Title: Resolution directing the Commissioner of Public Works to execute a Revised Project Agreement titled “State/Municipal Agreement for a State - Let Urbanized Area STP - Urban Project” with the Wisconsin Department of Transportation for the improvement of West Lloyd Street between North 60th Street and West Lisbon Avenue at a revised estimated total cost of $3,652,000 at an 80 percent State and Federal Aid under the Surface Transportation Program with a City’s share of $826,400 which includes $120,000 of non participating items at 100 percent City’s cost and grantor’s share of $2,825,600 of which revised preliminary engineering cost is $207,000 with the city's share being $41,400 and the grantor's share being $165,600.
Sponsors: THE CHAIR
Indexes: AGREEMENTS, STREET IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Executed Agreement, 2. Revised Agreement, 3. Comptroller's Certificate, 4. Hearing Notice List
Number
111462
Version
ORIGINAL
Reference
100021
Sponsor
THE CHAIR
Title
Resolution directing the Commissioner of Public Works to execute a Revised Project Agreement titled "State/Municipal Agreement for a State - Let Urbanized Area STP - Urban Project" with the Wisconsin Department of Transportation for the improvement of West Lloyd Street between North 60th Street and West Lisbon Avenue at a revised estimated total cost of $3,652,000 at an 80 percent State and Federal Aid under the Surface Transportation Program with a City's share of $826,400 which includes $120,000 of non participating items at 100 percent City's cost and grantor's share of $2,825,600 of which revised preliminary engineering cost is $207,000 with the city's share being $41,400 and the grantor's share being $165,600.
Analysis
The resolution authorizes the Commissioner of Public Works to execute a Revised Project Agreement with the Wisconsin Department of Transportation (WisDOT) for the reconstruction of West Lloyd Street between North 60th Street and West Lisbon Avenue and to fund the revised engineering cost estimate with a City of Milwaukee share of $ $41,400 and a grantor share of $165,600.  The Revised Project Agreement provides for 20 percent local funds and 80 percent Federal and State funds for engineering and construction costs of the project.  The total estimated additional project cost is $ 1,617,000 of which the City of Milwaukee's share is $419,400, and the grantor share is $1,197,600.  The resolution authorizes the Commissioner of Public Works to request the comptroller to transfer additional funds for preliminary engineering.  Construction funds for the project will be requested in a future Common Council resolution.
Body
Whereas, A Project Agreement has been executed by the Wisconsin Department of Transportation (WisDOT) and the City of Milwaukee for the improvement of West Lloyd Street between North 60th Street and North 47th Street with Federal/State aid under the STP program in accordance with Common Council Resolution File Number 100021, adopted May 25, 2010; and
 
Whereas, The limits of this project have been extended to include West Lloyd Street between North 47th Street and West Lisbon Avenue; and
 
Whereas, The City has requested and the WisDOT has agreed to and provided a Revised Project Agreement to include the additional limits of West Lloyd Street; and
 
Whereas, The project is currently scheduled for construction in 2013; now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is hereby directed to execute a Revised Project Agreement with the WisDOT to include the added cost of work to extend the project limits of West Lloyd Street between North 47th Street and West Lisbon Avenue with 80 percent Federal and State Aid, a copy of which is attached to Common Council Resolution File Number 111462, and is incorporated in this resolution by reference as though set forth in full; and, be it
 
Further Resolved, That the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project/Grant Chartfield Values for the added segment of the project (Expenditure) and transfer the amount required under the grant agreement, limited to the federal caps, and the City Accounting Policy but not to exceed a 10 percent increase of the total amount reserved for the grantor's share and local share or $5,000, whichever is greater, as follows:
 
Infrastructure Services Division
State I.D. 2984-16-01
ST320100701
West Lloyd Street
North 60th Street to West Lisbon Avenue
 
City Share Non-Assessable Fund Paving
Project I.D. ST320120000
Fund 0333
$41,400
 
Grantor Reimbursable Fund Paving
Project I.D. SP032120100
Fund 0306
$145,160
 
Grantor Non-Reimbursable Cash Fund Paving
$20,440
 
Estimated total (additional) engineering: $207,000
 
Previously authorized for Preliminary Engineering: $330,000
Current estimated cost of total project including this resolution: $3,652,000
Original estimated cost of total project: $2,035,000
 
; and, be it
 
Further Resolved, That the City Engineer is hereby authorized and directed to approve and make periodic payments to the WisDOT upon receipt of invoices for the City's share of costs of the project.