Number
13561
Version
Original
Reference
Sponsor
The Chair
Title
Resolution approving an award of contract to Selzer-Ornst Construction Company (Milwaukee, WI) for elevator modernization at Lincoln Court, in the amount of $884,662.00 (Official Notice 58148)
Analysis
Body
WHEREAS, the Housing Authority of the City of Milwaukee (Housing Authority) solicited sealed bids by Official Notice Number 58148 during the period January 10, 2025 through January 31, 2025 for Elevator Modernization at Lincoln Court; and
WHEREAS, two (2) sealed bids were received by the deadline of 2:00 PM CST on January 31, 2025; and
WHEREAS, the sealed bids were received and publicly opened on January 31, 2025, during which the bidding procedure was conducted in compliance with the requirements of local, state, and federal regulations; and
WHEREAS, Selzer-Ornst Construction Company, a qualified and competent bidder, submitted the lowest responsive and responsible bid in the amount of $884,662.00; therefore, be it,
RESOLVED, by the Commissioners of the Housing Authority that they hereby authorize and approves accepting the bid of and entering into a contract with Selzer-Ornst Construction Company for Elevator Modernization at Lincoln Court; and, be it
FURTHER RESOLVED, that funds for these services will come from the CFP 2023; and, be it
FURTHER RESOLVED, that the proper officers of the Housing Authority be and hereby are authorized and directed to properly execute said contract for and on behalf of the Housing Authority; and, be it
FURTHER RESOLVED, that if any change orders including the time of performance are needed, the Chairman and Acting Secretary-Executive Director may approve such request without any further action of the Commissioners of the Housing Authority; and, be it
FURTHER RESOLVED, that all of above is contingent upon receiving the approval of the U.S. Department of Housing and Urban Development, if required; and, be it
FURTHER RESOLVED, that all acts p...
Click here for full text