Skip to main content
powered help
header-left header-center header-right
File #: 251476    Version: 0
Type: Resolution Status: In Council-Adoption
File created: 12/16/2025 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action:
Effective date:    
Title: Resolution directing the Commissioner of Public Works to execute a document titled “State/Municipal Agreement for a State-Let Highway Project” with the Wisconsin Department of Transportation for the programming, design and construction of South Cesar Chavez and South 16th Street intersections with Burnham, Mitchell and Lapham, and to set up funds for design engineering at an estimated total cost of $500,000 with an estimated City share of $50,000 and a grantor share of $450,000.
Sponsors: THE CHAIR
Attachments: 1. 2615-08-02_72 CesarChavez_16th_Burnham_Mitchell_Lapham CMil.pdf, 2. Resolution Certification 2615-08-02.pdf

Number

 251476

Version

ORIGINAL

Reference

Sponsor

THE CHAIR

Title

Resolution directing the Commissioner of Public Works to execute a document titled “State/Municipal Agreement for a State-Let Highway Project” with the Wisconsin Department of Transportation for the programming, design and construction of South Cesar Chavez and South 16th Street intersections with Burnham, Mitchell and Lapham, and to set up funds for design engineering at an estimated total cost of $500,000 with an estimated City share of $50,000 and a grantor share of $450,000. 

Analysis

This resolution directs the Commissioner of Public Works to execute a State/Municipal Agreement with the Wisconsin Department of Transportation for the programming, design and construction of South Cesar Chavez/South 16th Street intersections with Burnham, Mitchell and Lapham.  The State/Municipal Agreement provides for 90 percent Federal and State aid and 10 percent local cost sharing for preliminary engineering.  The total estimated cost of this project is $4,013,663 with an estimated City share of $423,866 and a grantor share of $3,589,797. 

Body

Whereas, A project agreement has been requested and received from the Wisconsin Department of Transportation (WisDOT) to be executed by the City of Milwaukee for the programming, design, and construction of South Cesar Chavez/South 16th Street intersections with Burnham, Mitchell and Lapham with Federal aid under the Highway Safety Improvement Program (HSIP); and

 

Whereas, The Department of Public Works shall notify the Common Council of the City of Milwaukee of project cost overruns and changes in scope approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be 100 percent liable for project cost overruns and changes in scope as approved by the Department of Public Works; and

 

Whereas, The Common Council of the City of Milwaukee recognizes that the City may be liable for any cost incurred by the State should the City decide to withdraw from the project; and

 

Whereas, Construction funds for the project will be included in a separate resolution; now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is hereby authorized to execute the agreement for the programming, design, and construction of the aforementioned connecting highway project with Federal and/or State aid, copies of which are attached to Common Council Resolution File Number 251476, and are incorporated into this resolution by reference as though set forth in full; and, be it

 

Further Resolved, That the City Comptroller is hereby authorized to create within the Capital Improvement Fund, Grant and Aid Projects, the necessary Project Grant Chartfield Values for construction for the project (Expenditure) and transfer to any of these accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10 percent increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater, as follows:

 

State I.D. 2615-08-02

South Cesar Chavez/ South 16th Street

Intersections with Burnham, Mitchell and Lapham  

 

City Share Non-Assessable Fund Paving

ST320260000

Fund 0333

$50,000

 

Grantor Reimbursable Fund Paving

SP032260100

Fund 0306

$427,500

 

Grantor Non-Reimbursable

$22,500

 

Estimated Total Engineering $500,000

Total Engineering Previously Authorized $0

Current Estimated Cost of Total Project Including this Resolution $4,013,663

Original Estimate Cost of Total Project $4,013,663

 

Further Resolved, That the City Engineer is hereby authorized to approve and make periodic payments to the WisDOT upon receipt of invoices for the City’s share of the project costs.

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

ARETA ABEDINI: K. Vos

December 9, 2025