Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,061,400 for a total estimated cost of $1,160,000.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $1,061,400. The total estimated cost of these projects is $1,160,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
5th Aldermanic District
Alley between W. Capitol Dr., W. Fiebrantz Ave., W. Fiebrantz Ct., N. 79th St., and N. 81st St. (ST212140101) File Number 111698: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage facilities where necessary. (Assessable Alley Paving Fund -- $20,200; Nonassessable Alley Paving Fund -- $65,000). The total estimated cost for this project including the requested amount is $95,000. This project is anticipated to be completed during the 2014 construction season.
7th Aldermanic District
W. Melvina St. - N. 27th St. to N. 30th St. (ST211130115) File Number 110564: Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (5 - 7-foot width of tree border area), grading, and tree removal where necessary. (Assessable Reconstruction Paving Fund -- $10,500; Nonassessable Reconstruction Paving Fund -- $230,000). The total estimated cost for this project including the requested amount is $258,000. This project is anticipated to be completed during the 2014 construction season.
8th Aldermanic District
W. Legion St. - S. 24th St. to S. Layton Blvd. (ST211120115) File Number 130596: Concrete pavement reconstruction, replace all curb and gutter, sidewalk and driveway approaches, sodding (0-foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $27,200; Nonassessable Reconstruction Paving Fund -- $235,000). The total estimated cost for this project including the requested amount is $285,000. This project is anticipated to be completed during the 2014 construction season.
9th Aldermanic District
N. 73rd St. - W. Calumet Rd. to W. Bradley Rd. (ST211130117) File Number 110688: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, install new sidewalk as necessary, sodding (6-foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $57,400; Nonassessable Reconstruction Paving Fund -- $370,000). The total estimated cost for this project including the requested amount is $457,000. This project is anticipated to be completed during the 2014 construction season.
10th Aldermanic District
Alley between W. Brooklyn Pl., N. Norwood Pl., W. Roosevelt Dr., and N. 55th St. (N. Norwood Pl. entrance) (ST212130114) File Number 121751: Replace driveways and alley approaches as necessary. (Assessable Alley Paving Fund -- $500; Nonassessable Alley Paving Fund -- $10,000). The total estimated cost for this project including the requested amount is $20,000. This project is anticipated to be completed during the 2014 construction season.
14th Aldermanic District
Alley between E. Fernwood Ave., S. Illinois Ave., S. Indiana Ave., and E. Oklahoma Ave. (ST212140129) File Number 121751: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage facilities where necessary. (Assessable Alley Paving Fund -- $10,600; Nonassessable Alley Paving Fund -- $25,000). The total estimated cost for this project including the requested amount is $45,000. This project is anticipated to be completed during the 2014 construction season.
; and
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works' Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it
Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That projects: W. Melvina St. (ST211130115), W. Legion St. (ST211120115), and Alley E. Fernwood Ave. (ST212140129) will be billed after January 1, 2016, but not before 12 months after the project contract has been completed; and, be it
Further Resolved, That project Alley W. Capitol Dr. (ST212140101) will be billed after January 1, 2017, but not before 12 months after the project contract has been completed.
Requestor
Infrastructure Services Division
Drafter
MLD:dr
Afr 8