 24th St. - W. Greenfield Ave. to W. Scott St. (ST21110133) File Number 901783
S. 31st St. - W. Hayes Ave. to W. Lincoln Ave. (ST211020123) File Number 891182
Alley between W. Dakota St., W. Montana St., S. 49th St., and S. 50th St. (ST212020118) File Number 000838.
Requestor
Infrastructure Services Division
Drafter
mld:lk