Number
051444
Version
SUBSTITUE 1
Sponsor
THE CHAIR
Title
Substitute resolution determining it necessary to make various assessable public improvements at various locations.
Analysis
This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed. After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable. A resolution will be submitted after the Public Hearing authorizing construction.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:
2nd Aldermanic District
W. Florist Ave. - N. 68th St. to N. 76th St. (ST211070124): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $50,000)
W. Grantosa Dr. - N. 68th St. to W. Fond du Lac Ave. (ST211060137): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $2,000, additional engineering funds) File Number 050805 authorized $33,600, total estimated engineering is $35,600.
N. 58th St. - W. Vienna Ave. to W. Capitol Dr. (ST211060124): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $3,000, additional engineering funds) File Number 040689 authorized $8,000, total estimated engineering is $11,000.
4th and 15th Aldermanic Districts
N. 13th St. - W. Highland Ave. to W. Galena St. (ST211070142): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $38,000)
5th Aldermanic District
W. Florist Ave. - N. Lovers Ln. to N. 119th St. (ST211060131): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000, additional engineering funds) File Number 040689 authorized $9,000, total estimated engineering is $14,000.
W. Sarasota Pl. - N. 95th St. to N. 100th St. (Sponsored by the City of Wauwatosa) (ST211070143): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $23,000)
N. 93rd St. - W. Lisbon Ave. to W. Melvina St. (ST211060110): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $4,000, additional engineering funds) File Number 040945 authorized $5,000, total estimated engineering is $9,000.
6th and 15th Aldermanic Districts
W. Center St. - N. Dr. Martin Luther King Jr. Dr. to N. 12th St. (Excluding Structure) (ST211060111): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $10,000, additional engineering funds) File Number 040588 authorized $25,000, total estimated engineering is $35,000.
7th Aldermanic District
N. 46th St. - W. Capitol Dr. to W. Hope Ave. (ST211060120): Remove and replace concrete curb and gutter. (Nonassessable Reconstruction Paving Fund -- $3,000, additional engineering funds) File Number 040689 authorized $7,500, total estimated engineering is $10,500.
8th Aldermanic District
W. Dakota St. - S. 37th St. to S. 38th St. (ST211060151): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $1,000, additional engineering funds) File Number 041692 authorized $4,000, total estimated engineering is $5,000.
S. 41st St. - W. Orchard St. to W. Greenfield Ave. (ST211070145): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $4,000)
Alley between W. Drury Ln., W. Oklahoma Ave., S. 32nd St., and S. 33rd St. (East-West Leg) (ST212060128): Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $4,000, additional engineering funds) File Number 041692 authorized $4,000, total estimated engineering is $8,000.
9th Aldermanic District
N. Servite Dr. - A point south of W. Brown Deer Rd. to W. Brown Deer Rd. (ST211060159): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $3,000)
N. 81st St. - W. Clovernook St. to W. Acacia St. (ST21190232): Paving the roadway with concrete. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $2,000, additional engineering funds) File Number 980184 authorized $10,500, total estimated engineering is $12,500.
10th Aldermanic District
W. Chester St. - N. 92nd St. to W. Dixon St. (ST211060127): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000, additional engineering funds) File Number 040689 authorized $4,500, total estimated engineering is $9,500.
W. Wells St. - N. 44th St. to N. 45th St. (ST211070123): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $6,000)
N. 44th St. - W. Blue Mound Rd. to W. Wells St. (ST211070122): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $14,000)
N. 58th St. - W. Philip Pl. to W. Keefe Ave. (ST211060123): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $3,000, additional engineering funds) File Number 040689 authorized $7,500, total estimated engineering is $10,500.
11th Aldermanic District
W. Crawford Ave. - W. Tripoli Ave. to S. 73rd St. (Including S. 73rd St. - W. Tripoli Ave. to W. Crawford Ave.) (ST211060150): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $3,000, additional engineering funds) File Number 041468 authorized $9,000, total estimated engineering is $12,000.
W. Dakota St. - S. 68th St. to S. 72nd St. (ST211060112): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $ 3,000, additional engineering funds) File Number 040588 authorized $7,000, total estimated engineering is $10,000.
S. 81st St. - W. Warnimont Ave. to W. Morgan Ave. (ST211060145): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000, additional engineering funds) File Number 041236 authorized $5,000, total estimated engineering is $10,000.
S. 83rd St. - W. Morgan Ave. to W. Euclid Ave. (ST211060107): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $2,000, additional engineering funds) File Number 051223 authorized $26,700, total estimated engineering is $28,700.
13th Aldermanic District
S. 6th St. (West Side) - A point south of W. Grange Ave. to W. Grange Ave. (ST211060170): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000)
14th Aldermanic District
S. Burrell St. - A point 275 feet m/l south of E. Ohio Ave. to E. Ohio Ave. (ST211060141): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $1,000, additional engineering funds) File Number 041031 authorized $5,000, total estimated engineering is $6,000.
15th Aldermanic District
W. Medford Ave. - N. 24th St. to W. Meinecke Ave. (ST211050153): Replace concrete curb and gutter and walk. (Nonassessable Reconstruction Paving Fund -- $2,000, additional engineering funds) File Number 050024 authorized $3,500, total estimated engineering is $5,500.
N. 37th St. - W. Vliet St. to W. Cherry St. (ST211060135): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000, additional engineering funds) File Number 040945 authorized $7,000, total estimated engineering is $12,000.
Alley between W. Lisbon Ave., W. Roberts St., N. 39th St., and N. 40th St. (ST212060122): Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $2,000, additional engineering funds) File Number 041031 authorized $8,000, total estimated engineering is $10,000.
; and, be it
Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it
Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
mld:lk
apr8
03/08/06