Substitute resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $2,287,000 for a total estimated cost of these projects being $15,096,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $2,287,000 with the total cost estimated to be $15,096,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:
1st Aldermanic District
N. Hopkins St. - 70’ +/- south of W. Rohr Ave. (ext) to W. Custer Ave. (SM495210111) Relaying storm sewer. Storm sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of this project including the requested amount is $147,000. This project is anticipated to be completed during the 2022 construction season.
3rd Aldermanic District
N. Shepard Ave. - E. Newport Ave. to E. Edgewood Ave. (SM495210119) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of this project including the requested amount is $265,000. This project is anticipated to be completed during the 2022 construction season.
4th and 12th Aldermanic Districts
6th Street Cable-Stayed Bridges over the Menomonee River (BR100220105): In Depth Inspection of Cable-Stayed Bridges. (City Share Non-assessable Structure Fund - $300,000). The total estimated cost for this project including the requested amount is $300,000. This project is anticipated to be completed during the 2022 construction season.
6th Aldermanic District
N. 1st St. - E./W. Meinecke Ave. to E./W. Wright St. (SM495210112) - Combined sewer relay and lining. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost of this project including the requested amount is $483,000. This project is anticipated to be completed during the 2022 construction season.
7th Aldermanic District
W. Nash St. - N. 38th St. to 150’ +/- west of N. 38th St. (SM495210114) Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost of this project including the requested amount is $40,000. This project is anticipated to be completed during the 2022 construction season.
N. 38th St. - W. Keefe Ave. to W. Roosevelt Dr. (SM495210113) Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000). The total estimated cost of this project including the requested amount is $508,000. This project is anticipated to be completed during the 2022 construction season.
10th Aldermanic District
N. 47th St. - W. Vliet St. to W. Cherry St. (SM495210110) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of this project including the requested amount is $119,000. This project is anticipated to be completed during the 2022 construction season.
14th Aldermanic District
S. 14th St. - 650’ +/- north of W. Dakota St. to W. Dakota St. (SM495210115) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of this project including the requested amount is $180,000. This project is anticipated to be completed during the 2022 construction season.
15th Aldermanic District
W. Wright St. - N. 35th St. to N. 36th St. (SM495210109) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $25,000). The total estimated cost of this project including the requested amount is $1,852,000. This project is anticipated to be completed during the 2022 construction season.
N. 37th St. - W. Clarke St. to W. Center St. (SM495210118) Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of this project including the requested amount is $172,000. This project is anticipated to be completed during the 2022 construction season.
City Wide
Miscellaneous Bridge Capitol Repairs (BR100220104): Bridge Maintenance construction repairs to various projects. (City Share Non-assessable Structure Fund - $150,000). The total estimated cost for this project is $150,000. This project is anticipated to be completed during the 2022 construction season.
Bridge Indirect and Administration (BR100220101): Preliminary engineering and administration of bridge projects. (City share Non-assessable Structure Fund $100,000). The total estimated cost for this project is $100,000. This project is anticipated to be completed during the 2022 construction season.
Bridge Safety Inspection (BR100220102): Federal and State mandated safety inspection of in-service bridges. (City share Non-assessable Structure Fund $210,000). The total estimated cost for this project is $210,000. This project is anticipated to be completed during the 2022 construction season.
Miscellaneous Bridge Design (BR100220103): Engineering related to various bridge maintenance projects. (City Share Non-assessable Structure Fund - $100,000). The total estimated cost for this project is $100,000. The project is anticipated to be completed during the 2021 construction season.
Water Alterations - Developer Funded (WT430220300) Alterations. (Nonassessable Water Fund Budget Line 5010 -- $ 1,000; Nonassessable Water Fund Budget Line 6410 - $49,000). The total estimated cost for this project including the requested amount is $50,000. This project is anticipated to be completed during the 2022 construction season.
Work by MWW Prior to Paving (WT410220730) Alterations. (Nonassessable Water Fund Budget Line 5010 -- $ 1,000; Nonassessable Water Fund Budget Line 6410 - $14,000). The total estimated cost for this project including the requested amount is $100,000. This project is anticipated to be completed during the 2022 construction season.
Work Done by Contractor/Paving (WT410220750) Alterations. (Nonassessable Water Fund Budget Line 5010 -- $ 1,000; Nonassessable Water Fund Budget Line 6410 - $19,000). The total estimated cost for this project including the requested amount is $200,000. This project is anticipated to be completed during the 2022 construction season.
Work Done by Contractor/Sewer Alterations (WT410220770) Alterations. (Nonassessable Water Fund Budget Line 5010 -- $ 1,000; Nonassessable Water Fund Budget Line 6410 - $14,000). The total estimated cost for this project including the requested amount is $150,000. This project is anticipated to be completed during the 2022 construction season.
Suburban Plan Reviews (WT440220800) Plan Review. (Nonassessable Water Fund Budget Line 5010 -- $ 1,000;Nonassessable Water Fund Budget Line 6410 - $49,000). The total estimated cost for this project including the requested amount is $50,000. This project is anticipated to be completed during the 2022 construction season.
Water Repairs/Distribution Referred (WT410220840) Water main repairs. (Nonassessable Water Fund Budget Line 5010 -- $ 1,000; Nonassessable Water Fund Budget Line 6410 - $14,000). The total estimated cost for this project including the requested amount is $150,000. This project is anticipated to be completed during the 2022 construction season.
Material Inspection at Various Locations (WT410220880) Inspection (Nonassessable Water Fund Budget Line 5010 -- $ 1,000; Nonassessable Water Fund Budget Line 6410 - $29,000). The total estimated cost for this project including the requested amount is $30,000. This project is anticipated to be completed during the 2022 construction season.
2022 Indirect Account (SM495220001) (Nonassessable Sewer Maintenance Relay Fund -- $250,000). The total estimated cost of this project including the requested amount is $250,000. This project is anticipated to be completed during the 2022 construction season.
2022 Paving Coordination (SM495220002) (Nonassessable Sewer Maintenance Relay Fund -- $75,000). The total estimated cost of this project including the requested amount is $75,000. This project is anticipated to be completed during the 2022 construction season.
2022 Sanitary Manhole Inspections (SM494220001) (Infiltration/Inflow Reduction Fund -- $12,000). The total estimated cost of this project including the requested amount is $200,000. This project is anticipated to be completed during the 2022 construction season.
2022 Sanitary Manhole Rehabilitation (SM494220002) (Infiltration/Inflow Reduction Fund -- $15,000). The total estimated cost of this project including the requested amount is $400,000. This project is anticipated to be completed during the 2022 construction season.
2022 Sewer Exam Requests (SM495220003) (Nonassessable Sewer Maintenance Relay Fund -- $125,000). The total estimated cost of this project including the requested amount is $125,000. This project is anticipated to be completed during the 2022 construction season.
2022 Sewer Structure Inspectons (SM495220004) (Nonassessable Sewer Maintenance Relay Fund -- $10,000). The total estimated cost of this project including the requested amount is $40,000. This project is anticipated to be completed during the 2022 construction season.
2022 Sewer Survey Requests (SM495220005) (Nonassessable Sewer Maintenance Relay Fund -- $400,000). The total estimated cost of this project including the requested amount is $400,000. This project is anticipated to be completed during the 2022 construction season.
2022 Sewer Work Prior To Paving (SM495220500) (Nonassessable Sewer Maintenance Relay Fund -- $20,000). The total estimated cost of this project including the requested amount is $1,500,000. This project is anticipated to be completed during the 2022 construction season.
Administration cost for street paving engineering (ST211210001) File Number 201065: (Nonassessable Reconstruction Paving Fund -- $200,000, additional funds). The total 2021 budget for the street resurface/reconstruction program is $6,750,000. These funds are to cover administration cost until 2022 funding is available.
;and, be it
Further Resolved, That all City Departments are authorized to perform engineering, surveys, plan preparation, and determine an estimated cost thereof; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.