Legislation Details

File #: 260662    Version:
Type: Resolution Status: Passed
File created: 9/1/2026 In control: COMMON COUNCIL
On agenda: Final action: 9/22/2026
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $89,665 for a total estimated cost of $104,600.
Sponsors: THE CHAIR
Attachments: 1. Ad 1.pdf, 2. Ad Signed.pdf, 3. Letter Signed.pdf, 4. AFR 1 (now Substitute 1)
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
9/23/20261 MAYOR SIGNED   Action details Meeting details Not available
9/22/20261 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
9/10/20260 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Appeared Holly Rutenbeck (DPW)
Pass4:0 Action details Meeting details Video Video
9/10/20261 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Appeared Holly Rutenbeck (DPW) 6th Aldermanic District N. 7th St. - W. Abert Pl. to W. Melvina St. (ST211260133). Install traffic calming speed humps(s). No public testimony. Ald. Taylor moved approval. The motion was approved without objection. N. Port Washington Ave. - W. Keefe Ave. to W. Vienna Ave. (ST211250157). Install traffic calming speed table. Appeared Jonathan Cherry - in support Appeared Samuel Sims - in support Jonathan Cherry and Samuel Sims testified regarding extreme reckless driving on Port Washington Avenue, reporting that over 50 cars frequently take over the street to race at speeds exceeding 100 mph. Mr. Cherry presented video evidence of racing, vehicles driving in bicycle lanes, and cars passing on shoulders, noting that police response has been inconsistent despite multiple 911 calls. Ald. Coggs is in support. Ald. Brower moved approval. The motion was approved without objection.
Pass5:0 Action details Meeting details Not available
9/1/20260 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

 

Number

260662

Version

SUBSTITUTE 1

Reference

250901

Sponsor

THE CHAIR

Title

Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $89,665 for a total estimated cost of $104,600.

Analysis

This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.  The City cost of these projects approved by this resolution is estimated to be $89,665.  The total estimated cost of these projects is $104,600.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

 

6th Aldermanic District

 

N. 7th St. - W. Abert Pl. to W. Melvina St. (ST211260133). Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $945; Nonassessable Reconstruction Paving Fund -- $8,655).  The total estimated cost of this project including the requested amount is $9,600. This project is anticipated to be completed during the 2026 construction season.

 

N. Port Washington Ave. - W. Keefe Ave. to W. Vienna Ave. (ST211250157). File Number 250901: Install traffic calming speed table. (Assessable Reconstruction Paving Fund -- $20,065; Nonassessable Reconstruction Paving Fund -- $60,000). The total estimated cost of this project including the requested amount is $95,000. This project is anticipated to be completed during the 2027 construction season.

 

; and

 

Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and

 

Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works’ Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it

 

Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it

 

Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That projects  N. 7th St. (ST211260133) and N. Port Washington Ave. (ST211250157) will be billed after January 1, 2029, but not before 12 months after the project contract has been completed.

 

Requestor

Infrastructure Services Division

Drafter

Holly Rutenbeck

AFR 1