File #: 260865    Version: 0
Type: Resolution Status: In Committee
File created: 10/13/2026 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action:
Effective date:    
Title: Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $380,000 for a total estimated cost of these projects being $1,315,000.
Sponsors: THE CHAIR

Number

260865

Version

ORIGINAL

Sponsor

THE CHAIR

Title

Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $380,000 for a total estimated cost of these projects being $1,315,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $380,000 with the total cost estimated to be $1,315,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

4th Aldermanic District

 

N. 3rd St. - W. Everett St. to W. Michigan St. (SM495260046) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost of the project including the requested amount is $128,000.  This project is anticipated to be completed during the 2027 construction season.

 

7th Aldermanic District

 

W. Bernhard Pl. - N. 42nd St. to N. Sherman Blvd. (ST211260143) Concrete pavement reconstruct, replacing curb and gutter, driveway approaches and sidewalk where necessary (0’ to 2’ width of tree border area), tree removal as necessary and grading. (Nonassessable Reconstruction Paving Fund -- $20,000).  The total estimated cost for this project including the requested amount is $450,000. This project is anticipated to be completed during the 2028-2029 construction season.

 

12th Aldermanic District

 

W. Bruce St. - S. 1st St. to S. 2nd St. (SM495260048) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost of the project including the requested amount is $165,000.  This project is anticipated to be completed during the 2027 construction season.

 

15th Aldermanic District

 

N. 50th St. - W. Clarke St. to W. Center St. (SM495260047) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost of the project including the requested amount is $222,000.  This project is anticipated to be completed during the 2027 construction season.

 

Various Aldermanic Districts

 

2027 Scattered Alley Concrete Panel Replacement - Maintenance (ST212260104) (Nonassessable Alley Paving Fund -- $300,000). The total estimated cost of this project including the requested amount is $300,000. This project is anticipated to be completed during the 2027 construction season.

 

ADA ramps for 2026 Area wide sidewalk repair areas (ST211260141) Replace curb and gutter and sidewalk as necessary (Nonassessable Reconstruction Paving Fund -- $15,000). The total estimated cost of this project including the requested amount is $185,000. This project is anticipated to be completed during the 2026-2027 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Holly Rutenbeck

NPR 3