Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $399,400 for a total estimated cost of $452,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS, SPECIAL ASSESSMENTS
Attachments: 1. Cover Letter, 2. Official Notice Number 50 Committee Actions, 3. Official Notice Number 50, 4. Hearing Notice List, 5. Notice Published on 4-9-13
Number
121551
Version
SUBSTITUTE 1
Reference
120700
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $399,400 for a total estimated cost of $452,000.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.  The City cost of these projects approved by this resolution is estimated to be $399,400.  The total estimated cost of these projects is $452,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
 
2nd Aldermanic District
 
N. 96th St. - W. Carmen Ave. to W. Flagg Ave. (ST211130118) File Number 120700:  Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (6 foot width of tree border area), and grading.  (Assessable Reconstruction Paving Fund -- $5,400; Nonassessable Reconstruction Paving Fund -- $35,000).  The total estimated cost for this project including the requested amount is $56,000.  This project is anticipated to be completed during the 2013 construction season.
 
8th Aldermanic District
 
W. Orchard St. - S. 20th St. to S. 21st St. (ST211120108) File Number 091545:  Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, narrow street from 38 feet to 36 feet, sodding (4-5 foot width of tree border area), and grading.  (Assessable Reconstruction Paving Fund -- $4,400; Nonassessable Reconstruction Paving Fund -- $100,000).  The total estimated cost for this project including the requested amount is $115,000.  This project is anticipated to be completed during the 2013 construction season.
 
10th Aldermanic District
 
W. Vienna Ave. - N. 66th St. to N. 68th St. (ST211080151) File Number 090760:  Install traffic calming speed hump(s).  (Assessable Reconstruction Paving Fund -- $4,800; Nonassessable Reconstruction Paving Fund -- $15,000).  The total estimated cost for this project including the requested amount is $20,000.  This project is anticipated to be completed during the 2013 construction season.
 
11th Aldermanic District
 
S. 66th St. - W. Euclid Ave. to W. Oklahoma Ave. (ST21100118) File Number 110922:  Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (7-9 foot width of tree border area), and grading.  (Assessable Reconstruction Paving Fund -- $2,300; Nonassessable Reconstruction Paving Fund -- $55,000).  The total estimated cost for this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2013 construction season.
 
13th Aldermanic District
 
W. Denis Ave. - S. 23rd St. to S. 26th St. (ST211070133) File Number 120980:  Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (7 foot width of tree border area), and grading.  (Assessable Reconstruction Paving Fund -- $12,500; Nonassessable Reconstruction Paving Fund -- $165,000).  The total estimated cost for this project including the requested amount is $186,000.  This project is anticipated to be completed during the 2013 construction season.
 
; and
 
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
 
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
 
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works' Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it
 
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
 
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it
 
Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
 
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
 
Further Resolved, That projects:  N. 96th St. (ST211130118), W. Orchard St. (ST211120108), W. Vienna Ave. (ST211080151), S. 66th St. (ST21100118), and W. Denis Ave. (ST211070133) will be billed after January 1, 2015, but not before 12 months after the project contract has been completed.
 
Requestor
Infrastructure Services Division
Drafter
MLD:dr
Afr 9