powered help
header-left header-center header-right
File #: 221581    Version: 0
Type: Resolution Status: Passed
File created: 2/7/2023 In control: COMMON COUNCIL
On agenda: Final action: 2/28/2023
Effective date:    
Title: Resolution authorizing the City Comptroller to transfer additional funds to the previously established project for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of South Dana Court Bridge in the 10th Aldermanic district with a total estimated cost increase for the projects of $60,000, with an estimated Grantor share of $0, and an estimated City share of $60,000.
Sponsors: THE CHAIR
Indexes: BRIDGES, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Certification Comptroller's Office

Number

221581

Version

ORIGINAL

Reference

 

Sponsor

THE CHAIR

Title

Resolution authorizing the City Comptroller to transfer additional funds to the previously established project for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of South Dana Court Bridge in the 10th Aldermanic district with a total estimated cost increase for the projects of $60,000, with an estimated Grantor share of $0, and an estimated City share of $60,000.

Analysis

Resolution authorizing the City Comptroller to transfer additional funds to the previously established projects for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of South Dana Court Bridge in the 10th Aldermanic district with a total estimated cost increase for the projects of $60,000, with an estimated Grantor share of $0, and an estimated City share of $60,000.

Body

Whereas, construction work has resulted in an increased cost charged against the capital improvement project; and

 

Whereas, Additional funds are, therefore, necessary to complete the construction of the projects; now, therefore be it

 

Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized to transfer fund to the project grant chart field as follows:

 

Project Grant Value

State ID 2984-51-70

ST320180710

South Dana Court Bridge

Land Bridge P-40-0589

 

City Share Non-Assessable Fund, Paving

ST320230000

Fund 0333

$30,000

 

City Share Non-Assessable Fund, Structure

BR300230000

Fund 0303

$30,000

 

 

Grantor Reimbursable Fund Paving

SP032230100

Fund 0306

$0.00

 

Grantor Reimbursable Fund Structure

SP032230100

Fund 0306

$0

 

Grantor Non-Reimbursable Cash Fund Paving

$ 0.00

 

Grantor Non-Reimbursable Cash Fund Structure 

$ 0.00

 

Estimated Total Construction - $60,000

 

Total construction previously authorized $1,327,680

Current estimated cost of total project including this resolution $1,561,200

Original estimated cost of total project (Resolution File Number 181112) $2,102,820

 

 

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

DAVID J TAPIA: C. Murphy

January 31, 2023