File #: 070266    Version:
Type: Resolution Status: Passed
File created: 5/30/2007 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 6/19/2007
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,467,000 for a total estimated cost of these projects being $18,848,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter.pdf, 2. Fiscal Note

Number

070266

Version

SUBSTITUTE 1

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $1,467,000 for a total estimated cost of these projects being $18,848,000.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $1,467,000 with the total cost estimated to be $18,848,000.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

3rd Aldermanic District

 

N. Cramer St. - E. Park Pl. to E. Locust St. (SM495070079):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $197,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. Hackett Ave. - E. Newberry Blvd. to E. Kenwood Blvd. (SM495070080):  Combined sewer relay and lining. (Nonassessable Sewer Maintenance Relay Fund -- $20,000).  The total estimated cost for this project including the requested amount is $430,000.  This project is anticipated to be completed during the 2008 construction season.

 

E. Newberry Blvd. - N. Cramer St. to N. Farwell Ave. (SM495070083):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. Prospect Ave. - A point 180 feet m/l south of E. Park Pl. to E. Kenwood Blvd. (SM495070063):  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000, additional funds).  File Number 070081 authorized $10,000. The total estimated engineering cost including this request is $20,000.  The total estimated cost for this project including the requested amount is $687,000. This project is anticipated to be completed during the 2008 construction season.

 

N. Wahl Ave. - A point 570 feet m/l southwest of E. Bradford Ave. to E. Bradford Ave. (SM495070074):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $11,000).  The total estimated cost for this project including the requested amount is $149,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. Warren Ave. - N. Franklin Pl. to a point 125 feet m/l north (SM495070090):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $37,000.  This project is anticipated to be completed during the 2008 construction season.

 

E. Windsor Pl. - N. Summit Ave. to N. Lake Dr. (SM495070087):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $66,000.  This project is anticipated to be completed during the 2008 construction season.

 

4th Aldermanic District

 

E. Buffalo St. - N. Water St. to N. Milwaukee St. (WT410081012):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. St. Paul Ave. - N. 9th  St. to N. 13th St. (WT410080012):  Relaying water main. (Nonassessable Water Fund -- $30,000).  The total estimated cost for this project including the requested amount is $425,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 12th St. - W. St. Paul Ave. to a point 200 feet m/l north of W. St. Paul Ave. (WT410080013):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $45,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 12th Ln. - A point 330 feet m/l south of W. Vliet St. to a point 140 feet m/l south of W. Vliet St. (SM495070089):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $40,000).  This project is anticipated to be completed during the 2008 construction season.

 

N. 27th St. - A point 240 feet m/l south of W. Clybourn St. to W. Clybourn St. (SW170060108):  Relaying combined sewer. (Nonassessable Expansion of Capacity Sewer Fund -- $20,000).  The total estimated cost for this project including the requested amount is $268,000.  This project is anticipated to be completed during the 2008 construction season.

 

5th Aldermanic District

 

W. Melvina St. - N. 77th St. to N. 83rd St. (WT410081004):  Relaying water main. (Nonassessable Water Fund -- $30,000).  The total estimated cost for this project including the requested amount is $450,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 76th St. - W. Lisbon Ave. to W. Nash St. (WT410080014):  Relaying water main. (Nonassessable Water Fund -- $40,000).  The total estimated cost for this project including the requested amount is $520,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 76th St. - W. Melvina St. to W. Appleton Ave. (WT410080015):  Relaying water main. (Nonassessable Water Fund -- $40,000).  The total estimated cost for this project including the requested amount is $425,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 77th St. - W. Vienna Ave. to W. Melvina St. (WT410081005):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $135,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 79th St. - W. Vienna Ave. to W. Capitol Dr. (WT410081003):  Relaying water main. (Nonassessable Water Fund -- $20,000).  The total estimated cost for this project including the requested amount is $255,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 91st St. - W. Burleigh St. to W. Concordia Ave. (WT410080017):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $360,000.  This project is anticipated to be completed during the 2008 construction season.

 

6th Aldermanic District

 

N. Humboldt Ave. - N. Riverboat Rd. to W. Garfield Ave. (WT410080011):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. Palmer St. - W. Meinecke Ave. to W. Wright St. (WT410081017):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $120,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Wright St. - N. Palmer St. to N. Dr. Martin Luther King Jr. Dr. (WT410081016):  Relaying water main. (Nonassessable Water Fund -- $20,000).  The total estimated cost for this project including the requested amount is $260,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 1st St. - W. Meinecke Ave. to W. Wright St. (WT410081018):  Relaying water main.  (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $70,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 2nd St. - W. Meinecke Ave. to W. Center St. (WT410081015):  Relaying water main. (Nonassessable Water Fund -- $30,000).  The total estimated cost for this project including the requested amount is $420,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 5th St. - W. Hadley St. to W. Chambers St. (SM495070042):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $616,000.  This project is anticipated to be completed during the 2008 construction season.

 

7th Aldermanic District

 

W. Courtland Ave. - N. 42nd St. to N. Sherman Blvd. (WT410081020):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. Sherman Blvd. - A point 40 feet m/l south of W. Glendale Ave. to W. Derby Ave. (WT410081019):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $230,000.  This project is anticipated to be completed during the 2008 construction season.

 

8th Aldermanic District

 

W. Greenfield Ave. - S. 26th St. to S. Layton Blvd. (SM495070100):  Combined sewer lining.  The total estimated cost for this project including the requested amount is $61,000.  This project is anticipated to be completed during the 2007 construction season.

 

W. Greves St. - N. 25th St. to N. 30th St. (SW170070111):  New storm sewer and combined relay. (Nonassessable Expansion of Capacity Sewer Fund -- $50,000).  The total estimated cost for this project including the requested amount is $1,404,000.  This project is anticipated to be completed during the 2007 construction season.

 

S. 22nd St. - A point 350 feet m/l north of W. Scott St. to W. Greenfield Ave. (SM495070072):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $143,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 24th St. - W. Becher St. to W. Grant St. (SM495070078):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $156,000.  This project is anticipated to be completed during the 2007 construction season.

 

S. 36th St. - W. National Ave. to W. Scott St. (WT410081013):  Relaying water main. (Nonassessable Water Fund -- $20,000).  The total estimated cost for this project including the requested amount is $225,000.  This project is anticipated to be completed during the 2008 construction season.

 

8th and 12th Aldermanic Districts

 

S. 21st St. - W. National Ave. to a point 350 feet m/l south of W. Mineral St. (SM495070073):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $16,000).  The total estimated cost for this project including the requested amount is $287,000.  This project is anticipated to be completed during the 2008 construction season.

 

9th Aldermanic District

 

N. 62nd St. - A point 225 feet m/l north of W. Bobolink Ave. to W. Thurston Ave. (SM495070070):  Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $11,000).  The total estimated cost for this project including the requested amount is $152,000.  This project is anticipated to be completed during the 2007 construction season.

 

W. Thurston Ave. - N. 60th St. to N. 62nd St. (SM495070069):  Sanitary sewer lining.  (Nonassessable Sewer Maintenance Relay Fund -- $9,000).  The total estimated cost for this project including the requested amount is $96,000.  This project is anticipated to be completed during the 2007 construction season.

 

10th Aldermanic District

 

N. 78th St. - W. Stevenson St. to W. Mt Vernon Ave. (SM495070094):  Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $210,000.  This project is anticipated to be completed during the 2007 construction season.

 

W. Mt. Vernon Ave. - N. 78th St. to N. 79th St. (SM495070092):  Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $93,000.  This project is anticipated to be completed during the 2007 construction season.

 

W. Stevenson St. - N. 76th St. to N. 78th St. (SM495070093):  Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $275,000.  This project is anticipated to be completed during the 2007 construction season.

 

W. Washington Blvd. - N. 51st St. to N. 59th St. (SW170070113):  Relaying combined sewer. (Nonassessable Expansion of Capacity Sewer Fund -- $50,000).  The total estimated cost for this project including the requested amount is $1,250,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Wells St. - N. 45th Pl. to a point 360 feet m/l west of N. 45th Pl. (WT410081002):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $100,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 45th Pl. - W. Wisconsin Ave. to W. Wells St. (WT410081001):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2008 construction season.

 

11th Aldermanic District

 

W. Coldspring Rd. at S. 60th St. (WT410081101):  Water main alteration. (Nonassessable Water Fund -- $20,000).  The total estimated cost for this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Forest Home Ave. at S. 54th St. (WT410081411):  Water main alteration. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $20,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Howard Ave. - S. 51st St. to S. 56th St. (WT410081402):  Relaying water main. (Nonassessable Water Fund -- $25,000).  The total estimated cost for this project including the requested amount is $320,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Howard Ave. - A point 145 feet m/l east of S. 58th St. to a point 120 feet m/l west of S. 58th St. (WT410081401):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $70,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Jerelyn Pl. - S. 53rd St. to W. Andover Rd. (WT410081006):  Relaying water main. (Nonassessable Water Fund -- $15,000):  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Tesch Ave. - A point 60 feet m/l east of S. 48th St. to S. 50th St. (WT410081405):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Van Beck Ave. - A point 800 feet m/l east of S. 50th St. to S. 51st St. (WT410081403):  Relaying water main. (Nonassessable Water Fund -- $20,000).  The total estimated cost for this project including the requested amount is $230,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 48th St. - W. Norwich St. to W. Tesch Ave. (WT410081406):  Relaying water main. (Nonassessable Water Fund -- $15,000):  The total estimated cost for this project including the requested amount is $80,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 50th St. - W. Van Beck Ave. to W. Tesch Ave. (WT410081404):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $125,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 53rd St. - A point 230 feet m/l north of W. Jerelyn Pl. to W. Jerelyn Pl. (WT410081007):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $50,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 58th St. - A point 170 feet m/l north of W. Howard Ave. to a point 80 feet m/l south of W. Howard Ave. (WT410081409):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 60th St. at W. Forest Home Ave. (WT410081410):  Water main alteration. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $20,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 63rd St. - W. Nebraska Ave. to W. Forest Home Ave. (WT410081412):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $85,000.  This project is anticipated to be completed during the 2008 construction season.

 

12th Aldermanic District

 

W. Burnham St. - S. 15th Pl. to S. 17th St. (SM495070015):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $146,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Hayes Ave. - S. 7th St. to S. 9th St. (WT410081026):  Water main extension. (Nonassessable Water Fund -- $20,000).  The total estimated cost for this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Walker St. - S. 13th St. (Extended) to S. 14th St. (SM495070084):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $46,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Washington St. - S. 15th St. to S. 18th St. (SM495070082):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $184,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 8th St. - W. Lincoln Ave. to W. Harrison Ave. (WT410081025):  Relaying water main. (Nonassessable Water Fund - $30,000).  The total estimated cost for this project including the requested amount is $400,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 15th Pl. - W. Lincoln Ave. to W. Cleveland Ave. (SM495060032):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $25,000).  The total estimated cost for this project including the requested amount is $488,000.  This project is anticipated to be completed during the 2007 construction season.

 

12th and 13th Aldermanic Districts

 

W. Windlake Ave. - S. 16th St. to S. 17th St. (SM495070085):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $53,000.  This project is anticipated to be completed during the 2008 construction season.

 

12th and 14th Aldermanic Districts

 

W. Cleveland Ave. - S. 14th St. to S. 15th St. (SM495070086):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000):  The total estimated cost for this project including the requested amount is $56,000.  This project is anticipated to be completed during the 2008 construction season.

 

13th Aldermanic District

 

W. Armour Ave. - A point 20 feet m/l east of S. 5th St. to S. 5th Pl. (WT410081022):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Martin Ln. - S. Howell Ave. to a point 580 feet m/l west of S. 1st St. (WT410081023):  Relaying water main. (Nonassessable Water Fund -- $15,000).

The total estimated cost for this project including the requested amount is $190,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 5th Pl. - W. Allerton Ave. to W. Armour Ave. (WT410081021):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $90,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 7th St. - W. Abbott Ave. to W. Mallory Ave. (WT410081024):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2008 construction season.

 

14th Aldermanic District

 

S. Brisbane Ave. - S. Clarence St. to E. Deer Pl. (SM495070088):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $146,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. Delaware Ave. - E. Ohio Ave. to E. Holt Ave. (SM495070091):  Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project including the requested amount is $76,000.  This project is anticipated to be completed during the 2008 construction season.

 

15th Aldermanic District

 

W. Garfield Ave. - N. 20th St. to N. 24th St. (SM495070095):  Relaying combined sewer.  The total estimated cost for this project including the requested amount is $306,000.  This project is anticipated to be completed during the 2007 construction season.

 

Water Easement 166 (Vacated W. Medford Ave.) at W. North Ave. (WT410081014):  Abandoning water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $175,000.  This project is anticipated to be completed during the 2008 construction season.

 

Greenfield

 

W. Allerton Ave. - A point 150 feet m/l east of S. Placid Dr. to a point 120 m/l east of S. 60th St. (WT410081011):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $215,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Bottsford Ave. - S. Placid Dr. to S. 60th St. (WT410081009):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $190,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Edgerton Ave. at S. 43rd St. (WT410081104):  Water main alteration. (Nonassessable Water Fund -- $20,000).  The total estimated cost for this project including the requested amount is $250,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Edgerton Ave. at S. 60th St. (WT410081103):  Water main alteration. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2008 construction season.

 

W. Layton Ave. at S. 60th St. (WT410081102):  Water main alteration. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. Placid Dr. - A point 130 feet m/l north of W. Bottsford Ave. to W. Allerton Ave. (WT410081010):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $105,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 43rd St. - A point 450 feet m/l north of W. Cold Spring Rd. to W. Cold Spring Rd. (WT410081408):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $120,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 43rd St. at a point 625 feet m/l south of W. Upham Ave. (WT410081105):  Water main alteration. (Nonassessable Water Fund -- $30,000).  The total estimated cost for this project including the requested amount is $1,200,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 45th St. - W. Howard Ave. to W. Van Beck Ave. (WT410081407):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. 59th St. - A point 165 feet m/l north of W. Bottsford Ave. to W. Bottsford Ave. (WT410081008):  Relaying water main. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $50,000.  This project is anticipated to be completed during the 2008 construction season.

 

Various Aldermanic Districts

 

Various locations. (WT410081300):  Alterations by Milwaukee Water Works prior to paving. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $50,000.  This project is anticipated to be completed during the 2008 construction season.

 

Various locations. (WT410081305):  Water main material inspection. (Nonassessable Water Fund -- $30,000).  The total estimated cost for this project including the requested amount is $30,000.  This project is anticipated to be completed during the 2008 construction season.

 

Various locations. (WT410081700):  Water main alterations by private contractors prior to sewer construction. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2008 construction season.

 

Various locations. (WT410081500):  Water main alterations by private contractors prior to paving. (Nonassessable Water Fund -- $15,000).  The total estimated cost for this project including the requested amount is $250,000.  This project is anticipated to be completed during the 2008 construction season.

 

Various Suburbs

 

Various locations. (WT440080000):  Review of consultant prepared surburban construction plans. (Nonassessable Water Fund -- $60,000).  The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2008 construction season.

 

; and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

Requestor

Infrastructure Services Division

Drafter

mld:lk

npr12