File #: 021131    Version:
Type: Resolution Status: Passed
File created: 11/26/2002 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 12/20/2002
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
Sponsors: THE CHAIR
Indexes: ALLEY IMPROVEMENTS, PUBLIC IMPROVEMENTS, SIDEWALKS, SPECIAL ASSESSMENTS
Attachments: 1. Infr. Serv. Div. Cover Letter.pdf, 2. Fiscal Note.pdf
 
Number
021131
Version
SUBSTITUTE 1
Reference
900042
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
 
8th Aldermanic District
 
S. 47th St. - W. Manitoba St. to W. Cleveland Ave. (ST211030102) File Number 900042:  Asphalt pavement resurfacing, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Assessable Reconstruction Paving Fund -- $165,850; Nonassessable Reconstruction Paving Fund -- $55,323)
 
Alley between W. Grant St., W. Lincoln Ave., S. 17th St., and S. 18th St. (ST212030124) File Number 951703:  Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage facilities where needed. (Assessable Alley Paving Fund -- $41,600; Nonassessable Alley Paving Fund -- $14,600)
 
14th Aldermanic District
 
Alley between W. Euclid Ave., W. Oklahoma Ave., S. 15th Pl., and S. 16th St. (ST212030116) File Number 960740:  Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, and storm drainage facilities where needed. (Assessable Alley Paving Fund -- $36,800; Nonassessable Alley Paving Fund -- $8,100)
 
16th Aldermanic District
 
Alley between W. Galena St., W. Vliet St., N. 50th Pl., and N. 51st St. (ST212020108) File Number 941197:  Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage facilities where needed. (Assessable Alley Paving Fund -- $11,700; Nonassessable Alley Paving Fund -- $10,000)
 
; and
 
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
 
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works' Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it
 
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances, and, be it
 
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it
 
Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
 
Further Resolved, That projects: S. 47th St. (ST211030102), Alley W. Grant St. (ST212030124), Alley W. Euclid Ave. (ST212030116), and Alley W. Galena St. (ST212020108) will be billed after January 1, 2005, but not before 12 months after the project contract has been completed; and, be it
 
Further Resolved, That the following projects be deleted from the 2003 Paving Program.
 
7th Aldermanic District
 
N. 41st St. - W. Burleigh St. to W. Auer Ave. (ST211020126) File Number 000838
 
8th Aldermanic District
 
S. 47th St. - W. Oklahoma Ave. to W. Manitoba St.
 
S. 50th St. - W. Cleveland Ave. to W Jerelyn Pl. (ST211030103) File Number 930305
 
Alley between W. Manitoba St., W. Oklahoma Ave., S. 32nd St., and S. 33rd St. (ST212030102) File Number 941197
 
16th Aldermanic District
 
Alley between W. Clybourn St., W. St. Paul Ave., N. 39th St., and N. 40th St. (Except southerly 115 feet m/l) (ST212020104) File Number 951703
 
Requestor
Infrastructure Services Division
Drafter
mld:lk
afr5
12/11/02
 
 
Clerical error corrected 12/17/02.   mbh