Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
Sponsors: THE CHAIR
Indexes: ALLEY IMPROVEMENTS, PUBLIC IMPROVEMENTS, SIDEWALKS, SPECIAL ASSESSMENTS, STREET IMPROVEMENTS
NUMB:
991182
VERS:
SUBSTITUTE 1
REF:
980620
XXBY:
THE CHAIR
TITL:
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
ANLS:
-Analysis-
 
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.
BODY:
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
 
1st Aldermanic District
 
W. Fairmount Ave. - N. 28th St. to N. Teutonia Ave. (ST21100133) File Number 980620: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund -- $24,800; Assessable Reconstruction Paving Fund -- $4,500)
 
3rd Aldermanic District
 
Alley between E. Belleview Pl., E. Park Pl., N. Prospect Ave. and N. Stowell Ave. (ST21200109) File Number 970181: Concrete alley pavement reconstruction, replace some abutting sidewalk and driveway approaches, and grading. (Nonassessable Alley Paving Fund -- $32,800; Assessable Alley Paving Fund -- $16,700)
 
5th Aldermanic District
 
N. 98th St. - W. Lisbon Ave. to W. Capitol Dr. (ST21100123) File Number 920110: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund -- $54,600; Assessable Reconstruction Paving Fund -- $6,200)
 
6th Aldermanic District
 
Alley between W. Keefe Ave., W. Vienna Ave., N. 4th St. and N. 5th St. (Northerly 500 ft. m/l) (ST21200135) File Number 980909: Concrete alley pavement reconstruction, replace some abutting sidewalk and driveway approaches, and grading. (Nonassessable Alley Paving Fund -- $28,200; Assessable Alley Paving Fund -- $20,800)
 
8th Aldermanic District
 
W. Harrison Ave. - S. 6th St. to S. 13th St. (ST21100138) File Number 892058: Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund -- $392,700; Assessable Reconstruction Paving Fund -- $42,800)
 
Alley between W. Euclid Ave., W. Oklahoma Ave., S. 27th St. and S. 28th St. (East-West Leg) (ST21200130) File Number 980971: Concrete alley pavement reconstruction, replace some abutting sidewalk or driveway approaches, and grading. (Nonassessable Alley Paving Fund -- $26,200; Assessable Alley Paving Fund -- $8,300)
 
12th Aldermanic District
 
W. Scott St. - S. Cesar E. Chavez Dr. to S. 20th St. (ST21190165) File Number 881175: Asphalt pavement resurfacing, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund -- $166,700; Assessable Reconstruction Paving Fund -- $16,200)
 
Alley between W. National Ave., W. Pierce St., S. 2nd St. and S. 3rd St. (ST21200139) File Number 980790: Concrete alley pavement reconstruction, replace some abutting sidewalk or driveway approaches, and grading. (Nonassessable Alley Paving Fund -- $21,600; Assessable Alley Paving Fund -- $19,800)
 
14th Aldermanic District
 
Alley between S. Delaware Ave., E. Estes St., E. Trowbridge St. and S. Wentworth Ave. (ST21200126) File Number 980909: Concrete alley pavement reconstruction, replace some abutting sidewalk or driveway approaches, and grading. (Nonassessable Alley Paving Fund -- $20,000; Assessable Alley Paving Fund -- $11,900)
 
;and
 
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
 
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works' Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it
 
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it
 
Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
 
Further Resolved, That projects W. Fairmount Ave. (ST21100133), Alley Belleview Pl. (ST21200109), N. 98th St. (ST21100123), Alley W. Keefe Ave. (ST21200135), W. Harrison Ave. (ST21100138), Alley W. Euclid Ave. (ST21200130), W. Scott St. (ST21190165), Alley W. National Ave. (ST21200139), and Alley S. Delaware Ave. (ST21200126) will be billed after January 1, 2002, but not before 12 months after the project contract has been completed; and, be it
 
Further Resolved, That the following project be deleted from the 2000 Paving Program. 6th Aldermanic District Alley between N. Buffum St., E. Clarke St., N. Holton St. and E. Wright St. (ST21200113) File Number 980909.
 
 