Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes.
Sponsors: THE CHAIR

Number

241994

Version

Substitute 1

Reference

241616

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $2,141,000.  The total estimated cost of these projects is $2,265,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

3rd Aldermanic District

 

N. Bartlett Ave. - E. Kane Pl. to 200’ +/- Northeast of E. Kane Pl. (SM495250019) File Number 241616: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $61,000). The total estimated cost for this project including the requested amount is $73,000. This project is anticipated to be completed during the 2025 construction season.

 

8th and 12th Aldermanic Districts

 

W. Virginia St. - S. 6th St. to S. 9th St. (SM495250028) File Number 241616: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $495,000). The total estimated cost for this project including the requested amount is $515,000. This project is anticipated to be completed during the 2025 construction season.

 

10th Aldermanic District

 

W. Fairview Ave. - 170’ Southeast of N. 59th St. to 175’ Southwest of N. 60th St. (SM495240069) File Number 241329: Relaying sanitary sewer and relocation. (Nonassessable Sewer Maintenance Relay Fund -- $219,000). The total estimated cost for this project including the requested amount is $234,000. This project is anticipated to be completed during the 2025 construction season.

 

11th Aldermanic District

 

S. 57th St. at W. Ohio Ave.(ext’d) (ST216250113) Installing traffic calming raised crosswalk.  (Nonassessable High Impact Paving Fund -- $25,000).  The total estimated cost of this project including the requested amount is $25,000.  This project is anticipated to be completed during the 2025 construction season.

 

S. Princeton Ave. - 300’ North of W. Verona Ct. to S. 37th St. (SM495240035) File Number 241191: Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $245,000). The total estimated cost for this project including the requested amount is $260,000. This project is anticipated to be completed during the 2025 construction season.

 

12th Aldermanic District

 

S. 9th St. - W. Washington St. to W. Greenfield Ave. (SM495250027) File Number 241616: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $699,000). The total estimated cost for this project including the requested amount is $719,000. This project is anticipated to be completed during the 2025 construction season.

 

13th Aldermanic District

 

S. Austin St. - E. Van Norman Ave. to E. Armour Ave. (SM495250016) File Number 241616: Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $86,000). The total estimated cost for this project including the requested amount is $98,000. This project is anticipated to be completed during the 2025 construction season.

 

14th Aldermanic District

 

S. 6th St.- W. Ohio Ave. to 480’ South of W. Ohio Ave. (SM495250012) File Number 241616: Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $157,000). The total estimated cost for this project including the requested amount is $172,000. This project is anticipated to be completed during the 2025 construction season.

 

E. Howard Ave.- S. Nevada St. to S. Brust St. (SM495250023) File Number 241616: Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $154,000). The total estimated cost for this project including the requested amount is $169,000. This project is anticipated to be completed during the 2025 construction season.

 

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Holly Rutenbeck

NFR 11 Sub