Number
260985
Version
ORIGINAL
Reference
260758
Sponsor
THE CHAIR
Title
Resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $269,500 for a total estimated cost of these projects being $2,661,500.
Analysis
This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works. The City cost of the projects approved by this resolution is estimated to be $269,500. The total estimated cost of these projects is $2,661,500.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and
Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:
4th Aldermanic District
E. Summerfest Pl. - E. Erie St. to N. Harbor Dr. (SM495260016). File Number 260758: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $108,000). The total estimated cost of this project is $700,000. This project is anticipated to be completed during the 2026 construction season.
6th Aldermanic District
W. Keefe Ave. - N. 13th St. to N. 17th St. (SM495260024). File Number 260758: Relaying combined sewer. (Nonassessable Sewer Maintenance Relay Fund -- $105,000, additional funds). The total estimated cost of this project is $1,000,000. This project is anticipated to be completed during the 2027 construction season.
Citywide
2023 Indirect Account. (SM495230001) File Number 221442 (Nonassessable Sewer Maintenance Relay Fund -- $4,000, additional funds). The total estimated cost of this project including the requested amount is $404,000. These funds are needed to closeout 2023 construction season.
2024 Paving Coordination. (SM495240002) File Number 231140 (Nonassessable Sewer Maintenance Relay Fund --$1,500, additional funds). The total estimated cost of this project including the requested amount is $101,500. These funds are needed to closeout 2024 construction season.
2024 Sewer Structure Inspections. (SM495240004) File Number 231140 (Nonassessable Sewer Maintenance Relay Fund --$1,000, additional funds). The total estimated cost of this project including the requested amount is $51,000. These funds are needed to closeout 2024 construction season.
2025 Paving Coordination (SM495250002) File Number 251614 (Nonassessable Sewer Maintenance Relay Fund -- $30,000, additional funds). The total estimated cost of this project including the requested amount is $185,000. These funds are needed to closeout 2025 construction season.
2026 Paving Coordination. (SM495260002) File Number 251491 (Nonassessable Sewer Maintenance Relay Fund --$20,000, additional funds). The total estimated cost of this project including the requested amount is $220,000. This project is anticipated to be completed during the 2026 construction season.
now, therefore, be it
Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it
Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it
Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.
Requestor
Infrastructure Services Division
Drafter
Holly Rutenbeck
NFR 4
10/28/2026