File #: 091546    Version:
Type: Resolution Status: Passed
File created: 3/24/2010 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 4/13/2010
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $3,048,200 for a total estimated cost of $3,649,500.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Official Notice Number 73 committee actions, 3. Official Notice Number 73, 4. Sub. 2 Fiscal note, 5. Fiscal Note, 6. Hearing Notice List
Date Ver.Action ByActionResultTallyAction DetailsMeeting DetailsVideo
4/29/20102 CITY CLERK PUBLISHED   Action details Meeting details Not available
4/22/20102 MAYOR SIGNED   Action details Meeting details Not available
4/13/20102 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
4/13/20102 COMMON COUNCIL ADOPTEDPass15:0 Action details Meeting details Not available
4/13/20101 COMMON COUNCIL AMENDED

Minutes note: Ald. Hamilton moved to amend by adding the following: 1st Aldermanic District W. Lawn Ave. - N. 13th St. to N. Green Bay Ave. (ST211090114) File Number) 091545: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, sodding (3.5-foot width of tree border area), grading, tree removal where necessary, and install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $52,800; Nonassessable Reconstruction Paving Fund -- $250,000). The total estimated cost for this project including the requested amount is $378,000. This project is anticipated to be completed during the 2010 construction season. This amendment would also increase the total estimated dollar amounts in the title from $2,745,400 to $3,048,200 and from $3,271,500 to $3,649,500.
Pass15:0 Action details Meeting details Not available
4/1/20101 CITY CLERK DRAFT SUBMITTED   Action details Meeting details Not available
3/30/20101 PUBLIC WORKS COMMITTEE RECOMMENDED FOR ADOPTIONPass5:0 Action details Meeting details Not available
3/30/20100 PUBLIC WORKS COMMITTEE SUBSTITUTED

Minutes note: Individual present: Mary Dziewiontkowski, Dept. of Public Works
Pass5:0 Action details Meeting details Not available
3/26/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/26/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/26/20100 PUBLIC WORKS COMMITTEE HEARING NOTICES SENT   Action details Meeting details Not available
3/24/20100 COMMON COUNCIL ASSIGNED TO   Action details Meeting details Not available

Number

091546

Version

SUBSTITUTE 2

Reference

091545

Sponsor

THE CHAIR

Title

Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $3,048,200 for a total estimated cost of $3,649,500.

Analysis

This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held.  The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements.  The City cost of these projects approved by this resolution is estimated to be $3,048,200.  The total estimated cost of these projects is $3,649,500.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

 

1st Aldermanic District

 

W. Lawn Ave. - N. 13th St. to N. Green Bay Ave. (ST211090114) File Number 091545:  Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, sodding (3.5-foot width of tree border area), grading, tree removal where necessary, and install traffic calming speed hump(s).  (Assessable Reconstruction Paving Fund -- $52,800; Nonassessable Reconstruction Paving Fund -- $250,000).  The total estimated cost for this project including the requested amount is $378,000.  This project is anticipated to be completed during the 2010 construction season.

 

9th Aldermanic District

 

W. Brown Deer Rd. - N. 91st St. to N. 124th St. (State Highway 100) (ST320071001) (2150-05-70) File Number 090048:  Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where needed, including installation of new walk, sodding, adjustments to City of Milwaukee water and sanitary sewer appurtenances and grading.

 

Grantor Non-Reimbursable Paving Fund -- $2,244,000

 

City Share Non-assessable Paving Fund --$ 40,700

 

City Share Assessable Paving Fund --$25,300

 

These funds are to be transferred to the construction account (ST320071010)

(2150-05-70)

 

Previously authorized for street construction:  $0.00

Current estimated cost of the total project including this resolution: $2,796,500

Original estimated cost of the total project (File Number 090048):  $2,776,500.00

This project is anticipated to be completed during the 2010 construction season.

 

10th Aldermanic District

 

W. Notre Dame Ct. - A Point east of N. Hawley Rd. to N. Hawley Rd. (ST211100126) File Number 090010:  Concrete pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (6.5 - 7.5-foot width of tree border area), and grading.  (Assessable Reconstruction Paving Fund -- $11,000; Nonassessable Reconstruction Paving Fund -- $125,000).  The total estimated cost for this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2010 construction season.

 

11th Aldermanic District

 

S. 80th St. - W. Wilbur Ave. to W. Morgan Ave. (ST211030129) File Number 081486:  Concrete/Asphalt pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (7.0-foot width of tree border area), and grading.  (Assessable Reconstruction Paving Fund -- $24,400; Nonassessable Reconstruction Paving Fund -- $275,000).  The total estimated cost for this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2010 construction season.

 

; and

 

Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and

 

Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works’ Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it

 

Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it

 

Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it

 

Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it

 

Further Resolved, That the City Engineer and the Commissioner of Public Works are hereby authorized to negotiate and enter into an agreement with the State of Wisconsin, Department of Transportation for the City to undertake construction management duties on the following project: W. Brown Deer Rd. (ST320071001); and, be it

 

Further Resolved, That the City Engineer is authorized and directed to approve and make periodic payments to the State of Wisconsin, Department of Transportation after receipt of invoices from said State for the City's share of the costs for said project: W. Brown Deer Rd. (ST320071001); and, be it

 

Further Resolved, That upon the completion of project W. Brown Deer Rd. ST320071001) and a determination of the actual cost(s), it is understood that if the City of Milwaukee's share is less than the amount previously paid, the difference will be refunded to said City; and be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That projects: W. Lawn Ave. (ST211090114), W. Brown Deer Rd. (ST320071001), W. Notre Dame Ct. (ST211100126), and S. 80th St. (ST211030129) will be billed after January 1, 2012, but not before 12 months after the project contract has been completed.

 

Requestor

Infrastructure Services Division

Drafter

MLD:dr

Afr 10

03/31/2010