Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,812,000 for a total estimated cost of these projects being $4,104,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Infrastructure Services Division Cover Letter, 2. Fiscal Note

Number

071053

Version

SUBSTITUTE 1

Reference

061380

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $3,812,000 for a total estimated cost of these projects being $4,104,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $3,812,000.  The total estimated cost of these projects is $4,104,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

2nd and 7th Aldermanic Districts

 

N. 53rd St. - W. Nash St. to W. Melvina St. (SM495070036) File Number 061380:  Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $314,000).  The total estimated cost for this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2008 construction season.

 

3rd Aldermanic District

 

N. Commerce St. - E. North Ave. to a point 300 feet m/l north of E. North Ave. (WT410071090/WT420070001) File Number 070184:  Water main extension. (Nonassessable Expansion of Capacity Sewer Fund -- $25,000, additional funds).  File Number 070184 authorized $125,000.  The total estimated cost for this project including the requested amount is $150,000.  This project is complete.

 

7th Aldermanic District

 

W. Leon Tr. - W. Hoyt Pl. to W. Melvina St. (SM495070031) File Number 061380:  Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $35,000).  The total estimated cost for this project including the requested amount is $42,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 39th St. - W. Roosevelt Dr. to W. Capitol Dr. (SM495070035) File Number 061380:  Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $50,000).  The total estimated cost for this project including the requested amount is $58,000.  This project is anticipated to be completed during the 2008 construction season.

 

N. 48th St. - W. Center St. to W. Locust St. (SM495070034) File Number 061380:  Sanitary sewer lining and repair. (Nonassessable Sewer Maintenance Relay Fund -- $146,000).  The total estimated cost for this project including the requested amount is $158,000.  This project is anticipated to be completed during the 2008 construction season.

 

7th and 10th Aldermanic Districts

 

N. 49th St. - W. Burleigh St. to W. Chambers St. (SM495060047) File Number 061380:  Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $189,000).  The total estimated cost for this project including the requested amount is $196,000.  This project is anticipated to be completed during the 2008 construction season.

 

10th Aldermanic District

 

N. 54th St. - W. Center St. to W. Burleigh St. (SM495070012) File Number  061380:  Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $191,000).  The total estimated cost for this project including the requested amount is $203,000.  This project is anticipated to be completed during the 2008 construction season.

 

12th Aldermanic District

 

S. 1st St. - S. Kinnickinnic Ave. to W. Mitchell St. (SM495050060) File Number 050564:  Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $67,000).  The total estimated cost for this project including the requested amount is $76,000.  This project is anticipated to be completed during the 2008 construction season.

 

12th and 14th Aldermanic Districts

 

S. 8th St. - W. Lincoln Ave. to W. Arthur Ave. (SM495060041) File Number 060243:  Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $334,000).  The total estimated cost for this project including the requested amount is $349,000.  This project is anticipated to be completed during the 2008 construction season.

 

13th Aldermanic District

 

S. 19th St. - W. Holt Ave. to W. Ohio Ave. (SM495060086) File Number 061380:  Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $56,000).  The total estimated cost for this project including the requested amount is $66,000.  This project is anticipated to be completed during the 2008 construction season.

 

13th and 14th Aldermanic Districts

 

S. Howell Ave. - E. Wilbur Ave. to E. Howard Ave. (SM495070024) File Number 061380:  Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $135,000).  The total estimated cost for this project including the requested amount is $146,000.  This project is anticipated to be completed during the 2008 construction season.

 

14th Aldermanic District

 

E. Holt Ave. - S. Chase Ave. to S. Whitnall Ave. (SM495060018) File Number 061288:  Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $291,000).  The total estimated cost for this project including the requested amount is $318,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. Howell Ave. - A point 220 feet m/l north of E. Holt Ave. to E. Morgan Ave. (SM495060012) File Number 051658:  Sanitary and storm sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $206,000).  The total estimated cost for this project including the requested amount is $218,000.  This project is anticipated to be completed during the 2008 construction season.

 

E. Rosedale Ave. - S. Greeley St. to S. Howell Ave. (SM495070038) File Number 061380:  Relay combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $378,000).  The total estimated cost for this project including the requested amount is $396,000.  This project is anticipated to be completed during the 2008 construction season.

 

S. Whitnall Ave. - A point 160 feet m/l north of E. Holt Ave. to E. Holt Ave. (SM495070037) File Number 061380:  Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $15,000).  The total estimated cost for this project including the requested amount is $23,000. This project is anticipated to be completed during the 2008 construction season.

 

Various Aldermanic Districts

 

Various Locations (SM495080001) File Number 071055:  Engineering studies throughout the City of Milwaukee. (Sewer Maintenance Relay - Nonassessable $600,000).  The total estimated cost for this project including the requested amount is $600,000.  This project is anticipated to be completed during the 2008 construction season.

 

Various Locations (ST211080122) File Number 071055:  Asphalt resurfacing of various streets by contract. (Nonassessable Reconstruction Paving Fund  -- $300,000).  The total estimated cost for this project including the requested amount is $300,000.  This project is anticipated to be completed during the 2008 construction season.

 

Various Locations (ST211080123) File Number 071055:  Sealcoating of various streets by contract. (Nonassessable Reconstruction Paving Fund -- $280,000).  The total estimated cost for this project including the requested amount is $280,000.  This project is anticipated to be completed during the 2008 construction season.

 

Various Locations (ST211080124) File Number File Number 071055:  Crackfilling of various streets by contract. (Nonassessable Reconstruction Paving Fund -- $200,000).  The total estimated cost for this project including the requested amount is $200,000.  This project is anticipated to be completed during the 2008 construction season.

 

; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it

 

Further Resolved, That the following project be deleted from the 2007 Water Program.

 

W. Juneau Ave. - N. 35th St. to N. 38th St. (WT410071026) File Number 070267.

 

 

Requestor