powered help
header-left header-center header-right
File #: 110689    Version:
Type: Resolution Status: Passed
File created: 9/20/2011 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 10/11/2011
Effective date:    
Title: Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $128,000 for a total estimated cost of $135,200.
Sponsors: THE CHAIR
Indexes: ALLEY IMPROVEMENTS, PUBLIC IMPROVEMENTS
Attachments: 1. Cover Letter, 2. Official Notice Number 26 Committee Actions, 3. Official Notice Number 26, 4. Hearing Notice List, 5. Notice Published on 10-27-11
Number
110689
Version
SUBSTITUTE 1
Reference
110161
Sponsor
THE CHAIR
Title
Substitute resolution approving levying of assessments and construction of assessable public improvement projects at various locations and appropriating funds for these purposes with the City cost of these projects approved by this resolution is estimated to be $128,000 for a total estimated cost of $135,200.
Analysis
This resolution confirms the report of the Commissioner of Public Works, as modified by the Common Council Committee, on projects for which Public Hearings have been held. The resolution authorizes the levying of special assessments and directs the installation and construction of said public improvements. The City cost of these projects approved by this resolution is estimated to be $128,000. The total estimated cost of these projects is $135,200.
Body
Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions, determining it necessary and in the public interest to construct and levy special assessments for the following improvements:

5th Aldermanic District

Alley between W. Appleton Ave., W. Congress St., W. Ruby Ave., and N. 80th St. (ST212120102) File Number 110161: Concrete alley pavement reconstruction, replace some abutting walk or driveway approaches, grading, and storm drainage facilities where necessary. (Assessable Alley Paving Fund -- $32,800; Nonassessable Alley Paving Fund -- $85,000). The total estimated cost for this project including the requested amount is $125,000. This project is anticipated to be completed during the 2012 construction season and funded with the 2012 budgeted funds.

6th Aldermanic District

N. Hubbard St. - E. Meinecke Ave. to E. Wright St. (ST211110158): Install traffic calming speed hump(s). (Assessable Reconstruction Paving Fund -- $7,200; Nonassessable Reconstruction Paving Fund -- $3,000). The total estimated cost for this project including the requested amount is $10,200. This proje...