File #: 151288    Version:
Type: Resolution Status: Passed
File created: 12/15/2015 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 1/19/2016
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,665,000 for a total estimated cost of these projects being $11,249,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
1/28/20161 MAYOR SIGNED   Action details Meeting details Not available
1/19/20161 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Not available
1/6/20161 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Proposed Substitute A
Pass4:0 Action details Meeting details Video Video
1/6/20161 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Jean Ziller, Department of Public Works
Pass4:0 Action details Meeting details Not available
12/15/20150 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

151288

Version

Substitute 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,665,000 for a total estimated cost of these projects being $11,249,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $1,665,000 with the total cost estimated to be $11,249,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

1st Aldermanic District

 

W. Elm St. - N. Teutonia Ave. to 1,600 feet west of N. Teutonia Ave. (WT410160010):  Hydrant alteration.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $45,000.  This project is anticipated to be completed during the 2016 construction season.

 

4th Aldermanic District

 

N. Broadway - E. Wells St. to E. Kilbourn Ave. (SM495160009):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $83,000 .  This project is anticipated to be completed during the 2016 construction season.

 

E. Mason St. - N. Milwaukee St. to N. Jefferson St. (SM495160011):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $35,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. Milwaukee St. - E. Mason St. to E. Wells St. (SM495160012):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $56,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. Highland Ave. - N. 12th St. to N. 27th St. (WT410160008):  Hydrant alteration.  (Nonassessable Water Fund Budget Line 5010 -- $1,000; Nonassessable Water Fund Budget Line 6410 -- $9,000).  The total estimated cost for this project including the requested amount is $15,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. Van Buren St. - E. Michigan St. to E. Wisconsin Ave. (WT410160719):  Abandon water main.  (Nonassessable Water Fund Budget Line 5010 -- $5,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $40,000.  This project is anticipated to be completed during the 2016 construction season.

 

4th and 15th Aldermanic Districts

 

N. 27th St. - W. Highland Blvd. to W. Lisbon Ave. (WT410160011):  Hydrant alterations.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $30,000.  This project is anticipated to be completed during the 2016 construction season.

 

6th Aldermanic District

 

W. Vine St. - N. Dr. Martin Luther King Jr. Dr. to N. 7th St. (SM495160008):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $342,000.  This project is anticipated to be completed during the 2016 construction season.

 

9th Aldermanic District

 

N. 60th St. - W. Florist Ave. to W. Mill Rd. (WT410160009):  Hydrant alterations.  (Nonassessable Water Fund Budget Line 5010 -- $2,000; Nonassessable Water Fund Budget Line 6410 -- $13,000).  The total estimated cost for this project including the requested amount is $30,000.  This project is anticipated to be completed during the 2016 construction season.

 

10th Aldermanic District

 

W. Fairview Ave. - N. 61st St. to N. 63rd St. (SM495160002):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $169,000.  This project is anticipated to be completed during the 2016 construction season.

 

10th and 15th Aldermanic Districts

 

W. Wisconsin Ave. - N. 37th St. to a point west of N. 39th St. (SM495160007):  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $443,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 37th St. - W. Wisconsin Ave. to 175 feet north of W. Wisconsin Ave. (SM495160013):  Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $82,000.  This project is anticipated to be completed during the 2016 construction season.

 

12th Aldermanic Districts

 

W. Walker St. - S. 2nd St. to S. 3rd St. (WT410160686):  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $5,000; Nonassessable Water Fund Budget Line 6410 -- $10,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2016 construction season.

 

13th Aldermanic District

 

Easement south of W. Barnard Ave. Extended - North/South Freeway to 90 feet west of North/South Freeway (SM495160010):  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $35,000.  This project is anticipated to be completed during the 2016 construction season.

 

14th Aldermanic District

 

S. Pennsylvania Ave. - E. Euclid Ave. to E. Fernwood Ave. (SM495160006):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $23,000.  This project is anticipated to be completed during the 2016  construction season.

 

15th Aldermanic District

 

W. Meinecke Ave. - N. 19th St. to N. 21st St. (SM495160004):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $252,000.  This project is anticipated to be completed during the 2016 construction season.

 

W. Wright St. - N. 20th St. to N. 22nd St. (SM495160005):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project including the requested amount is $261,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 21st St. - W. Wright St. to 250 feet north of W. Wright St. (SM495160014):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $71,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 48th St. - W. Meinecke Ave. to W. Wright St. (SM495160003):  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $42,000.  This project is anticipated to be completed during the 2016 construction season.

 

Various Aldermanic Districts

 

Bridge Indirect and Administration (BR100160101):  Preliminary engineering and administration of bridge projects.  (City Share Non-assessable Structure Fund -- $125,000).  The total estimated cost for this project $125,000.  This project is anticipated to be completed during the 2016 construction season.

 

Bridge Safety Inspection (BR100160102):  Federal and State mandated safety inspection of in-service bridges.  (City Share Non-assessable Structure Fund -- $200,000).  The total estimated cost for this project is $200,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 60th St. - W. Appleton Ave. to W. Burleigh St.; N. 81st St. - W. Calumet Rd. to

W. Bradley Rd.; N. 84th St. - W. Florist Ave. to W. Mill Rd.; N. 87th St. - W. Bradley Rd. to W. Tower Ave.; N. 100th St. - South of W. Hampton Ave. to W. Hampton Ave.; W. Calumet Rd. - N. 76th St. to N. 91st St.; W. Mill Rd. - Hwy. 41 to west City limits (ST216160101):  High impact streets asphalt overlay by contract.  (Nonassessable High Impact Streets Fund -- $5,000).  The total estimated cost for this project including the requested amount is $700,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 51st St. - W. Center St. to W. Burleigh St.; N. 86th St. - W. Capitol Dr. to W. Fiebrantz Ave. and W. Olive St. to W. Marion St.; N. 92nd St. - W. Lisbon Ave. to W. Capitol Dr.; N. Colgate Cr. - W. Fiebrantz Ave. to N. 88th St.; W. Hope Ave. - N. 84th St. to N. 85th St. and N. 89th St. to N. 91st St.; W. Olive St. - N. 85th St. to N. 89th St.; W. Villard Ave. - N. Sherman Blvd. to N. 51 Blvd. (ST216160102):  High impact streets asphalt overlay by contract. (Nonassessable High Impact Streets Fund -- $5,000).  The total estimated cost for this project including the requested amount is $800,000.  This project is anticipated to be completed during the 2016 construction season.

 

E. Chicago St. - N. Jackson St. to N. Milwaukee St. and N. Milwaukee St. to N. Water St.; N. Jefferson St. - E. Erie St. to E. Chicago St. and E. Chicago St. to E. St. Paul Ave.; N. Maryland Ave. - E. Hartford Ave. to E. Edgewood Ave.; N. Oakland Ave. - E. Park Pl. to E. Edgewood Ave.; N. Van Buren St. - E. Kilbourn Ave. to E. Ogden Ave. (ST216160103):  High impact streets asphalt overlay by contract. (Nonassessable High Impact Streets Fund -- $5,000).  The total estimated cost for this project including the requested amount is $1,100,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 37th St. - W. Fond du Lac Ave. to W. Townsend St.; W. Center St. - N. 20th St. to N. 27th St.; W. Lisbon Ave./ W. Walnut St. - N. 20th St. to N. 31st St.; W. Wells St. - N. 27th St. to N. 37th St. (ST216160104):  High impact streets asphalt overlay by contract. (Nonassessable High Impact Streets Fund -- $5,000).  The total estimated cost for this project including the requested amount is $1,000,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 6th St. - W. Walnut St. to W. Brown St./N. Halyard St.; N. Halyard St. - N. 6th St. to a point north of W. Garfield Ave.; W. Atkinson Ave. - W. Keefe Ave. to N. Teutonia Ave. (ST216160105):  High impact streets asphalt overlay by contract. (Nonassessable High Impact Streets Fund -- $5,000).  The total estimated cost for this project including the requested amount is $1,000,000.  This project is anticipated to be completed during the 2016 construction season.

 

N. 51st Blvd. - W. Capitol Dr. to W. Hampton Ave.; W. Roosevelt Dr. - N. 36th St. to W. Fond du Lac Ave. (ST216160106):  High impact streets asphalt overlay by contract. (Nonassessable High Impact Streets Fund -- $5,000).  The total estimated cost for this project including the requested amount is $900,000.  This project is anticipated to be completed during the 2016 construction season.

 

S. 14th St. - W. Maplewood Ct. to W. Abbott Ave.; S 15th Pl. - W. Maplewood Ct. to W. Mallory Ave. and W. Clayton Crest Ave. to W. Abbott Ave.; W. Abbott Ave. - S. 13th St. to S. 15th Pl.; W. Grange Ave. - S. Howell Ave. to S. 6th St.; W. Maplewood Ct. - S. 14th St. to S. 15th Pl.; W. Oklahoma Ave. - S. Chase Ave. to S. 6th St. (ST216160107):  High impact streets asphalt overlay by contract. (Nonassessable High Impact Streets Fund -- $5,000).  The total estimated cost for this project including the requested amount is $800,000.  This project is anticipated to be completed during the 2016 construction season.

 

S. 16th St. - W. Oklahoma Ave. to W. Windlake Ave.; S. 35th St. - W. Greenfield Ave. to W. National Ave.; W. Lincoln Ave. - S. 16th St. to S. Layton Blvd./ S. 27th St.; W. Morgan Ave. - W. Forest Home Ave. to S. 68th St. (ST216160108): High impact streets asphalt overlay by contract. (Nonassessable High Impact Streets Fund -- $5,000).  The total estimated cost for this project including the requested amount is $1,300,000.  This project is anticipated to be completed during the 2016 construction season.

 

Water Alterations - Developer Funded (WT430160300):  Alterations.  (Nonassessable Water Fund Budget Line 6410 -- $50,000).  The total estimated cost for this project is $50,000.  This project is anticipated to be completed during the 2016 construction season.

 

Work by Milwaukee Water Works prior to paving (WT410160730):  Alterations.  (Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2016 construction season.

 

Work done by Contractor-Paving (WT410160750):  Alterations.  (Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2016 construction season.

 

Work Done by Contractor-Sewer (WT410160770):  Alterations.  (Nonassessable Water Fund Budget Line 6410 -- $9,000).  The total estimated cost for this project including the requested amount is $50,000.  This project is anticipated to be completed during the 2016 construction season.

 

Suburban Plan Reviews (WT440160800):  Plan review.  (Nonassessable Water Fund Budget Line 6410 -- $50,000).  The total estimated cost for this project is $50,000.  This project is anticipated to be completed during the 2016 construction season.

 

Post Guarantee Work on Water Mains (WT440160850):  Inspection.  (Nonassessable Water Fund Budget Line 5010 -- $5,000).  The total estimated cost for this project is $5,000.  This project is anticipated to be completed during the 2016 construction season.

 

Material Inspection at Various Locations (WT410160880):  Inspection.  (Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project is $15,000.  This project is anticipated to be completed during the 2016 construction season.

 

2016 Indirect Account (SM495160001):  (Nonassessable Sewer Maintenance Relay Fund -- $800,000).  The total estimated cost for this project is $800,000.  This project is anticipated to be completed during the 2016 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/Denise Reinholtz

Npr 6