Number
220872
Version
Substitute 1
Reference
210456
Sponsor
THE CHAIR
Title
Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $2,560,000 for a total estimated cost of these projects being $3,030,000.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $2,560,000. The total estimated cost of these projects is $3,030,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
1st and 7th Aldermanic Districts
N. 35th St. - W. Capitol Dr. to W. Congress St. (SM497210303) File Number 210456: Installing new storm sewer. (Flood Mitigation - Nonassessable --$500,000). The total estimated cost of this project including the requested amount is $675,000. This project is anticipated to be completed during the 2024 construction season.
W. Capitol Dr. - N. 31st St. to N. 35th St. (SM497210304) File Number 210456: Installing new storm sewer. (Flood Mitigation - Nonassessable --$500,000). The total estimated cost of this project including the requested amount is $750,000. This project is anticipated to be completed during the 2024 construction season.
4th Aldermanic District
N. Jefferson St. - E. Chicago St. to E. Buffalo St. (WT410220641) File Number 201552: Relaying water main and lead replacement of service. (Nonassessable Water Fund Budget Line 5010 -- $0. Nonassessable Water Fund Budget Line 6410 -- $170,000). The total estimated cost of this project including the requested amount is $185,000. This project is anticipated to be completed during the 2023 construction season.
5th Aldermanic District
W. Metcalf Pl. - 160’ East of N. 96th St. to N. 97th St. (WT410190606) File Number 171854: Relaying water main. (Nonassessable Water Fund Budget Line 5010 -- $0. Nonassessable Water Fund Budget Line 6410 -- $205,000). The total estimated cost of this project including the requested amount is $220,000. This project is anticipated to be completed during the 2022 construction season.
6th Aldermanic District
W. Locust St. - N. 8th St. to N. 13th St. (WT410220671) File Number 201552: Relaying water main, water main extension and lead replacement of service. (Nonassessable Water Fund Budget Line 5010 -- $0. Nonassessable Water Fund Budget Line 6410 -- $1,185,000). The total estimated cost of this project including the requested amount is $1,200,000. This project is anticipated to be completed during the 2023 construction season.
now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
Holly Rutenbeck/TW
NFR 3 Sub
10/14/2022