Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $1,983,800 for a total estimated cost of $2,212,000.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $1,983,800. The total estimated cost of these projects is $2,212,000.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:
5th Aldermanic District
W. Hadley St. - N. 80th St. to N. 86th St. (ST211130104) File Number 101348: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (6-7 foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $7,700; Nonassessable Reconstruction Paving Fund -- $250,000). The total estimated cost for this project including the requested amount is $278,000. This project is anticipated to be completed during the 2012-2013 construction season.
8th Aldermanic District
S. 24th St. - W. Greenfield Ave. to W. Scott St. (ST21110133) File Number 091545: Asphalt pavement resurfacing, narrow 40 feet to 36 feet, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (0-5 foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $13,200; Nonassessable Reconstruction Paving Fund -- $110,000). The total estimated cost for this project including the requested amount is $141,000. This project is anticipated to be completed during the 2012-2013 construction season.
11th Aldermanic District
W. Warnimont Ave. - S. 84th St. to S. 91st St. (ST211120145) File Number 100214: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (7 foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $13,200; Nonassessable Reconstruction Paving Fund -- $275,000). The total estimated cost for this project including the requested amount is $313,000. This project is anticipated to be completed during the 2012-2013 construction season.
S. 51st St. - W. Crawford Ave. to W. Wilbur Ave. (City of Milwaukee Portion) (ST211030125) File Number 051660: Asphalt pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (6 foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $2,000; Nonassessable Reconstruction Paving Fund -- $110,000). The total estimated cost for this project including the requested amount is $127,000. This project is anticipated to be completed during the 2012-2013 construction season.
13th Aldermanic District
S. 23rd St. - W. Edgerton Ave. to W. Layton Ave. (ST211110109) File Number 111166: Asphalt pavement resurfacing, replace curb and gutter, sidewalk and driveway approaches where necessary, sodding (5-7 foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $20,200; Nonassessable Reconstruction Paving Fund -- $255,000). The total estimated cost for this project including the requested amount is $300,000. This project is anticipated to be completed during the 2012-2013 construction season.
14th Aldermanic District
S. Delaware Ave. - E. Oklahoma Ave. to 75 feet north of E. Oklahoma Ave. (ST211120188) File Number 111575: Construct curb and gutter, sodding and grading. (Assessable Reconstruction Paving Fund -- $500; Nonassessable Reconstruction Paving Fund -- $20,000). The total estimated cost for this project including the requested amount is $28,000. This project is anticipated to be completed during the 2012 construction season.
Alley between S. Ellen St., S. Kinnickinnic Ave., and E. Rusk Ave. (ST212060117) File Number 061097: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage facilities where necessary. (Assessable Alley Paving Fund -- $20,000; Nonassessable Alley Paving Fund -- $100,000). The total estimated cost for this project including the requested amount is $133,000. This project is anticipated to be completed during the 2012-2013 construction season.
15th Aldermanic District
W. Clarke St. - N. 20th St. to W. Monroe St. (except N. 23rd St. to N. 24th St.) (ST211120184) File Number 111280: Asphalt pavement resurfacing, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (4-5 foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $11,000; Nonassessable Reconstruction Paving Fund -- $200,000). The total estimated cost for this project including the requested amount is $221,000. This project is anticipated to be completed during the 2012 construction season.
N. 26th St. - W. Meinecke Ave. to W. Medford Ave. (ST211110185) File Number 110833: Asphalt pavement resurfacing, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (5 foot width of tree border area), and grading. (Assessable Reconstruction Paving Fund -- $5,000; Nonassessable Reconstruction Paving Fund -- $60,000). The total estimated cost for this project including the requested amount is $125,000. This project is anticipated to be completed during the 2012 construction season.
N. 29th St. - W. Meinecke Ave. to W. Center St. (ST211110103) File Number 101270: Pavement reconstruction, replace all curb and gutter, replace sidewalk and driveway approaches where necessary, sodding (4 foot width of tree border area), grading, and install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $30,000; Nonassessable Reconstruction Paving Fund -- $481,000). The total estimated cost for this project including the requested amount is $546,000. This project is anticipated to be completed during the 2012-2013 construction season.
; and
Whereas, The report of the Commissioner of Public Works has been filed with the City Clerk; and
Whereas, Notices have been sent to all interested persons and public hearings held; now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works' Report, as amended at said Public Hearing, is approved and the properties therein identified are benefited; and, be it
Further Resolved, That said Commissioner of Public Works is authorized and directed to proceed with said work in accordance with said report pursuant to Section 66.0703 and any other pertinent sections of the Wisconsin Statutes and in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That the proper departments take such action as is required of them to assess the abutting or adjacent properties and collect such assessment in the manner directed by Section 115-42 of the Milwaukee Code of Ordinances; and, be it
Further Resolved, That the City Comptroller is authorized and directed to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts; and, be it
Further Resolved, That the projects do not involve any parcels of agricultural land which are eligible for deferred special assessments under the provisions of Section 14.30 of the Milwaukee City Charter; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That projects: W. Hadley St. (ST211130104), S. 24th St. (ST21110133), W. Warnimont Ave. (ST211120145), S. 51st St. (ST211030125), S. 23rd St. (ST211110109), S. Delaware Ave. (ST211120188), Alley S. Ellen St. (ST212060117), W. Clarke St. (ST211120184), N. 26th St. (ST211110185), and N. 29th St. (ST211110103) will be billed after January 1, 2014, but not before 12 months after the project contract has been completed.