powered help
header-left header-center header-right
File #: 110354    Version:
Type: Resolution Status: Passed
File created: 7/6/2011 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 7/26/2011
Effective date:    
Title: Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $146,800 for a total estimated cost of these projects being $1,341,800.
Sponsors: THE CHAIR
Indexes: SEWER IMPROVEMENTS, SEWERS
Attachments: 1. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
8/4/20112 MAYOR SIGNED   Action details Meeting details Not available
7/26/20112 COMMON COUNCIL ADOPTEDPass14:0 Action details Meeting details Not available
7/26/20111 PUBLIC WORKS COMMITTEE RECONSIDEREDPass4:0 Action details Meeting details Not available
7/26/20112 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass4:0 Action details Meeting details Not available
7/26/20112 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Proposed Substitute B was accepted.
Pass4:0 Action details Meeting details Not available
7/22/20111 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/13/20111 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
7/13/20110 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Individual appearing: Clark Wantoch, Department of Public Works-Infrastructure Proposed Substitute A was accepted.
Pass5:0 Action details Meeting details Not available
7/13/20111 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Not available
7/11/20110 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/8/20110 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/8/20110 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
7/6/20110 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

110354

Version

Substitute 2

Sponsor

THE CHAIR

Title

Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $146,800 for a total estimated cost of these projects being $1,341,800.

Analysis

This resolution authorizes engineering studies on projects which by City Charter are nonassessable.  After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council.  The City cost for engineering these projects is estimated to be $146,800 with the total cost estimated to be $1,341,800.

Body

Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:

 

2nd Aldermanic District

 

W. Stark St. - N. 64th St. to N. 68th St. (SM495110534):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $2,000).  The total estimated cost for this project is $2,000.  This project is anticipated to be completed during the 2011-2012 construction season.

 

3rd Aldermanic District

 

Alley between N. Cramer St., E. Hampshire St., E. Hartford Ave., and N. Oakland Ave. (SM495110538):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $1,500).  The total estimated cost for this project is $1,500.  This project is anticipated to be completed during the 2011-2012 construction season.

 

4th Aldermanic District

 

W. McKinley Blvd. - N. 27th St. to N. 35th St. (SM495110539):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $70,000).  The total estimated cost for this project is $70,000.  This project is anticipated to be completed during the 2011-2012 construction season.

 

5th Aldermanic District

 

W. Bobolink Ave. - W. Appleton Ave. to N. Lovers Ln. Rd. (SM495110535):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $4,000).  The total estimated cost for this project is $4,000.  This project is anticipated to be completed during the 2011-2012 construction season.

 

W. Townsend St. - N. 76th St. to N. 82nd St. (SM495110540):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $20,000).  The total estimated cost for this project is $20,000.  This project is anticipated to be completed during the 2011-2012 construction season.

 

N. 79th St. - W. Keefe Ave. to W. Nash St. (SM495110541):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $12,000).  The total estimated cost for this project is $12,000.  This project is anticipated to be completed during the 2011-2012 construction season.

 

Alley between W. Capitol Dr., W. Melvina St., N. 80th St., and N. 81st St. (SM495110536):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $3,000).  The total estimated cost for this project is $3,000.  This project is anticipated to be completed during the 2011-2012 construction season.

 

6th Aldermanic District

 

W. North Ave. - N. 8th St. to N. 9th St. (SM495110537):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $10,000).  The total estimated cost for this project is $10,000.  This project is anticipated to be completed during the 2011-2012 construction season.

 

7th Aldermanic District

 

Area bounded by W. Congress St., W. Capitol Dr., N. Sherman Blvd., and N. 35th St. (#7) (SM494110105):  Sanitary sewer lining.  (Infiltration/Inflow Reduction Fund -- $1,000).  The total estimated cost for this project including the requested amount is $694,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. 42nd St. - W. Burleigh St. to W. Townsend St. (SM495110520):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $10,100, Additional Funds).  The total estimated cost for this project including the requested amount is $50,100.  This project is anticipated to be completed during the 2011 construction season.

 

8th Aldermanic District

 

Alley between W. Branting Ln., W. Greenfield Ave., S. 35th St., and S. 36th St. (SM495110542):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $2,000).  The total estimated cost for this project is $2,000.  This project is anticipated to be completed during the 2011-2012 construction season.

 

Alley between W. Dakota St., W. Montana St., S. 49th St., and S. 50th St. (SM495110543):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $2,000).  The total estimated cost for this project is $2,000.  This project is anticipated to be completed during the 2011-2012 construction season.

 

10th Aldermanic District

 

N. Alois St. - 175 feet m/l north of W. State St. to W. State St. (SM495110066):  Relay storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $1,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2011 construction season.

 

W. State St. - N. Alois St. to N. 50th St. (SM495110053):  Relay storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $1,000).  The total estimated cost for this project including the requested amount is $125,000.  This project is anticipated to be completed during the 2011 construction season.

 

N. 44th St. - W. Blue Mound Rd. to W. Wells St. (SM495110515):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $700, Additional Funds).  The total estimated cost for this project including the requested amount is $5,700.  This project is anticipated to be completed during the 2011-2012 construction season.

 

N. 50th St. - W. State St. to W. Juneau Ave. (SM495110052):  Relay storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $1,000).  The total estimated cost for this project including the requested amount is $260,000.  This project is anticipated to be completed during the 2011 construction season.

 

14th Aldermanic District

 

Alley between S. Austin St., S. Brisbane Ave., E. Euclid Ave., and E. Oklahoma Ave. (SM495110544):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $2,500).  The total estimated cost for this project is $2,500.  This project is anticipated to be completed during the 2011-2012 construction season.

 

Alley between S. Ellen St., S. Kinnickinnic Ave., E. Morgan Ave., and E. Vollmer Ave. (SM495110545):  Sewer work prior to paving.  (Nonassessable Sewer Maintenance Relay Fund -- $3,000).  The total estimated cost for this project is $3,000.  This project is anticipated to be completed during the 2011-2012 construction season.

 

;and, be it

 

Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Npr 15

07/22/2011