powered help
header-left header-center header-right
File #: 210456    Version: 0
Type: Resolution Status: Passed
File created: 7/7/2021 In control: PUBLIC WORKS COMMITTEE
On agenda: Final action: 7/27/2021
Effective date:    
Title: Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $437,000 for a total estimated cost of these projects being $9,065,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

Number
210456
Version
ORIGINAL
Sponsor
THE CHAIR
Title
Resolution determining it necessary to make various nonassessable public improvements at various locations and appropriating funds for these purposes with the City engineering cost estimated to be $437,000 for a total estimated cost of these projects being $9,065,000.
Analysis
This resolution authorizes engineering studies on projects which by City Charter are nonassessable. After design plans and estimates of costs have been prepared, a resolution authorizing construction will be submitted to the Common Council. The City cost for engineering these projects is estimated to be $437,000 with the total cost estimated to be $9,065,000.
Body
Resolved, By the Common Council of the City of Milwaukee, that it is necessary and in the public interest to do the following described improvements according to City specifications:


1st and 7th Aldermanic Districts

N. 35th St. - W. Capitol Dr. to W. Congress St. (SM497210303) Installing new storm sewer. (Flood Mitigation - Nonassessable --$175,000). The total estimated cost of this project including the requested amount is $5,267,000. This project is anticipated to be completed during the 2023 construction season.

W. Capitol Dr. - N. 31st St. to N. 35th St. (SM497210304) Installing new storm sewer. (Flood Mitigation - Nonassessable -- $250,000). The total estimated cost of this project including the requested amount is $3,712,000.This project is anticipated to be completed during the 2023 construction season.

10th Aldermanic District

S. 90th St. - W. Adler St. to 340’ +/- south of W. Adler St. (SM495210038) Relaying sanitary sewer. Sanitary sewer lining. (Nonassessable Sewer Maintenance Relay Fund -- $12,000). The total estimated cost of this project including the requested amount is $86,000.This project is anticipated to be completed during the 2022 construction season.

;and, be it

Further Resolved, That all City Departments are authorized to p...