| | 3. | | Project Status
Minutes note: - Recent Activity
Progressed Final design for Mainline and OMF
Conducted Project meetings
Continuted Utility Coordination
Lakefront line design 30% complete
Completed WaterWorks Construction
TIGER grant applied for on April 29, 2016
Onbainted Categorical Exclusion on Lakefront Line on May 17th
- 90 Day Look Ahead
Select and Enageg CM/GC for pre-construction services
Hold CM design workshops and schedule development
Continue Private and Public Utility coordination and design
PSC review of Gas & Steam for We Energies
Update Project Management plan and sub-plans
Finalize Draft Financial Plan
Conduct project design, ultility, and vehicle engineering meetings
Continue with 60% design completion for Lakefront line extension
- Tentative Phase 1 Project Schedule
Reevalutating schedule for OMF and Mainline (roadway, trackwork, systems/Overhead Contact System)
Create baseline schedule upon CM/GC selection and input
Revenue Service 2018
- Budget Status
A total of $49.89 Million has been spent through May 2016 | | | |
|
Not available
|
| | 4. | | Utility Coordination
Minutes note: We Energies Electric Relocation work is ongoing and high impact pedestrian areas are re-opened for summer season
A Single Reimbursement Agreement on behalf of all Telecoms is being negotiated, with scope and budget being negotiated individually
All water work has been completed
AT&T work began June 9th
Employee Support for Business Program utility related work | | | |
|
Not available
|
| | 5. | | Vehicle Procurement
Minutes note: Executed contract with Brookville Equipment Corp in November 2015
Brookville site visit took place in April 2016
Spare parts consortium meeting with Detroit, Oklahoma City, and Dallas
Executed Contract Option for Lakefront line vehicle in May 2016
Anticipated delivery of first vehicle in December 2017
Conduct biweekly vehicle engineering meetings | | | |
|
Not available
|
| | 6. | | Contract Procurement
Minutes note: Procurement Timeline
RFP issued April 18th
Pre-proposal Meeting May 3rd
Proposal Submissions June 1st
Contractor Interviews June 2016
Notify Selected Contractor June 2016
Issue Notice to Proceed June 2016 | | | |
|
Not available
|
| | | | Matters related to this Committee can be found in the following file: | | | |
|
Not available
|
141879
| 0 | | Communication | Communication relating to the activities and report of the Joint Committee on Downtown Streetcar Implementation. | | | |
Action details
|
Not available
|