Number
252185
Version
ORIGINAL
Reference
251747
Sponsor
THE CHAIR
Title
Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $5,879,951.53 for a total estimated cost of these projects being $52,438,733.45.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $5,879,951.53. The total estimated cost of these projects is $52,438,733.45.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
8th Aldermanic District
W. Montana St. - S. 33rd St. to S. 35th St. (SM495250057) File Number 251747: Sanitary sewer relay and lining. (Nonassessable Sewer Maintenance Relay Fund -- $150,000, additional funds). The total estimated cost of the project including the requested amount is $562,000. This project is anticipated to be completed during the 2026 construction season.
W. National Ave. - S. 27th St. to S. 39th St. (ST3202004XX) (2410-10-70) File Number 191755: Asphalt pavement reconstruction, narrowing roadway, replace all curb and gutter, driveway approaches and sidewalk, storm sewer, sanitary sewer, traffic signals, street lighting, underground conduit, fiber optic, raised separated bike lanes, traffic calming, sodding (variable width of tree border area), tree removal where necessary, and grading. This project is anticipated to be completed during the 2026 construction season.
Grantor Non-Reimbursable Paving Fund -- $10,387,721.92
Grantor Reimbursable Paving Fund -- $1,558,158.29
City Share Non-Assessable Paving Fund -- $2,514,793.24
These funds are to be transferred to the construction accounts (ST3202004XX) (2410-10-70)
Previously authorized for project construction: $0.00
Current estimated cost of total project including this resolution: $48,626,773.45
Original estimated cost of the project (File Number 191755): $24,795,000
10th Aldermanic District
4600 West State Street (BR100240108) File 231828: Retaining Wall Replacement. (Non-assessable Structure Fund - $560,000). The total estimated cost for this project is $1,160,000. This project is anticipated to be completed during the 2026 construction season.
12th Aldermanic District
S. 15th Pl. - W. Cleveland Ave. to 620’ South of W. Cleveland Ave. (SM495250071) File Number 251287: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $243,000). The total estimated cost of this project including the requested amount is $258,000. This project is anticipated to be completed during the 2026 construction season.
S. 16th St. - W. Cleveland Ave. to 630’ +/- South of W. Cleveland Ave. (SM495250068) File Number 251147: Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $273,000). The total estimated cost of the project including the requested amount is $288,000. This project is anticipated to be completed during the 2026 construction season.
W. Cleveland Ave. - S. 15th St. to 300’+/- West of S. 16th St. (SM495250069) File Number 251147: Relaying sanitary and combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $381,000). The total estimated cost of this project including the requested amount is $401,000. This project is anticipated to be completed during the 2026 construction season.
14th Aldermanic District
S. Burrell St. - E. Dover St. to 150’ North of E. Dakota St. (SM495250037) File Number 251881: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $100,000, additional funds). The total estimated cost of this project including the requested amount is $935,000. This project is anticipated to be completed during the 2026 construction season.
E. Falling Heath Pl. - 225’+/- West of S. Swain Ct. to S. Swain Ct. (SM495250053) File Number 251614: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $100,000, additional funds). The total estimated cost of this project including the requested amount is $208,000. This project is anticipated to be completed during the 2026 construction season.
now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
Holly Rutenbeck
NFR 11
4/15/2026