powered help
header-left header-center header-right
File #: 130363    Version:
Type: Resolution Status: Passed
File created: 7/2/2013 In control: COMMON COUNCIL
On agenda: Final action: 7/23/2013
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,089,000 for a total estimated cost of these projects being $2,399,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
7/25/20131 MAYOR SIGNED   Action details Meeting details Not available
7/23/20131 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Not available
7/10/20131 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
7/10/20130 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Individual appearing: Mary Dziewiontkoski, Department of Public Works Proposed Substitute A was accepted.
Pass4:0 Action details Meeting details Video Video
7/10/20131 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass4:0 Action details Meeting details Not available
7/10/20130 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/10/20130 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/2/20130 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available
Number
130363
Version
Substitute 1
Reference
130362
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $1,089,000 for a total estimated cost of these projects being $2,399,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $1,089,000.  The total estimated cost of these projects is $2,399,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
 
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
 
2nd Aldermanic District
 
W. Thurston Ave. - N. 94th St. to N. 97th St. (ST211130200) File Number 130362:  Pedestrian walkway.  Laying concrete walk.  Doing all necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $15,000).  The total estimated cost for this project including the requested amount is $20,000.  This project is anticipated to be completed during the 2013 construction season.
 
4th Aldermanic District
 
N. Milwaukee St. - E. Menomonee St. to E. St. Paul Ave. (ST211130173) File Number 121089:  Installation of median and special treatment.  (Nonassessable Reconstruction Paving Fund -- $215,000).  The total estimated cost for this project including the requested amount is $230,000.  This project is anticipated to be completed during the 2013 construction season.
 
11th and 13th Aldermanic Districts
 
S. 27th St. - 930 feet north of W. Oklahoma Ave. to W. Howard Ave. (WT410130016) File Number 130146:  Hydrant alteration.  (Nonassessable Water Fund Budget Line 5010 -- $3,000; Nonassessable Water Fund Budget Line 6410 -- $72,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2013 construction season.
 
12th Aldermanic District
 
S. 17th St. - S. Pearl St. to 200 feet m/l south of S. Pearl St. (SM495130049) File Number 130362:  Combined sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $14,000).  The total estimated cost for this project including the requested amount is $15,000.  This project is anticipated to be completed during the 2013 construction season.
 
13th Aldermanic District
 
S. Howell Ave. - W. Grange Ave. to W. College Ave. (WT410130015) File Number 121753:  Hydrant alteration.  (Nonassessable Water Fund Budget Line 6410 -- $15,000).  The total estimated cost for this project including the requested amount is $30,000.  This project is anticipated to be completed during the 2013 construction season.
 
14th Aldermanic District
 
S. Bay St. (East Side) - E. Potter Ave. to E. Conway St. (ST211130170) File Number 120700:  Laying concrete walk.  Doing all necessary grading pertaining to said work.  (Nonassessable Reconstruction Paving Fund -- $15,000).  The total estimated cost for this project including the requested amount is $25,000.  This project is anticipated to be completed during the 2013 construction season.
 
S. Carferry Dr. - E. Lincoln Ave. to 5,100 feet m/l north of E. Lincoln Ave. (SM495120085) File Number 130043:  Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $250,000, Additional Funds).  The total estimated cost for this project including the requested amount is $1,379,000.  This project is anticipated to be completed during the 2013 construction season.
 
Various Aldermanic Districts
 
Crackfilling of various streets by contract (ST211130181) File Number 121754:  (Nonassessable Reconstruction Paving Fund -- $40,000, Additional Funds).  The total estimated cost for this project including the requested amount is $140,000.  This project is anticipated to be completed during the 2013 construction season.
 
High Impact Streets - Asphalt resurface by contract - various locations (ST216130103) File Number 130362:  Asphalt pavement overlay.  (Nonassessable High Impact Streets -- $395,000).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2013 construction season.
 
City of Greenfield
 
S. 60th St. - W. Allerton Ave. to 1,236 feet south of W. Layton Ave. (WT410130676) File Number 120583:  Hydrant alteration.  (Nonassessable Water Fund Budget Line 6410 -- $55,000).  The total estimated cost for this project including the requested amount is $70,000.  This project is anticipated to be completed during the 2013 construction season.
 
now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it
 
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
 
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
 
Requestor
Infrastructure Services Division
Drafter
MLD:dr
Nfr 15