File #: 201550    Version:
Type: Resolution Status: Passed
File created: 3/23/2021 In control: COMMON COUNCIL
On agenda: Final action: 4/13/2021
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $362,300 for a total estimated cost of $430,300.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Signed Letter 10.pdf, 2. Cycle 10 Ad.pdf, 3. Signed Ad 10.pdf, 4. Notice published on 4-30-2021
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
4/30/20211 CITY CLERK PUBLISHED   Action details Meeting details Not available
4/19/20211 MAYOR SIGNED   Action details Meeting details Not available
4/13/20211 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Video Video
3/31/20211 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTION

Minutes note: Mary Dziewiontkoski - DPW 1st Aldermanic District N. Parkway Ave. – W. Glendale Ave. to N. 18th St. (ST211190131) Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, sodding (5’ width of tree border area), grading, and tree removal where necessary. Ald. Borkowski moved approval. (Prevailed 4-0) 2nd Aldermanic District W. Medford Ave. – N. 71st St. to N. 73rd St. (ST211180246) Install traffic calming speed hump(s). Ald. Zamarripa moved approval. (Prevailed 4-0) N. 57th St. – W. Villard Ave. to W. Custer Ave. (ST211170161) Install traffic calming speed hump(s). Ald. Stamper moved approval. (Prevailed 4-0) N. 62nd St. – W. Melvina St. to W. Capitol Dr. (ST211210114) Install traffic calming speed hump(s). Ald. Perez moved approval. (Prevailed 5-0) 5th Aldermanic District W. Nash St. – N. 79th St. to N. 81st St. (ST211210121) Install traffic calming speed hump(s). Lisa Kamutzki 3635 N 80th St stated she is in support of the speed humps because the speeding is rampant. Ald. Zamarripa moved approval. (Prevailed 5-0) W. Vienna Ave. – N. 82nd St. to N. 84th St. (ST211210122) Install traffic calming speed hump(s). Ald. Perez moved approval. (Prevailed 5-0) N. 83rd St. – W. Fiebrantz Ave. to W. Hope Ave. (ST211210117) Install traffic calming speed hump(s). Ald. Perez moved approval. (Prevailed 5-0) N. 93rd St. – W. Elmore Ave. to W. Melvina St. (ST211210119) Install traffic calming speed hump(s). Ald. Borkowski moved approval. (Prevailed 5-0)
Pass5:0 Action details Meeting details Video Video
3/23/20210 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

 

Number

201550

Version

SUBSTITUTE 1

Reference

181685

Sponsor

THE CHAIR

Title

Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $362,300 for a total estimated cost of $430,300.

Analysis

This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.  The City cost of these projects approved by this resolution is estimated to be $362,300.  The total estimated cost of these projects is $430,300.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

 

1st Aldermanic District

 

N. Parkway Ave. - W. Glendale Ave. to N. 18th St. (ST211190131) File Number 181685: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, sodding (5’ width of tree border area), grading, and tree removal where necessary. (Assessable Reconstruction Paving Fund -- $32,000; Nonassessable Reconstruction Paving Fund  -- $250,000).   The total estimated cost of this project including the requested amount is $350,000.  This project is anticipated to be completed during the 2021 construction season.

 

2nd Aldermanic District

 

W. Medford Ave. - N. 71st St. to N. 73rd St. (ST211180246) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $9,100; Nonassessable Reconstruction Paving Fund  -- $2,300).   The total estimated cost of this project including the requested amount is $11,400. This project is anticipated to be completed during the 2021 construction season.

 

N. 57th St. - W. Villard Ave. to W. Custer Ave. (ST211170161) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $15,200; Nonassessable Reconstruction Paving Fund  -- $2,000).   The total estimated cost of this project including the requested amount is $17,200. This project is anticipated to be completed during the 2021 construction season.

 

N. 62nd St. - W. Melvina St. to W. Capitol Dr. (ST211210114) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $6,500; Nonassessable Reconstruction Paving Fund  -- $2,000).   The total estimated cost of this project including the requested amount is $8,500. This project is anticipated to be completed during the 2021 construction season.

 

5th Aldermanic District

 

W. Nash St. - N. 79th St. to N. 81st St. (ST211210121) Install traffic calming speed

hump(s). (Assessable Reconstruction Paving Fund -- $3,600; Nonassessable Reconstruction Paving Fund  -- $8,400).   The total estimated cost of this project including the requested amount is $12,000. This project is anticipated to be completed during the 2021 construction season.

 

W. Vienna Ave. - N. 82nd St. to N. 84th St. (ST211210122) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $2,400; Nonassessable Reconstruction Paving Fund  -- $9,300).   The total estimated cost of this project including the requested amount is $11,700. This project is anticipated to be completed during the 2021 construction season.

 

N. 83rd St. - W. Fiebrantz Ave. to W. Hope Ave. (ST211210117) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $7,400; Nonassessable Reconstruction Paving Fund  -- $2,000).   The total estimated cost of this project including the requested amount is $9,400. This project is anticipated to be completed during the 2021 construction season.

 

N. 93rd St. - W. Elmore Ave. to W. Melvina St. (ST211210119) Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $8,100; Nonassessable Reconstruction Paving Fund  -- $2,000).   The total estimated cost of this project including the requested amount is $10,100. This project is anticipated to be completed during the 2021 construction season.

 

; and

 

Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and

 

Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works’ Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it

 

Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it

 

Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That projects:   N. Parkway Ave. (ST211190131), W. Medford Ave.  (ST211180246), N. 57th St. (ST211170161), N. 62nd St. (ST211210114), W. Nash St. (ST211210121), W. Vienna Ave. (ST211210122), N. 83rd St. (ST211210117), N. 93rd St. (ST211210119) will be billed after January 1, 2023, but not before 12 months after the project contract has been completed.

 

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/dl

Afr10

03/31/2021