Title: Resolution directing the Commissioner of Public Works to execute a revised project agreement titled “State/Municipal Agreement for a State-Let Highway Improvement Project”, with the Wisconsin Department of Transportation, for the improvement of North Mayfair Road (STH 100) from West Burleigh Street to West Silver Spring Drive, including West Silver Spring Drive from North Mayfair Road (STH 100) to North 118th Court, with Federal and State aid, under the State Trunk Highway Improvement Program; with an estimated total cost of $10,322,000, which is an increase of $3,450,000 and a total estimated City share of $121,000, which is an increase of $10,500.
Sponsors: THE CHAIR
Indexes: INTERGOVERNMENTAL AGREEMENTS, STREET IMPROVEMENTS, WISCONSIN DEPARTMENT OF TRANSPORTATION
Attachments: 1. Revised Agreement, 2. Comptroller's Certificate, 3. Hearing Notice List

Number

120234

Version

ORIGINAL

Reference

Sponsor

THE CHAIR

Title

Resolution directing the Commissioner of Public Works to execute a revised project agreement titled “State/Municipal Agreement for a State-Let Highway Improvement Project”, with the Wisconsin Department of Transportation, for the improvement of North Mayfair Road (STH 100) from West Burleigh Street to West Silver Spring Drive, including West Silver Spring Drive from North Mayfair Road (STH 100) to North 118th Court, with Federal and State aid, under the State Trunk Highway Improvement Program; with an estimated total cost of $10,322,000, which is an increase of $3,450,000 and a total estimated City share of $121,000, which is an increase of $10,500.

Analysis

This resolution directs the Commissioner of Public Works to execute a revised project agreement with the Wisconsin Department of Transportation for the improvement of North Mayfair Road (STH 100) from West Burleigh Street to West Silver Spring Drive, including West Silver Spring Drive from North Mayfair Road (STH 100) to North 118th Court. This project is approved and included in the Wisconsin Department of Transportation current State Trunk Highway Improvement Program. The City of Milwaukee is responsible for 0% of the preliminary engineering costs. City cost associated with Plan review and developments are 100% responsibility of the City of Milwaukee. City costs for the participating portion of construction for this project will be dependent upon the amount of parking allowed. The estimated total cost of this project is $10,322,000, of which the City’s share is $121,000 and the grantor’s share is $10,201,000.

Body

Whereas, A project agreement has been executed by the Wisconsin Department of Transportation and the City of Milwaukee for the improvement of North Mayfair Road (STH 100) from West Burleigh Street to West Silver Spring Drive, including West Silver Spring Drive from North Mayfair Road to North 118th Court, with Federal /State aid under the State Trunk Highway Improvement Program, in accordance with the Common Council resolution file number 091564 adopted April 13, 2010; and

 

Whereas, The Wisconsin Department of Transportation, has approved adding the section of West Silver Spring Drive from North Mayfair Road (STH 100) to North 118th Court; resulting in a increase in estimated construction costs from the original agreement; and

 

Whereas, A revised project agreement with the updated project costs has been received from the Wisconsin Department of Transportation, to be executed by the City of Milwaukee, under the State Trunk Highway Improvement Program; and

 

Whereas, Construction funds for the project will be included in a separate resolution; now, therefore, be it

Resolved, By the Common Council of the City of Milwaukee, that the Commissioner of Public Works is hereby authorized to execute a revised project agreement for the improvement of W North Mayfair Road (STH 100) from West Burleigh Street to West Silver Spring Drive, including West Silver Spring Drive from North Mayfair Road (STH 100) to North 118th Court, under the State Trunk Highway Improvement Program; be it

Further Resolved, That the City Comptroller is hereby authorized to transfer to the appropriate accounts the amount required under the grant agreement and City Accounting Policy but not to exceed a 10% increase of the total amounts reserved for the grantor’s share and local share or $5,000, whichever is greater, as follows:

 

Infrastructure Services Division

State I.D. 2030-09-00

ST320100401- North Mayfair Road (STH 100)

West Burleigh Street to West Silver Spring Drive,

Including West Silver Spring Drive

North Mayfair Road (STH 100) to North 118th Court

 

City Share Non-Assessable Paving

ST320120000

Fund 0333

$10,000.00

 

Construction is scheduled for 2014

 

Previously authorized for City plan review and development: $30,000.00

Current estimated cost of total project including this resolution: $10,362,000.00

Original estimated cost of the total project (Resolution 091564): $6,902,000.00

 

Resolution total: $10,000.00

 

; and, be it

 

Further Resolved, That the City Engineer is hereby authorized to approve and make periodic payments to the Wisconsin Department of Transportation, upon receipt of invoices, for the City of Milwaukee’s share of the costs to the project; be it

 

Further Resolved, A copy of the revised project agreement is attached to Common Council resolution file number 120234, and is incorporated into this resolution by reference as though set forth in full.

Requestor

Department of Public Works

Drafter

Infrastructure Services Division

LCG: ns