powered help
header-left header-center header-right
File #: 210305    Version:
Type: Resolution Status: Passed
File created: 6/15/2021 In control: COMMON COUNCIL
On agenda: Final action: 7/7/2021
Effective date:    
Title: Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $5,541,000 for a total estimated cost of these projects being $5,922,000.
Sponsors: THE CHAIR
Indexes: PUBLIC IMPROVEMENTS

 

Number

210305

Version

Substitute 1

Reference

191786

Sponsor

THE CHAIR

Title

Substitute resolution approving construction of nonassessable public improvements at various locations and appropriating funds for these purposes with the City construction cost estimated to be $5,541,000 for a total estimated cost of these projects being $5,922,000.

Analysis

This resolution directs the installation and construction of certain public improvements which have been determined to be nonassessable by the Commissioner of Public Works.  The City cost of the projects approved by this resolution is estimated to be $5,541,000.  The total estimated cost of these projects is $5,922,000.

Body

Whereas, The Common Council of the City of Milwaukee adopted preliminary resolutions determining it necessary and in the public interest to construct nonassessable improvements; and

 

Whereas, Plans, specifications and cost estimates have been prepared for the following described improvements:

 

2nd Aldermanic District

 

W. Rio St. - N. 95th St. to N. Denmark St. (WT410210685) File Number 191786: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $215,000).  The total estimated cost of this project including the requested amount is $230,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 95th St. - W. Rio St./N. 95th St. to W. Fond du Lac Ave. (WT410210683)  File Number 191786:  Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $250,000).  The total estimated cost of this project including the requested amount is $270,000.  This project is anticipated to be completed during the 2021 construction season. 

 

4th Aldermanic District

Alley betw. W. Clybourn St., W. St Paul Av., N. 28th St., N. 29th St. (new e/w leg to N. 29th St.) (MKE playground)( ST212180117) File Number 190519: Concrete alley construction. (Nonassessable Alley paving fund -- $35,000 additional funds) This project was completed in 2020 and the funds are needed to close out the contract.

 

5th Aldermanic District

 

W. Grantosa Dr. - N. 92nd St to N. 100th St (portions in the City of Wauwatosa) (ST214210102) Pavement marking (Nonassessable Developer Fund- $10,000) The total estimated cost of the work in the City of Wauwatosa is $10,000. The project is anticipated to be completed during the 2021 construction season.

 

6th Aldermanic District

 

W. Abert Pl. - N. 3rd St. to 200’ west of N. 3rd St. (SM495210028) File Number 201669: Relaying storm sewer. (Nonassessable Sewer Maintenance Relay Fund -- $53,000). The total estimated cost for this project including the requested amount is $63,000.  This project is anticipated to be completed during the 2021 construction season.    

 

N. Killian Pl. - E. Reservoir Ave. to E. Brown St. (WT410210619) File Number 191657: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $130,000).  The total estimated cost of this project including the requested amount is $145,000.  This project is anticipated to be completed during the 2021 construction season. 

 

E. Reservoir Ave. - N. Hubbard St. to N. Buffum St. (WT410210618)  File Number 191657: Relaying water main.  (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $125,000).  The total estimated cost of this project including the requested amount is $140,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 2nd  St. - 300’ south of W. Hadley St. to W. Hadley St. (SM495200052)  File Number 201139: Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $79,000).  The total estimated cost of this project including the requested amount is $91,000.  This project is anticipated to be completed during the 2021 construction season.

 

N. 23rd St. - W. Nash St. to W. Vienna Ave. (SM495200044)  File Number 200922: Relaying storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $184,000).  The total estimated cost of this project including the requested amount is $196,000.  This project is anticipated to be completed during the 2021 construction season.

 

10th Aldermanic District

 

N. 58th St. - W. Vine St. to 450+/- north of W. Vine St. (SM495200026) File Number 200229:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $109,000).  The total estimated cost of this project including the requested amount is $121,000.  This project is anticipated to be completed during the 2021 construction season.

 

N. 95th St. - 325’ south of W. St. Paul Ave. to 100’ north of W. St. Paul Ave. (SM495200040) File Number 200817:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $91,000).  The total estimated cost of this project including the requested amount is $103,000.  This project is anticipated to be completed during the 2021 construction season.

 

11th Aldermanic District

 

S. Athens St. - W. New Jersey Ave. to W. Crawford Ave. (SM495210019) File Number 201669: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $299,000). The total estimated cost for this project including the requested amount is $311,000.  This project is anticipated to be completed during the 2021 construction season.   

 

W. Nebraska Ave. - S. 61st St. to S. 63rd St.  (SM495210020) File Number 201669: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $251,000). The total estimated cost for this project including the requested amount is $263,000.  This project is anticipated to be completed during the 2021 construction season.    

 

W. New Jersey Ave. - S. 81st St. to S. 83rd St.  (SM495210018) File Number 201669: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $112,000). The total estimated cost for this project including the requested amount is $124,000.  This project is anticipated to be completed during the 2021 construction season.

 

 W. Tripoli Ave. - S. 85th St. to S. 87th St.  (SM495210021) File Number 201669: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $134,000). The total estimated cost for this project including the requested amount is $146,000.  This project is anticipated to be completed during the 2021 construction season.    

 

W. Warnimont Ave. - S. 84th St. to S. 87th St.  (SM495210026)  File Number 201669: Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $322,000). The total estimated cost for this project including the requested amount is $337,000.  This project is anticipated to be completed during the 2021 construction season.    

 

S. 40th St. - W. Oklahoma Ave. to W. Euclid Ave. (SM495210027) File Number 201669: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $168,000). The total estimated cost for this project including the requested amount is $180,000.  This project is anticipated to be completed during the 2021 construction season.    

 

S. 81st St. - W. Morgan Ave. to W. Warnimont Ave. (SM495210016) File Number 201669:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $166,000). The total estimated cost for this project including the requested amount is $178,000.  This project is anticipated to be completed during the 2021 construction season.    

 

S. 83rd St. - W. Wilbur Ave. to W. New Jersey Ave. (SM495210017) File Number 201669:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $50,000). The total estimated cost for this project including the requested amount is $60,000.  This project is anticipated to be completed during the 2021 construction season.    

 

S. 85th St. - W. Warnimont Ave. to 350’ south of W. Warnimont Ave. (SM495210025) File Number 201669:  Relaying storm sewer.  Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $171,000). The total estimated cost for this project including the requested amount is $183,000.  This project is anticipated to be completed during the 2021 construction season.    

 

S. 85th St. - W. Warnimont Ave. to W. Wilbur Ave. (SM495210022) File Number 201699:  Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $264,000). The total estimated cost for this project including the requested amount is $276,000.  This project is anticipated to be completed during the 2021 construction season.    

 

S. 86th St. - W. Warnimont Ave. to 300’ south of W. Warnimont Ave. (SM495210024)  File Number 201669: Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $229,000). The total estimated cost for this project including the requested amount is $241,000.  This project is anticipated to be completed during the 2021 construction season.    

 

S. 86th St. - W. Warnimont Ave. to W. Wilbur Ave. (SM495200075)  File Number 201139: Relaying sanitary sewer. (Nonassessable Sewer Maintenance Relay Fund -- $139,000). The total estimated cost for this project including the requested amount is $151,000.  This project is anticipated to be completed during the 2021 construction season.   

 

S. 87th St. - W. Warnimont Ave. to W. Crawford Ave. (SM495200074)  File Number 201669: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $375,000). The total estimated cost for this project including the requested amount is $390,000.  This project is anticipated to be completed during the 2021 construction season.    

 

S. 87th St. - W. Warnimont Ave. to W. Wilbur Ave. (SM495210023)  File Number 201669: Installing new storm sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $256,000). The total estimated cost for this project including the requested amount is $268,000.  This project is anticipated to be completed during the 2021 construction season.    

 

S. 88th St. -W. Wilbur Ave. to W. Crawford Ave. (SM495210011) File Number 201345: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $135,000). The total estimated cost for this project including the requested amount is $147,000.  This project is anticipated to be completed during the 2021 construction season. 

 

12th Aldermanic District

 

S. 19th St. - W. Windlake Ave. to W. Cleveland Ave. (SM495210013) File Number 201345: Relaying sanitary sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $100,000). The total estimated cost for this project including the requested amount is $112,000.  This project is anticipated to be completed during the 2021 construction season. 

 

15th Aldermanic District

 

W. Clarke St. - N. 9th St. to N. 10th St. (SM495200043) File Number 200922: Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $90,000).  The total estimated cost of this project including the requested amount is $102,000.  This project is anticipated to be completed during the 2021 construction season.

 

N. 9th St. - W. Locust St. to W. Burleigh St. (SM495200062) File Number 201139:  Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $279,000).  The total estimated cost of this project including the requested amount is $294,000.  This project is anticipated to be completed during the 2021 construction season.

 

N. 30 th St. - W. Cherry St. to W. Walnut St. (WT410210612) File Number 191657:  Relaying water main.  Lead Replacement of Service (Nonassessable Water Fund Budget Line 5010 -- $0.  Nonassessable Water Fund Budget Line 6410 -- $410,000).  The total estimated cost of this project including the requested amount is $430,000.  This project is anticipated to be completed during the 2021 construction season. 

 

N. 45th St. - W. Meinecke Ave. to W. Clarke St. (SM495210012) File Number 201669: Relaying combined sewer.  (Nonassessable Sewer Maintenance Relay Fund -- $310,000). The total estimated cost for this project including the requested amount is $325,000.  This project is anticipated to be completed during the 2021 construction season. 

 

 

now, therefore, be it

 

Resolved, By the Common Council of the City of Milwaukee that the Commissioner of Public Works is authorized and directed to proceed with said work; and, be it

 

Further Resolved, That the Department of Public Works is authorized to use the funding as specified in the above description of work; and, be it

 

Further Resolved, That the City Comptroller is authorized to transfer such funds which are available for this purpose to the appropriate capital Project/Grant accounts.

 

Requestor

Infrastructure Services Division

Drafter

Mary Dziewiontkoski/dl

Nfr14 Sub

06/16/2021