File #: 971780    Version:
Type: Resolution Status: Passed
File created: 2/26/1998 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 3/20/1998
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
Sponsors: THE CHAIR
Indexes: ALLEY IMPROVEMENTS, PUBLIC IMPROVEMENTS, SIDEWALKS, SPECIAL ASSESSMENTS, STREET IMPROVEMENTS, STREET LIGHTING
NUMB:
971780
VERS:
SUBSTITUTE 1
REF:
960973
XXBY:
THE CHAIR
TITL:
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations.
ANLS:
-Analysis-
 
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.
BODY:
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
 
1st Aldermanic District
 
Alley between W. Courtland Ave., N. Green Bay Ave., W. Hampton Ave., N. Parkway Ave. and N. 18th St. (888-0727-6) File Number 960973: Concrete alley pavement reconstruction, replace some abutting sidewalk and driveway approaches, grading, and storm drainage facilities where needed. (Nonassessable Alley Paving Fund 31-523---212-0001 -- $50,250; Assessable Alley Paving Fund 71-523---212-0001 -- $31,730
 
1st and 9th Aldermanic Districts
 
W. Villard Ave. - N. Teutonia Ave. to N. Sherman Blvd. (892-0158-6) (2984-17-70) File Number 960092: Narrowing the entire roadway from 48 ft. to 44 ft.; asphalt pavement resurfacing between N. Teutonia Ave. and N. 35th St., and concrete pavement reconstruction between N. 35th St. and N. Sherman Blvd.; replace all curb and gutter, and driveway approaches, replace sidewalk where needed, sodding, and grading. (State or Federal Funds -- $940,825; Nonassessable State Aid Paving Fund 32-523---550-0001 -- $192,580; Assessable State Aid Paving Fund 71-523---550-0001 -- $91,770; and State/Federal Grantor Paving Fund 32-523---010-0000 -- $142,000; Business Improvement District DCD Fund -- $90,685)
 
2nd Aldermanic District
 
Alley between W. Hadley St., N. Lefeber Ave., W. Locust St., N. 72nd St. and N. 73rd St. (880-0645-2) File Number 881935: Concrete alley pavement reconstruction, replace some abutting sidewalk and driveway approaches, and grading. (Nonassessable Alley Paving Fund 31-523---212-0001 -- $45,020; Assessable Alley Paving Fund 71-523---212-0001 -- $9,515)
 
4th Aldermanic District
 
N. 6th St. - W. Clybourn Ave. to W. State St. (Excluding eastside between W. Wisconsin Ave. to W. Kilbourn Ave.) (690-0023-6) File Number 971679: Install special lighting. (Nonassessable Lighting Fund 31-523---060-0001 -- $10,980; Assessable Lighting Fund 71-523---060-0001 -- $154,020)
 
5th Aldermanic District
 
W. Grantosa Dr. (Northerly Roadway) - N. 94th St. to W. Byron Pl. (Portion in City of Wauwatosa) (878-0709-1) File Number 960854: Asphalt pavement resurfacing, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund 31-523---211-0001 -- $50,510; Assessable Reconstruction Paving Fund 71-523---211-0001 -- $18,605)
 
N. 84th St. - W. Grantosa Dr. to W. Villard Ave. (878-0705-X) File Number 960854: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund 31-523---211-0001 -- $143,905; Assessable Reconstruction Paving Fund 71-523---211-0001 -- $34,420)
 
12th Aldermanic District
 
S. 12th St. - W. Greenfield Ave. to W. National Ave. (877-0435-5) File Number 85-381: Asphalt pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund 31-523---211-0001 -- $287,760; Assessable Reconstruction Paving Fund 71-523---211-0001 -- $51,995)
 
S. 12th St. - W. National Ave. to W. Bruce St. (877-1435-3) File Number 971200: Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund 31-523---211-0001 -- $119,110; Assessable Reconstruction Paving Fund 71-523---211-0001 -- $37,330)
 
13th Aldermanic District
 
S. 17th St. - W. Howard Ave. to W. Crawford Ave. (870-0772-7) File Number 881710: Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund 31-523---211-0001 -- $85,465; Assessable Reconstruction Paving Fund 71-523---211-0001 -- $ 25,845)
 
17th Aldermanic District
 
W. Brown St. - N. 39th St. to W. Lisbon Ave. (873-0839-2) File Number 911748: Asphalt pavement resurfacing, replace all curb and gutter, replace sidewalk and driveway approaches where needed, sodding, and grading. (Nonassessable Reconstruction Paving Fund 31-523---211-0001 -- $95,790; Assessable Reconstruction Paving Fund 71-523---211-0001 -- $7,320)
 
;and
 
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
 
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works' Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it
 
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital purpose subaccounts; and, be it
 
Further Resolved, That the projects do not involve any parcels of land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
 
Further Resolved, That the City Engineer and the Commissioner of Public Works are hereby authorized to negotiate and enter into an agreement with the State of Wisconsin, Department of Transportation for the City to undertake construction management duties on the following project: W. Villard Ave. (892-0158-6)
 
;and, be it
 
Further Resolved, That the City Engineer is authorized and directed to approve and make periodic payments to the State of Wisconsin, Department of Transportation after receipt of invoices from said State for the City's share of the costs for said project:
 
W. Villard Ave. (892-0158-6) (2984-17-70) Nonassessable Fund 32-523---556-2610 -- $192,580 Assessable Fund 71-523---556-2610 -- $91,770
 
;and, be it
 
Further Resolved, That upon the completion of project 892-0158-6 and a determination of the actual cost, it is understood that if the City of Milwaukee's share is less than the amount previously paid, the difference will be refunded to said City; and, be it
 
Further Resolved, That projects W. Brown St. (873-0839-2); W. Grantosa Dr. (878-0709-1); W. Villard Ave. (892-0158-6); N. 6th St. (690-0023-6); S. 12th St. (877-0435-5); S. 12th St. (877-1435-3); S. 17th St. (870-0772-7); N. 84th St. (878-0705-X); Alley W. Courtland Ave. (888-0727-6) and Alley W. Hadley St. (880-0645-2) will be billed after January 1, 2000, but not before 12 months after the project contract has been completed.
DFTR:
INFRASTRUCTURE SERVICES DIVISION
MGL:sdp
03-11-98
971780.AFR