File #: 071168    Version:
Type: Resolution Status: Passed
File created: 12/11/2007 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 1/15/2008
Effective date:    
Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $209,000 for a total estimated cost of these projects being $1,904,330.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter, 2. Fiscal note

Number

071168

Version

SUBSTITUTE 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various assessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $209,000 for a total estimated cost of these projects being $1,904,330.

Analysis

This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed.  After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable.  A resolution will be submitted after the Public Hearing authorizing construction.  The City cost for engineering these projects is estimated to be $209,000 with the total cost estimated to be $1,904,330.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:

 

2nd Aldermanic District

 

W. Fiebrantz Ave. - W. Appleton Ave. to N. 76th St. (ST211080120):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $7,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Winfield Ave. - N. 76th St. to W. Bender Ave. (ST211090111):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $44,000).  The total estimated cost for this project including the requested amount is $328,000.  This project is anticipated to be completed during the 2009 construction season.

 

4th Aldermanic District

 

W. Kilbourn Ave. - N. 27th St. to N. 29th St. (ST211070169):  Installing traffic calming devices. (Nonassessable Reconstruction Paving Fund -- $2,000, additional funds).  File Number 071054 authorized $15,000.  The total estimated cost for this project including the requested amount is $17,000.  This project was completed in 2007.

 

N. 29th St. - W. Kilbourn Ave. to W. State St. (ST211070164):  Installing traffic calming devices. (Nonassessable Reconstruction Paving Fund -- $1,000, additional funds).  File Number 070490 authorized $8,300.  The total estimated cost for this project including the requested amount is $9,300.  This project was completed in 2007.

 

N. 32nd St. - W. Wisconsin Ave. to W. Wells St. (ST211070167):  Installing traffic calming devices. (Nonassessable Reconstruction Paving Fund -- $1,000, additional funds).  File Number 070268 authorized $8,200.  The total estimated cost for this project including the requested amount is $9,200.  This project was completed in 2007.

 

5th Aldermanic District

 

N. 91st St. - W. Capitol Dr. to W. Congress St. (ST211090106):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $42,000).  The total estimated cost for this project including the requested amount is $316,000.  This project is anticipated to be completed during the 2009 construction season.

 

11th Aldermanic District

 

W. Crawford Ave. - S. 84th St. to S. 87th St. (ST211090107):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $18,000).  The total estimated cost for this project including the requested amount is $134,000.  This project is anticipated to be completed during the 2009 construction season.

 

14th Aldermanic District

 

S. Delaware Ave. - E. Oklahoma Ave. to E. Russell Ave. (ST211040121):  Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, sodding, grading, and tree removal where necessary. (Nonassessable Reconstruction Paving Fund -- $40,000, additional funds).   File Number 050316 authorized $598,830.  The total estimated cost for this project including the requested amount is $628,830.  This project is complete.

 

S. Herman St. - E. Howard Ave. to E. Saveland Ave. (ST211090108):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $17,000).  The total estimated cost for this project including the requested amount is $125,000.  This project is anticipated to be completed during the 2009 construction season.

 

E. Morgan Ave. - S. Iowa Ave. (East) to S. Brust Ave. (ST211090109):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $25,000).  The total estimated cost for this project including the requested amount is $189,000.  This project is anticipated to be completed during the 2009 construction season.

 

E. Norwich St. - S. Herman St. to S. Lenox St. (ST211090110):  Paving the roadway with asphalt.  Laying a concrete curb and gutter.  Laying concrete sidewalk.  Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $12,000).  The total estimated cost for this project including the requested amount is $88,000.  This project is anticipated to be completed during the 2009 construction season.

 

; and, be it

 

Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it

 

Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

mld:lk

apr5