Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $7,885,000 for a total estimated cost of these projects being $8,664,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

 

Number

200360

Version

SUBSTITUTE 1

Reference

181588

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $7,885,000 for a total estimated cost of these projects being $8,664,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $7,885,000.  The total estimated cost of these projects is $8,664,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

2nd Aldermanic  District

 

N. 71st St. - W. Bobolink Ave. to W. Florist Ave. (WT410200634) File Number 181588:  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $195,000). The total estimated cost of this project including the requested amount is $210,000.  This project is anticipated to be completed during the 2020 construction season.

 

N. 72nd St. - W. Bobolink Ave. to W. Florist Ave. (WT410200635) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $200,000). The total estimated cost of this project including the requested amount is $215,000.  This project is anticipated to be completed during the 2020 construction season.

 

N. 73rd St. - W. Bobolink Ave. to W. Florist Ave. (WT410200636) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $190,000). The total estimated cost of this project including the requested amount is $205,000.  This project is anticipated to be completed during the 2020 construction season.

 

5th Aldermanic District

 

W. Auer Ave. - N. 89th St. to N. 97th St. (WT410200624) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $930,000). The total estimated cost of this project including the requested amount is $970,000.  This project is anticipated to be completed during the 2020 construction season.

 

W. Hampton Ave. (southside) - N. 84th St. to N. 90th St. (WT410200644) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $615,000). The total estimated cost of this project including the requested amount is $650,000.  This project is anticipated to be completed during the 2020 construction season.

 

W. Concordia Ave. - N. 89th St. to N. 98th St. (WT410200620)  File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $905,000). The total estimated cost of this project including the requested amount is $950,000.  This project is anticipated to be completed during the 2020 construction season.

 

10th Aldermanic District

 

W. Adler St. - 60’east of S. 59th St. to S. 62nd St. (SM495200015)  File Number 191657: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund-- $235,000).   The total estimated cost of this project including the requested amount is $247,000.  This project is anticipated to be completed during the 2020 construction season.  

 

S. 64th St. - W. Main St. to W. Dickinson St. (SM495200016)  File Number 191657:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund-- $138,000).   The total estimated cost of this project including the requested amount is $150,000.  This project is anticipated to be completed during the 2020 construction season. 

 

S. 67th St. - W. Dixon St. to 300’ south of W. Dixon St. (SM495200014)  File Number 191657: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund-- $74,000).   The total estimated cost of this project including the requested amount is $86,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 76th St. - 330’ south of W. Stevenson St. to W. Stevenson St.  (SM495200019) File Number 191657: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund-- $77,000).   The total estimated cost of this project including the requested amount is $89,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 80th St. - W. Fairview Ave. to W. Stevenson St. (SM495200013)  File Number 191657:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund-- $54,000).   The total estimated cost of this project including the requested amount is $66,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 80th St. - 290’ north of W. O’Connor St. to W. O’Connor St. (SM495200020) File Number 191657:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund-- $72,000).   The total estimated cost of this project including the requested amount is $84,000.  This project is anticipated to be completed during the 2020 construction season. 

 

N. 50th St. - W. State St. to W. Juneau Ave. (SM495200025) File Number 181686: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund-- $155,000).   The total estimated cost of this project including the requested amount is $167,000.  This project is anticipated to be completed during the 2020 construction season. 

 

11th Aldermanic District

 

W. Paine St. - W. Lakefield Dr. to S. 33rd St. (WT410200626) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $180,000). The total estimated cost of this project including the requested amount is $195,000.  This project is anticipated to be completed during the 2020 construction season.

 

S. Sunset Dr. - W. Morgan Ave. to S. Massachusetts Ave. (WT410200638) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $670,000). The total estimated cost of this project including the requested amount is $700,000.  This project is anticipated to be completed during the 2020 construction season.

 

W. Tripoli Ave. - S. Massachusetts Ave. to S. 73rd St. (WT410200639) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $515,000). The total estimated cost of this project including the requested amount is $540,000.  This project is anticipated to be completed during the 2020 construction season.

 

W. Warnimont Ave. - S. 78th St. to S. 81st St. (WT410200656) Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $255,000). The total estimated cost of this project including the requested amount is $275,000.  This project is anticipated to be completed during the 2020 construction season.

 

S. 33rd St. - W. Paine St. to W. Verona Ct. (WT410200625) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $165,000). The total estimated cost of this project including the requested amount is $180,000.  This project is anticipated to be completed during the 2020 construction season.

 

S. 74th St. - W. Van Beck Ave. to W. Waterford Ave. (WT410200640) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $280,000). The total estimated cost of this project including the requested amount is $300,000.  This project is anticipated to be completed during the 2020 construction season.

 

S. 75th Ave. - W. Van Beck Ave. to W. Waterford Ave. (WT410200641) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $270,000). The total estimated cost of this project including the requested amount is $290,000.  This project is anticipated to be completed during the 2020 construction season.

 

S. 95th St. - W. Oklahoma Ave. to W. Beloit Rd. (WT410200668) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $355,000). The total estimated cost of this project including the requested amount is $375,000.  This project is anticipated to be completed during the 2020 construction season.

 

S. 98th St. - W. Oklahoma Ave. to W. Beloit Rd. (WT410200669) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $675,000). The total estimated cost of this project including the requested amount is $705,000.  This project is anticipated to be completed during the 2020 construction season.

 

12th Aldermanic District

 

W. Lincoln Ave. at S. 6th St. and at S. 16th St. (ST211200136) File Number 200359:

Install walk, curb and gutter and walk as necessary.  (Nonassessable Reconstruction Paving Fund  -- $70,000).  The total estimated cost of this project including the requested amount is $75,000.  This project is anticipated to be completed during the 2020 construction season.

 

13th Aldermanic District

 

W. Fardale Ave. - W. Loomis Rd. to S. Miner St. (WT410200618)  File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $345,000). The total estimated cost of this project including the requested amount is $365,000.  This project is anticipated to be completed during the 2020 construction season.

 

S. Miner St. - W. Fardale Ave. to W. Howard Ave. (WT410200617) File Number 181588: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0; Nonassessable Water Fund Budget Line 6410 -- $215,000). The total estimated cost of this project including the requested amount is $230,000.  This project is anticipated to be completed during the 2020 construction season.

 

City Wide

 

2020 Bioretention Maintenance Contract Stormwater Quality.  (SM499200004) Files 191657 and 191658: (Storm Water Quality - Nonassessable Water Quality Projects to meet TMDL Requirements -- $50,000, additional funds).  The total estimated cost for this project including the requested amount is $345,000. The project is anticipated to be completed in 2020.

 

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 