Resolution authorizing the City Comptroller to transfer additional funds to the previously established project for the Wisconsin Department of Transportation and the City of Milwaukee for cost participation for the construction of the North Holton Street Bridge over the Milwaukee River, North Commerce Street, and North Water Street in Aldermanic District 3 and 6 with a total cost increase for the project of $2,719,816.31, with a Grantor share of $1,719,666.90 and a City share of $1,000,149.41.
Analysis
Body
Whereas, Additional funds are, therefore, necessary to complete the construction of the projects; now, therefore be it
Resolved, By the Common Council of the City of Milwaukee, that the City Comptroller is hereby authorized to transfer funds to the project grant chart field as follows:
Project Grant Value
State ID 2984-12-73
BR320201110 and ST320201110
North Holton Street Bridge over
Milwaukee River, North Commerce Street, North Water Street
City Share Non-Assessable Fund, Structure
BR300230000
Fund 0303
$738,323.38
Grantor Reimbursable Fund, Structure
SP032230100
$155,067.54
Grantor Non-Reimbursable Fund Structure
$1,033,783.26
City Share Non-Assessable Fund Paving
ST320230000
Fund 0333
$261,826.03
Grantor Reimbursable Fund Paving
SP032230100
Fund 0306
$69,236.93
Grantor Non-Reimbursable Fund Paving
$461,579.17
Estimated Total - $2,719,816.31
Total construction previously authorized $5,258,605.57
Current estimated cost of total project including the resolution: $7,978,411.88
Original estimated cost of the project (File Number 200576): $4,967,681