powered help
header-left header-center header-right
File #: 981692    Version:
Type: Resolution Status: Passed
File created: 3/23/1999 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 4/20/1999
Effective date:    
Title: Substitute resolution determining it necessary to make various assessable public improvements at various locations.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SIDEWALKS, STREET IMPROVEMENTS
NUMB:
981692
VERS:
SUBSTITUTE 1
XXBY:
THE CHAIR
TITL:
Substitute resolution determining it necessary to make various assessable public improvements at various locations.
ANLS:
-Analysis-
 
This resolution authorizes engineering studies and directs the Commissioner of Public Works to determine any benefits or damages which would result if the projects were to be constructed. After the Commissioner files his report, a Public Hearing will be held on those projects determined assessable. A resolution will be submitted after the Public Hearing authorizing construction.
BODY:
Resolved, By the Common Council of the City of Milwaukee that it is necessary and in the public interest to do the following described work according to City specifications, and that such public improvements and resulting special assessments be made pursuant to Section 66.60 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances:
 
2nd and 5th Aldermanic Districts
 
N. 76th St. - W. Appleton Ave. to W. Grantosa Dr. ST30683701 (890-0999-4): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work.
 
11th Aldermanic District
 
W. Morgan Ave. - S. 84th St. to W. Beloit Rd. ST32090101 (879-0911-7): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work.
 
13th Aldermanic District
 
Alley between W. Morgan Ave., W. Wilbur Ave., S. 18th St. and S. 19th St. (Center Portion) ST21290159 (889-0908-7): Paving the alley with concrete. Doing all the necessary grading pertaining to said work. (Nonassessable Alley Paving Fund -- $5,000)
 
15th Aldermanic District
 
W. Arch Ct. - 460 feet m/l east of N. 111th St. to 200 feet m/l east of N. 111th St. ST21490132 (839-0909-0): Paving the roadway with asphalt. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work.
 
16th Aldermanic District
 
W. State St. - N. 35th St. to a point west of N. Hawley Rd. (West City Limits) ST32090201 (879-0910-1): Paving the roadway with concrete. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work.
 
N. 54th St. - 300 feet m/l north of W. State St. to 600 feet m/l north of W. State St. ST21190246 (879-0907-5): Paving the roadway with concrete. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000)
 
N. 54th St. - 600 feet m/l north of W. State St. to W. Juneau Ave. (Ext'd) (Private Roadway) BU11086902 (879-0906-X): Paving the roadway with concrete. Laying a concrete curb and gutter. Laying concrete sidewalk. Doing all the necessary grading pertaining to said work. (Nonassessable Reconstruction Paving Fund -- $5,000)
 
;and, be it
 
Further Resolved, That the abutting and adjacent properties be assessed a portion of the cost, said assessment to be recommended by the Commissioner of Public Works in his report; and, be it
 
Further Resolved, That all assessments and payments be made in accordance with Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That all City departments are authorized to do engineering, surveying, preparing of plans, and estimates of cost thereof, to be utilized in the preparation of said report of the Commissioner of Public Works.
DFTR:
INFRASTRUCTURE SERVICES DIVISION
MGL:lmh
03-26-99
APR10-99