File #: 240615    Version:
Type: Resolution Status: Passed
File created: 9/3/2024 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 9/24/2024
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $5,183,000 for a total estimated cost of these projects being $6,341,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Resolution Certification 2555-07-70.pdf
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
9/30/20241 MAYOR SIGNED   Action details Meeting details Not available
9/24/20241 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
9/11/20240 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Appearing: Holly Rutenbeck, DPW Ald. Westmoreland moved substitution of the file with Proposed Substitute A. (Prevailed 5-0)
Pass5:0 Action details Meeting details Video Video
9/11/20241 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Not available
9/3/20240 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

240615

Version

SUBSTITUTE 1

Reference

200573

Sponsor

THE CHAIR

 

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $5,183,000 for a total estimated cost of these projects being $6,341,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $5,183,000.  The total estimated cost of these projects is $6,341,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

7th and 12th Aldermanic Districts

 

W. Burleigh St. - N. Sherman Blvd. to N. 20th St. and S. Cesar Chavez Dr. - W. Mitchell St. to W. Pierce St. (ST3202010XX) File Number 200573: Construct pedestrian and transit-oriented traffic calming improvements on W. Burleigh St. between N. Sherman Blvd. and N. 20th St. and S. Cesar Chavez Dr. between W. Mitchell St. and W. Pierce St. This project is anticipated to be completed during the 2025 construction season.

 

Grantor Non-Reimbursable Fund - $808,000

City Share Non-Assessable Fund - $202,000

 

These funds are to be transferred to the construction account (ST3202010XX) (2555-07-70)

 

Previously authorized for project construction: $0.00

Current estimated cost of construction including this resolution: $1,010,000

Current estimated total cost of the project including this resolution: $1,180,000

Original estimated cost of the project: (File Number 200573): $1,180,000

 

 

10th Aldermanic District

 

N. 50th Pl. - W. Vliet St. to 230’ North of W. Galena St. (SM495230051) File Number 231140: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $402,000). The total estimated cost of this project including the requested amount is $422,000. This project is anticipated to be completed during the 2025 construction season.

 

N. 51st St. - W. Vliet St. to W. Washington Blvd. (SM495240012) File Number 231828: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $513,000). The total estimated cost of this project including the requested amount is $533,000. This project is anticipated to be completed during the 2025 construction season.

 

N. 51st St. - W. Washington Blvd. to W. Vine St. (SM495240019) File Number 231828: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $261,000). The total estimated cost of this project including the requested amount is $276,000. This project is anticipated to be completed during the 2025 construction season.

 

N. 52nd St. - W. Vliet St. to W. Washington Blvd. (SM495230048) File Number 231140: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $396,000). The total estimated cost of this project including the requested amount is $416,000. This project is anticipated to be completed during the 2025 construction season.

 

N. 52nd St. - W. Washington Blvd. to W. Lloyd St. (SM495240010) File Number 231828: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $486,000). The total estimated cost of this project including the requested amount is $506,000. This project is anticipated to be completed during the 2025 construction season.

 

N. 53rd St. - W. Washington Blvd. to W. Vine St. (SM495240011) File Number 231828: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $312,000). The total estimated cost of this project including the requested amount is $327,000. This project is anticipated to be completed during the 2025 construction season.

 

11th Aldermanic District

 

S. 28th St. - W. Oklahoma Ave. to W. Euclid Ave. (SM495240023) File Number 231828: Relaying sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $407,000). The total estimated cost of this project including the requested amount is $427,000. This project is anticipated to be completed during the 2025 construction season.

 

W. Euclid Ave. - S. 27th St. to S. 31st St. (SM495240026) File Number 231828: Relaying sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $417,000). The total estimated cost of this project including the requested amount is $437,000. This project is anticipated to be completed during the 2025 construction season.

 

13th Aldermanic District

 

S. 24th St. - W. Euclid Ave. to W. Ohio Ave. (SM495240025) File Number 231828: Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $178,000). The total estimated cost of this project including the requested amount is $193,000. This project is anticipated to be completed during the 2025 construction season.

 

S. 26th St. - W. Oklahoma Ave. to W. Ohio Ave. (SM495230039) File Number 230975: Relaying sanitary and storm sewers. (Nonassessable Sewer Maintenance Relay Fund -- $609,000). The total estimated cost of this project including the requested amount is $624,000. This project is anticipated to be completed during the 2025 construction season.

 

Various Aldermanic Districts

 

Crack Filling of Various Streets by Contract (ST211240102) (Nonassessable Reconstruction Paving Fund -- $500,000). The total estimated cost for this project including the requested amount is $500,000. This project is anticipated to be completed during the 2024 construction season.

 

Sealcoating of Various Streets by Contract (ST211240101) (Nonassessable Reconstruction Paving Fund -- $500,000). The total estimated cost of this project including the requested amount is $500,000. This project is anticipated to be completed during the 2024 construction season.

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Holly Rutenbeck

NFR 1 Sub

9/6/2024