Number
110841
Version
Substitute 1
Reference
71689
Sponsor
THE CHAIR
Title
Substitute resolution authorizing the City Comptroller to transfer funds to various State or Federal Aid project subaccounts for the estimated remaining Wisconsin Department of Transportation and City of Milwaukee's preliminary engineering and construction costs being $140,000 with the City's share being $140,000 and the grantor's share being $0.00.
Analysis
This resolution authorizes the City Comptroller to transfer funds to the previously established subaccounts for the remaining Wisconsin Department of Transportation and City of Milwaukee's preliminary engineering and construction costs being $140,000. The City of Milwaukee's share is $140,000 and the grantor's share is $0.00
Body
Whereas, The Common Council has previously adopted resolutions authorizing the City Comptroller to transfer funds to various State or Federal Aid project subaccounts for preliminary engineering and Construction; and
Whereas, Additional funds are, therefore, necessary for the estimated remaining Wisconsin Department of Transportation and City of Milwaukee preliminary engineering and construction costs for these projects; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee that the City Comptroller is directed to transfer funds to the project grant chartfields as follows:
Project Grant Value
State I.D. 2555-06-70
ST320081210
W. Burleigh St-W. Roosevelt & N.60th St Intersection
City Share Non-Assessable Fund, Paving
ST320110000
Fund 0333
$20,000
Grantor Share
$0
Previously authorized for Construction: $128,826.50
Current estimated cost of total project including this resolution: $521,926.50
Original estimated cost of total project (Resolution 071689): $276,076.00
State I.D. 1009-00-17
ST320071101
Hopkins Street Elementary School Improvement .
City Share Non-Assessable Fund, Paving
ST320110000
Fund 0333
$10,000
Grantor Share
$0
Previously authorized for Engineering: $22,000
Current estimated cost of total project including this resolution: $137,500.00
Original estimated cost of total project (Resolution 070954): $62,500.00
State I.D. 2275-04-00
ST320071401
N 20th Street-West Hopkins St to W.Capitol Drive.
City Share Non-Assessable Fund, Paving
ST320110000
Fund 0333
$20,000
Grantor Share
$0
Previously authorized for Engineering: $183,485.85
Current estimated cost of total project including this resolution: $2,300,485.85
Original estimated cost of total project (Resolution 071072): $2,219,000.00
State I.D. 2219-00-70
ST520042210
S. 1st -E. Lincoln Ave to S. Kinnnickinnic Ave.
City Share Non-Assessable Fund, Paving
ST320110000
Fund 0333
$50,000
Grantor Share
$0
Previously authorized for Construction: $60,000
Current estimated cost of total project including this resolution:
$2,996,180.00
Original estimated cost of total project (Resolution 040400): $1,675,955.00
State I.D. 1300-06-01
ST320061401
S. and E. Bay St. - Lincoln Memorial Dr to Erie (Downtown to Bay view bikeway-Phase 1 &2)
City Share Non-Assessable Fund Paving
ST320110000
Fund 0333
$30,000
Previously authorized for Eng for Phase 1&2: $606,700.00
Current estimated cost of total project including this resolution: $2,428,851.00
Original estimated cost of total project (Res 060275): $2,428,851.00
State I.D. 2010-10-00
ST320070101
W. Appleton-W. Capital (STH 190) to USH 45
City Share Non-Assessable Fund Paving
ST320110000
Fund 0333
$10,000
Previously authorized for Engineering: $15,000.00
Current estimated cost of total project including this resolution: $10,625,000.00
Original estimated cost of total project (Res 061218): $10,600,000.00
Requestor
Department of Public Works
Drafter
Infrastructure Services Division
MK:amh
Oct 06, 2011
(6) Reso Vari Fed Sta Aid Pjec Saccou 100511.rtf