Skip to main content
powered help
header-left header-center header-right
File #: 252025    Version: 0
Type: Resolution Status: In Committee
File created: 3/24/2026 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action:
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute a document titled “1st Revision State/Municipal Agreement for a State-Let Highway Project” with the Wisconsin Department of Transportation for the programming, design, real estate acquisition, and construction of North Farwell Avenue, East Bradford Avenue (STH 32) from North Prospect Avenue to North Lake Drive.
Sponsors: THE CHAIR
Attachments: 1. 2984-16-03_73 STH 32 CMil Prospect-LakeRev.pdf

Number

252025

Version

ORIGINAL

Reference

 

Sponsor

THE CHAIR

Title

Resolution directing the Commissioner of Public Works to execute a document titled “1st Revision State/Municipal Agreement for a State-Let Highway Project” with the Wisconsin Department of Transportation for the programming, design, real estate acquisition, and construction of North Farwell Avenue, East Bradford Avenue (STH 32) from North Prospect Avenue to North Lake Drive.

Analysis

This resolution directs the Commissioner of Public Works to execute a State/Municipal Agreement with the Wisconsin Department of Transportation for the programming, design, real estate acquisition, and construction of North Farwell Avenue, East Bradford Avenue (STH 32) from North Prospect Avenue to North Lake Drive. The State/Municipal Agreement provides for 75 percent Federal and State aid and 25 percent local cost sharing for preliminary engineering, and 100 percent Federal and State aid for real estate acquisition. The total estimated cost of this project is $29,015,500 with a City share of $5,620,767 and a grantor share of $23,394,733.  Construction funds for this project will be included in future resolutions.

Body

Whereas, A project agreement has been requested and received from the Wisconsin Department of Transportation (WisDOT) to be executed by the City of Milwaukee for the programming, design, real estate acquisition, and construction of North Farwell Avenue, East Bradford Avenue (STH 32) from North Prospect Avenue to North Lake Drive with Federal and State aid under the State Highway Rehabilitation Program; and

 

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee of project cost overruns and changes in scope approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be 100 percent liable for project cost overruns and changes in scope as approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be liable for any cost incurred by the State should the City decide to withdraw from the project; and

 

Whereas, Construction funds for the project will be included in a separate resolution; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is hereby authorized to execute the agreement for the programming, design, real estate acquisition, and construction of the aforementioned connecting highway project with Federal and/or State aid, copies of which are attached to Common Council Resolution File Number 252025, and are incorporated into this resolution by reference as though set forth in full; and, be it

 

Further Resolved, That the Commissioner of Public Works is hereby authorized to undertake or engage a consultant to undertake preliminary engineering and real estate acquisition services for the improvement of the aforementioned project and to reimburse the WisDOT for preliminary engineering and real estate costs they incur from the improvement; and, be it

 

Further Resolved, That the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project Grant Chartfield Values for design engineering for the project (Expenditure) and transfer to any of these accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater, as follows:

 

State I.D. 2984-16-03

North Farwell Avenue, East Bradford Avenue (STH 32) from North Prospect Avenue to North Lake Drive

Preliminary Engineering

 

City Share Non-Assessable Paving

ST320260000

Fund 0333

$0

 

Grantor Reimbursable Fund Paving

SP032260100

Fund 0306

$0

 

Grantor Non-Reimbursable

$0

 

State I.D. 2984-16-23

North Farwell Avenue, East Bradford Avenue (STH 32) from North Prospect Avenue to North Lake Drive

Real Estate Acquisition

 

City Share Non-Assessable Real Estate

ST320260000

Fund 0333

$0

 

Grantor Reimbursable Fund Real Estate

SP032260100

Fund 0306

$0

 

Grantor Non-Reimbursable

$0

 

Estimated Total Preliminary Engineering $1,650,000

Estimated Total Real Estate Acquisition $125,000

Total Engineering Previously Authorized $1,650,000

Total Real Estate Previously Authorized $125,000

Current Estimated Cost of Total Project Including this Resolution $29,015,500

Original Estimate Cost of Total Project (File #230396) $17,600,000

 

Further Resolved, That the City Engineer is hereby authorized to approve and make periodic payments to the WisDOT upon receipt of invoices for the City’s share of the project costs.

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

DAVID J TAPIA: K. Vos

March 18, 2026